Why Repeatable Procedures?

Why Repeatable Procedures?

“My maintenance staff are highly trained and do not like using procedures. " --- Unnamed Maintenance Supervisor"

If the statement above is valid, and the cost of asset failure is not important to our operation, then your staff must have an unlimited and infallible memory – congratulations!

Human error rate is high and thus without repeatable, effective maintenance procedures create errors which are called failures. Maintenance professionals actually think procedures are not required because they “know how to do it”.

However, this couldn’t be further from the truth. Over our careers we have seen thousands of examples of human variation creating equipment failure. We as humans are built to produce variation in almost everything we do.

Most people deny this human variation exists. However, when managers are asked if they ever could not find their car keys, they look at me sheepishly and say, “Yes, great point”. Many companies honestly believe their maintenance staff members are paid to “know how to do it” without a procedure with specifications, step by step instructions, etc. What if a maintenance employee does “know how to do it” every time?

One must take into consideration skill level, current state mind, and current working condition, in order to mitigate human error. In addition, what would happen if new information presented itself based on failure data? The only way to ensure this new information is used effectively would be to write or change a procedure.

Well-designed maintenance procedures and a solid procedures feedback and follow-up process will mitigate human induced failures and allow for continuous improvement to occur naturally. If a company wants to optimize asset reliability then repeatable, effective procedures cannot be optional. Did you know that the most complex equipment ever built was a nuclear submarine and that the first nuclear submarines experienced failures due to lack of effective procedures, thus ending in catastrophic failure?

If safety is number one in your organization, then repeatable, effective work procedures should be as well. Figure #1 shows the correlation between injury rate and OEE.

No alt text provided for this image

We may not know why the bearing in Figure 2 failed. It is easy to surmise that the correct lubricant, quantity, and re-lubrication interval were likely not clearly specified in the maintenance instructions related to the equipment.

No alt text provided for this image
Firgure 2 - Bearing Failed due to "Lack of Lubrication

In the field of maintenance, the traditional approach has been to rely upon the intuitive knowledge and skill of the craftspeople who conduct it. There is a corollary that accompanies all of this that many skilled craftspeople believe and would like management to believe firmly, “There are too many variables in maintenance, making compliance with written procedures impossible and impractical, that the ’way we’ve always done it’ is the best and only way to conduct maintenance.”

The bottom line is effective, repeatable procedures are a requirement if a company wants a true continuous improvement process for optimizing asset reliability then repeatable procedures cannot be optional.

There is a big problem when moving from current state to this future of repeatable, effective procedures and that is change. Change is not easy. Here are proven steps to success in this area:

  1. Send a few hard-core individuals to be trained in developing repeatable, effective procedures ("Maintenance and Reliability Best Practices"). Be sure they will come back excited so select the right training.
  2. .Upon return from the training sit down with the employees who received the training and work with them to develop a plan to move from current state to future state with effective, repeatable procedures.
  3. Be sure this plan has imbedded the following items:

a. Training for maintenance technicians, planners, supervisors, managers, reliability and maintenance engineers (2-4 hours for most)

b. Develop a process map for procedure development and approval along with defining roles and responsibilities.

No alt text provided for this image

Figure 3 - Process Map for Creating Procedures

No alt text provided for this image

Figure 4: Roles and Responsibilities for Creating Procedures

There is really no valid excuse, today, for not moving towards procedure-based maintenance. The basic conclusion is worth repeating. The more detailed the procedures and the more insistence on compliance with procedures an organization becomes, the more precise and less error prone its maintenance will become. The result will be an increase in reliability to as close to the limit that design, and other factors will permit.

If one makes the decision to not use effective, repeatable procedures you must prepared to accept the consequences of this action which would be higher equipment failure, higher maintenance cost, along with higher safety and environmental risk.

Developing effective, repeatable procedures is the only choice an organization has if it wants to mitigate risk and invoke continuous improvement into the reliability of its assets.

Mitigate human induced failure and optimize reliability and cost through the use of effective, repeatable preventive, predictive and corrective maintenance and operator-care procedures.

Questions?

  1. Does anyone know the hydraulic fluid micron level required for their hydraulic systems?
  2. Are PMs executed with PM variation? For example, a 30-day PM may be accomplished on the3rd of the month this month and on the 20th of the month next month, resulting in equipment problems. PM is a “controlled experience” and, as such, requires repeatable, effective, and on-time procedures. (See Figure 3.)

No alt text provided for this image

Figure 3: PM Balancing

No alt text provided for this image

A repeatable maintenance procedure is a detailed list of steps that describes how to perform a maintenance task and is also a documented standard to which the job or task should be performed.

No alt text provided for this image

Like a copy of this article go to my website at: https://worldclassmaintenance.org/articles-of-the-week

Mick Woodcock

Retired Manufacturing and Services Manager.

2 年

An excellent read. Maintenance managers need to really focus on standardisation and process feedback. The days of "We know best" are gone. Thankyou.#reliabilitycenteredmaintenance

回复
Subhakar Chaganti

Asset Integrity (Rotating Equipment) Engineer - SBM OFFSHORE

2 年

Also it is important to periodically review & update these procedures by including the lessons learned during previous maintenance actions,RCA recommendations if any, updates from OEM etc.

回复
Cristiam Kechinski

Manufacturing / Operations / Maintenance

2 年
回复
Jason Rider

Plant Engineering

2 年

One method I have used in larger facilities especially in multiple shift locations; I divide lines or even machines to separate books-folders. I do RCA’s of failures. I record date/time type of failure, then put description in book with failure type as lead page. This allows any mechanic/shift/supervisor to look up when we have a repeat offender, the RCA is done and at least gives everyone an explanation if not a heads start if not identicle. This way you do not reinvent the wheel so to speak.

John Rollo, EIT

Automation, Controls, and Instrumentation Engineer

2 年

One of the more entertaining endeavors of my career.. How do you create a repeatable test plan/calibration method for tuning vibrators for gummy bear material handling.

要查看或添加评论,请登录

Ricky Smith CMRP, CMRT, CRL的更多文章

  • Day in the Life of a Proactive Maintenance Supervisor

    Day in the Life of a Proactive Maintenance Supervisor

    "Based on real life experience by Ricky Smith CMRP, CMRT" "Maintenance Supervisors are truly unsung heroes who seek no…

    7 条评论
  • Day in the Life of a Proactive Maintenance Manager

    Day in the Life of a Proactive Maintenance Manager

    With respect to maintenance and reliability, the definition for proactive is: ?To act before the cost of doing so…

    14 条评论
  • Six Tips for Optimizing a Preventive Maintenance Program

    Six Tips for Optimizing a Preventive Maintenance Program

    PM Tip No. 1: Measure the effectiveness of your PM Program.

    11 条评论
  • Maintenance Best Practices

    Maintenance Best Practices

    By John Day, Engineering/Maintenance Manager Alumax Mt Holly A best practice is a method or technique that has been…

    2 条评论
  • Why Maintenance Procedures are Critical

    Why Maintenance Procedures are Critical

    by Ricky Smith CMRP, CMRT “My maintenance staff are highly trained and do not like using procedures.” -Unnamed…

    5 条评论
  • 11 Attributes of a Proactive Maintenance Supervisor

    11 Attributes of a Proactive Maintenance Supervisor

    "Attribute Definition: a quality or feature regarded as a characteristic or inherent part of someone"…

    4 条评论
  • Benefits of Maintenance Planning and Scheduling

    Benefits of Maintenance Planning and Scheduling

    1. Production Schedule is Optimized 2.

    1 条评论
  • Day in the Life of a Proactive Maintenance Supervisor

    Day in the Life of a Proactive Maintenance Supervisor

    "Based on real life experience by Ricky Smith CMRP, CMRT“as a Maintenance Supervisor, Maintenance Manager, etc…

    6 条评论
  • Total Productive Maintenance

    Total Productive Maintenance

    TPM is a company-wide equipment maintenance system involving all employees–from top management to production line…

    2 条评论
  • MTBF Users Guide

    MTBF Users Guide

    Most companies do not measure Mean Time Between Failure (MTBF). Yet, it is one of the first and most basic measurements…

    16 条评论

社区洞察

其他会员也浏览了