Who owns the float?
A common question when demonstrating entitlement to an Extension of Time is 'who owns the float?'.?
When considering who owns the float, one first must understand the various definitions of 'float' typically associated with construction projects. Secondly, one must understand the applicable contractual clause relating to claiming an extension of time.
What is Float??
Most people will associate float with the CPM (critical path method) of scheduling. The critical path is determined by the sequence of activities within a program that dictates the overall program duration, i.e., the 'critical path'?has?zero total floats.?
However, there are several other applicable definitions of float, namely:
?
?
The consideration of 'external float' raises the question of 'who owns the float'.?
The Contractor may argue that it 'owns' the float because they plan how the work should be carried out and in what sequence. They may also allow a 'buffer' or contingency between its likely Date?of?Completion and the Date?for?Completion.?
Suppose, therefore, there is a delay to the Contractor's progress for which the Contractor is not responsible[1]?and the time contingency has not been fully exhausted. In this case, the Contractor may contend that it is entitled to an extension of time, even if the delay to progress did not result in the Date for Completion being impacted. Rather, the delay merely 'eroded' its planned time contingency. In this scenario the Contractor is asserting ownership of the float.
On the other hand, the Employer may consider the Contractor has no contractual relief for being prevented from completing the works before the contractual Date for Completion. Meaning the Contractor is not entitled to an extension of time unless the excusable delay results in the Date for Completion date being impacted. In this scenario, the project [i.e. the Employer] is claiming ownership of the float.
The expression 'float' is rarely if ever, defined in the conditions of the contract. Where the wording of the extension of time clause is such that an extension of time is only to be granted?if?the Employer delays completion beyond the Date for Completion, then the likely effect of that wording is that all external float must be 'consumed' before an extension of time will be due.
Suppose the wording of the extension of time clause is such that an extension of time will be due whenever the Employer delay event adversely impacts the Date for Completion date. In that case, the external float will not be available for the benefit of the Employer in the event of an Employer related delay.??
?
Contractual requirements?
The SCL Protocol maintains the following regarding float' ownership':
"Unless there is express provision to the contrary in the contract, where there is remaining total float in the program at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the critical path affected by the Employer Delay to Completion"?[2]
In other words, unless the contract says otherwise, the float is owned by the project.
?The following unamended (Australian) standard forms of contract demonstrate the specific wording regarding (external) float 'ownership'. All three examples deem the Contractor to 'own the float'.
?
AS2124-1992 35.5?
In respect of an extension of time claim, in determining whether the Contractor is or will be delayed in reaching Practical Completion regard shall?not?be had to:
领英推荐
?
AS4902-2000 34.4?
In assessing each EOT the Superintendent shall?disregard?questions of whether:?
But shall have regard to what prevention and mitigation of the delay has not been affected by the Contractor.?
?
AS4300-1995 35.5
In determining whether the Contractor is or will be delayed in reaching Practical
Completion regard shall?not?be had to:
?
?
The three examples of the extension of time clauses entitle the Contractor to claim for an extension of time to the Date for Completion regardless of the status of the works at the time of the delaying event.?
?For example, a Contractor is contracted to a November Date?for?Completion. However, the works are progressing quicker than planned and an earlier date?of?Completion of some three months sooner is reported, in August. The Employer has accepted the Contractor's progress and approved the updated Contractor's program. A variation direction has been demonstrated to have impacted the program by a month, meaning the Date?of?Completion is likely to be September.?
Is the Contractor entitled to an extension of time to the Date?for?PC??
Yes. The Contractor 'owns' the float. The Contractor has made the time and is entitled to use the time, i.e., what if a subsequent contractor delay event meant that all that float was subsequently consumed? The float is the Contractor's?opportunity.?
?
Key Takeaways?
?
?
[1]?And three-part chain of causation is satisfied?
[2]?Section 8, Society?of Construction Law Delay and Disruption Protocol, 2nd Edition 2017