Why the EVM Schedule Indicators Are NOT Reliable!
Shohreh Ghorbani
Founder & Technical Director, Project Control Academy | I help you master your knowledge and skills in Project Controls, so you become the HERO ?? of your projects.
“Your critical path schedule shows behind schedule. How come your EVM schedule performance indicates an ahead of schedule status?”
“What is wrong with your SPI report?”
“We are going to finish this project 3 months behind the schedule. Tell me why your SPI is showing a good schedule performance?”
Have you ever faced an angry customer or a project manager screaming, “what is wrong with your EVM schedule performance report?” We are late and yet show me good schedule performance? What is going on here?!
Earned Value Management has proven itself to be one of the most efficient performance measurement and feedback tools for managing projects, as outlined in PMI Practice Standard for Earned Value Management
However, EVM implementation and interpretation may cause some difficulties to those who are new to the EVM concept or doesn’t have a deep understanding and appreciation of EVM.
A gray area in EVM that has created lots of debates and dilemmas is the EVM scheduling metrics; Schedule Performance Index (SPI), and Schedule Variance (SV).
In this video training, I would like to make you aware of the issues with the EVM scheduling metrics especially toward the final third of the project, so next time you are faced with an angry client questioning the accuracy of your EVM report, you know how to respond.
EVM Scheduling Metrics:
EVM uses two primary schedule performance indicators to evaluate the schedule status:
- Schedule Performance Index (SPI)
- Schedule Variance (SV)
To calculate these scheduling metrics, you need to have two key elements in EVM; “Planned Value” & “Earned Value”.
Planned Value (PV):
Planned Value, also known as Performance Measurement Baseline, is the project’s time-phased budget resulted from the project planning effort.
Your total Planned Value should always match your total approved progress based budget.
Earned Value (EV):
Earned Value is the value of your accomplishments; the value of what has been actually accomplished in the project.
Earned Value is determined as the physical percentage of your budget
EV= % x Budget
Once you have EV and PV, you can determine the SPI and SV.
Schedule Performance Index (SPI)
The Schedule Performance Index (or SPI) is a measure of schedule efficiency.
SPI measures the value of work performed against the work scheduled.
The formula for the Schedule Performance Index is “Earned Value” divided by “Planned Value.”
SPI= EV/PV
Schedule Variance (SV)
The schedule variance (SV) determines whether a project is ahead of or behind schedule in accomplishing work.
The Schedule Variance is the difference between the “Earned Value” and the “Planned Value”.
SV= EV-PV
To better understand these metrics, let’s walk through a simple example:
In this example, Earned Value is $300, and Planned Value is $430. What is the Schedule Performance Index (SPI)?
SPI= EV/PV= $300/$430= 0.7
The SPI of 0.7 indicates that work is being accomplished at 70% of its planned rate. In another word, on average for every 8 hours per day working on the project, only 5 hours and 35 minutes worth of the planned work is being performed.
How about the Schedule Variance (SV)?
SV= EV-PV= $300-$430= -$130 (SV<0)
What SPI or SV Indicate
As illustrated in the previous example,
- If SPI<1 (or SV<0), less work is completed than planned (“Behind” schedule)
- If SPI>1 (or SV>0), more work is completed than planned (“Ahead” of schedule)
- If SPI=1 (or SV=0), the project is “on schedule”
The ahead or behind schedule interpretation of the EVM scheduling metrics comes with a big warning!
SPI/ SV Warning
Please be advised that an unfavorable SPI or SV does not necessarily mean a schedule slippage. On the other hand, a favorable SPI or SV does not necessarily indicate an ahead of schedule status.
Schedule variance is very often misinterpreted as a time-based indicator, for example, are we early or late and by how much?
SV & SPI are not time-based indicators, but rather an indication of the physical status (how much of the work has been accomplished).
EVM Scheduling metrics show whether less or more work has been accomplished than planned.
What SPI shows is the dollar value of the work completed for every dollar of work scheduled. For example, a SPI of 0.95 means that for every dollar of work scheduled for completion, only 95 cents worth of work was actually completed.
EVM measures the schedule performance not in units of time, but rather in cost.
Do you remember the example brought earlier? The schedule variance (SV) was -$130.
The point is that SPI & SV are independent of the Critical Path Schedule.
A schedule slippage can only be determined by evaluating the critical path network.
Another issue with the EVM scheduling indicators happens toward the end of the project.
SPI & SV are not very reliable metrics in assessing the schedule status of the project toward the end of the project.
I know you might be thinking “why”??... What is happening at toward the end of the project that makes the EVM scheduling metrics unreliable?!
To show you the reason why let’s do a quick trend analysis on SPI:
This is an example of a project that is behind the schedule, according to EVM scheduling metrics (EV<PV):
If you draw the SPI curve over time, how would it look like?
Well, Earned Value is less than Planned Value, therefore Schedule Variance is negative and SPI is less than one. With this performance, the schedule slippage is also predicted.
Therefore, if you plot SPI from the beginning of the project up to now, it will look something like this graph:
What is your opinion about the SPI graph from “time now” until the end of the project?
Would it further decline or improve?
How about the SPI at the end of the project?
To answer this question, let’s first examine what SPI will be at the end of the project.
SPI= EV/PV
EV= % x Budget at Completion
At the end of the project,
Progress is 100%, therefore;
EV= 100%x BAC= BAC
Your total Planned Value should always match your total approved progress based budget. Therefore, at the end of the project,
PV= BAC
As a result, at the end of the project,
- EV= PV= BAC
- SV= 0
- SPI=1
Therefore, at some point in time, all SPI curves will level off, then make their way back up to ultimately touch the one line when the actualized work has been completed.
Although the project may be late compared to the original baseline plan, at project completion there will be no schedule variances!
Now the question is whether the increase in SPI toward the end of the project is an indication of project schedule improvement or a false indication?
Schedule Performance at completion is ONE by definition, even if the project is completed late!
Now, are you convinced why the EVM scheduling metrics are not reliable especially toward the 2/3rd of the project?
As stated by a report from the Department of Defense, “an SPI or Schedule Variance is stated in terms of dollars of work and must be analyzed in conjunction with other schedule information.”
The EVM schedule variance simply reflects a variance from the approved baseline. It is sometimes misleading to look at an earned value schedule position alone and rely on it to provide the project’s schedule position.
Being ahead or behind schedule often depends on where each task was placed on the baseline. Likely, most baselines reflect simply a best guess, perhaps the most likely position for each task. The time placement of each task may have little relationship to the project’s critical path. Critical path assessment complements the true schedule position.
That is the reason why a schedule variance analysis needs to be performed to complement the result of the EVM schedule variance and performance metrics.
Therefore, don’t rely solely on EVM scheduling metrics to assess the project schedule status.
Always analyze the EVM scheduling metrics in conjunction with the critical path schedule analysis.
Now you might question, should I ignore the EVM scheduling metrics if they are not reliable?
No. Until the 2/3rd of the project, those metrics are still reliable. However, you have to use them with caution.
You need to analyze your EVM scheduling metrics alongside with your CPM schedule. By doing so, the EVM scheduling metrics reveal great information about your project, especially if the EVM scheduling indicators and your CPM schedule are contradicting. For example, your SPI shows ahead of schedule (SPI>1) while your CPM schedule shows a behind schedule status. When you dig down into your schedule, you will realize something is causing that issue.
The EVM scheduling metrics provide a good warning signal that raises a flag for deeper analysis.
I hope this training clarified some of the issues you might have faced with applying the EVM scheduling metrics in your projects.
Now the question is:
How can I justify the quirky behavior of SPI & SV, especially toward the end of my project?
Is there any solution besides analyzing the critical path schedule?
There are several methods that you can apply to improve the accuracy and reliability of your EVM scheduling metrics.
One of the newly merged techniques is the application of “Earned Schedule”.
The Earned Schedule concept has been considered as an improvement/extension to the EVM practice.
The Earned Schedule concept has been added an as an appendix to the PMI Practice Standard for Earned Value Management in 2011. However, it was initiated in 2003.
If you are interested in learning more about the Earned Schedule, check out the next episode of Project Control Mastery, where I show you the concept of the Earned Schedule and how you can apply it in your projects.
-------------
Thank You Note
Thanks for reviewing this post. I regularly shoot videos or write articles on Project Controls. If you would like to have access to my future posts simply click "Follow." Also feel free to connect with me on Facebook, LinkedIn, and Instagram.
You might also be interested in receiving my 10-day free online video training series on Earned Value Management and how to unleash its amazing power in effectively managing your projects.
As the founder & director of Project Control Academy, I am committed to adding value to Project Control community not only through our comprehensive training programs in Project Controls but also by delivering these free training videos and resources on a regular and consistent basis. I hope you find these training resources helpful.
For More Project Controls Resources:
- Visit Project Control Academy
- Join thousands of like-minded professionals on Facebook.
- Subscribe for more: Podcast | Blog | LinkedIn | Instagram | Youtube
----------------------------------
Please share how you justified your EVM scheduling metrics in your projects? I’d be interested in hearing your thoughts and comments that would promote a healthy and positive discussion.
Senior project control specialist at Hirbodan
1 年That's right, exactly like this project.
Planning Engineer/ Principal Planner AL RYUM GROUP OF COMPANY (Al Ryum Cont. & Gen.Transp. LLC)
4 年Great designed article, Thanks?
Senior Project/Program Planner
6 年Thanks for sharing You earned the value for tasks that are not in the critical path, that's when you see your EV metrics indicate "ahead of schedule" status, which is not correct. Imagine a 20-story building construction project, for instance. We are at day 1 and we need to do excavation work with PV equals to 100,000 AUD by the end of day 30. If, supposedly, we decide to supply the whole HVAC system during the first 30 days with PV equals to 200,000 AUD. What has happened? By the end of day 30, we have EV equals to 200,000 as we bought the HVAC system instead of doing the excavation work, which makes SPI = EV/PV = 200K/100K = 2 >> "Ahead of schedule". WHICH IS NOT CORRECT. Because, this earned value during the first month is not coming from a critical path activity. Another case that EV indicators show misbehave, which you mentioned correctly, is the time we get closer to the end of the project.
To better assess you schedule, Earned Schedule technique should be used, which allows one to find SPI and SV in terms of time.
Director-Delay, at Analyzer, MEng - SP, RMP, PMP
7 年Dear Shohreh, that's a very informative article about SPI, indeed. I would like to add my thoughts with regards not only to SPI but to the EVM, as well as to the Earned Schedule method. SPI To start with, the SPI might prove to be unreliable not only during the last 1/3 of a project but within the first 2/3. That, depends on the position of the “Earned” curve in relation to the “Planned” one. Larger SPI values might erroneously signify that the project stands in a better condition as opposed to past smaller indices, whilst quite the opposite might be the case. EVM There is no doubt that EVM is a powerful tool in regard to the budget of the project and any cost related assessment or forecast. However, from a time related perspective it might be absolutely unreliable the same way the SPI is. EVM can tell how much a project has progressed against the plan, on a cost or man-hours basis, but it cannot unfortunately tell how much the project is delayed. The fact that EVM proves inconsistent at this point is an inherent drawback of the method itself. Having earned more in terms of cost or man-hours does not mean that you have equally earned more in terms of time. Whilst the performance of a contractor might be outstanding and a much greater portion of the initially estimated cost has been achieved at a particular point in time, there might be one and only path that pushes the completion date out, coming to directly confute what the verifiable (%), produced through the EVM, indicate. The existence of the particular path does not necessarily mean that something has been done wrong with the development of the schedule as Michael De Kort says. This can happen even if the most sophisticated Programme has been developed. Even further, the root cause(s) contributing to the formation of an emerging critical path might be beyond the responsibility of the contractor. It’s just part of a Programme’s life that EVM is unable to cope with. The best way to produce a Time forecast is to run a Risk Analysis, provided that a sound schedule along with meticulously prepared updated programmes and an adequately developed risk model are available. Earned Schedule (ES) The introduction of the alternative SPI(t), via the Earned Schedule methodology is undoubtedly a much better index as compared to the highly controversial SPI. However, it again assesses all the activities of a schedule collectively the same way EVM does. As a result, critical and non-critical tasks are embedded together in the model without any distinction between them to be apparent. Thus, the ES methodology remains susceptible in producing misleading information for the same reasons the EVM does. I will come back with some more advanced thoughts on the topic, when the article about ES is released.