When projects go wrong and it's the worst possible moment
Susanne Madsen
Project Leadership Coach, Facilitator, Speaker, Award-winning author of "The Power of Project Leadership" & "How to Do the Inner Work"
A project is a unique undertaking that’s full of risk and uncertainty, because it has never been done before in that exact way. Project management, as a discipline, is a response to this ambiguity. It’s a way to control the unknown. Just consider the most important techniques we use as project managers: we define scope, analyse requirements, plan and estimate work, add contingency, manage risks, track changes and check the quality. These techniques are designed to control uncertainty and plan for the things that could go wrong. We also analyse our stakeholders and draw up a communication plan that will help us gain their buy-in and support. If we don't take time to apply these project management tools, we may jeopardise the success of the project. As Murphy’s Law reminds us, anything that can go wrong will go wrong. And when it goes wrong it may be the worst possible moment.
Let the following three examples remind us of how bad it can go. These projects have served the public in amazing ways after they became fully operational. But let’s not forget that they started off as failures.
Heathrow Terminal 5
Heathrow Terminal 5 was built to handle a yearly capacity of up to 35 million passengers. It was 19 years in the making with the construction phase spanning 6 of those years. It consisted of 16 individual projects and involved over 60 contractors. In other words, it was a HUGE project.
At the time of opening in March 2008, only 85% of project deliverables had been completed. As construction work was running late, IT testing and staff training had also been delayed. In spite of the delays, it was decided to go ahead with the original opening date without deferring it. Terminal 5 was a big deal and moving the opening date would have been a big deal too. As a result of the delay there was less time available for hands-on training, dress rehearsals and fixing any problems arising from testing. Cutting short the testing and simulation activities had severe consequences.
On the opening day itself, staff had difficulties parking, moving around the terminal and operating the systems. But worst of all was the failing baggage handling system. On the first day 15,000 bags were lost and 35 flights were cancelled as the airport struggled to clear the baggage backlog. By 5pm passengers were told to travel without luggage if they still wanted to fly.
In the first week 500 flights were cancelled, 23,000 bags had been misplaced and hundreds of passengers had been left stranded. MPs described the opening as a national humiliation.
Although Terminal 5 was a much bigger project than most of us will ever get involved in, we can still learn from its lessons. Making a project operationally ready should never be underestimated or compromised. Testing, training, dry runs and handovers are essential activities on most projects.
Millennium Bridge
London’s Millennium Bridge was the first pedestrian bridge over the Thames in 100 years. Proclaimed as an engineering feat in its slender profile, the 320 metres suspension bridge was built in 2000. It was constructed using lateral suspension, an engineering innovation allowing suspension bridges to be built without tall supporting columns. But two days after its initial opening it was forced to close due to safety reasons. It was swaying – or wobbling – so much that people had to hold the handrails in order to stay safe. The bridge had been hit by a phenomenon called synchronous lateral excitation caused by the movement of the thousands of people who crossed the bridge by foot on its opening day. Whereas lateral excitation was a known phenomenon, the engineers had failed to understand that even when people walk randomly, a certain percentage is bound to “match step” and thereby cause lateral motion in the bridge.
As a result of this oversight the bridge was closed to the public just two days after its initial opening. Engineers spent 19 months reinforcing the structure with 91 dampers designed to reduce the movement. When the bridge was reopened in 2002 it had cost an additional £5million ponds.
Although the Millennium Bridge is a beautiful piece of architecture, let’s remind ourselves of the importance of proper risk management. Some risks are highly unlikely but if they were to happen the impact would be severe. It’s the team’s responsibility to respond appropriately to these risks. In the case of the Millennium Bridge it seems the risk of lateral excitation had been identified, but not appropriately addressed.
Sydney Opera House
As Australia’s most distinctive brand, Sydney Opera House attracts tourists from all over the world and adds almost $800 million to the Australian economy every year. But although the Opera House is a national symbol and has been recognised as an incredible feat of architecture, it’s one of the best-known case studies of a failed infrastructure project.
The architect, J?rn Utzon was appointed in 1957 with the construction of the Opera House starting in 1959. The goal was to complete the building in four years with a budget of AUS $7 million. But the project took a very different turn. It ended up taking 14 years to complete and cost a whopping AUS $102 million. A number of things went wrong that could be classified as project management failures:
- There was no detailed plan in place when the project started and there was no project manager
- The project was deliberately underestimated by its proponents to get the project approved and started
- The design of the building was not completed by the time construction got underway. Utzon protested but for political reasons the government was pushing for the construction to start.
- Major changes to the requirements were approved after construction had started, moving from two to four theatres. This meant that the designs, which were already challenging for the construction team to build, had to be modified on the go.
- The Danish architect resigned from the project mid way through as he felt his creative freedom was restricted. The government had started to withhold payments as it felt costs were spiralling out of control.
Redesigns, underestimates and cost overruns continued until Queen Elizabeth II finally inaugurated the Opera House in 1973.
Human ingenuity is not enough to make projects happen. We need proper project management to control the unknown elements. We also need excellent leadership to create a unified team of designers, engineers, clients and stakeholders, who act from a place of trust and honesty and who do what’s in the project’s best interest. Thankfully the world of project management has evolved since the 60ties and 70ties and is now a recognised practice. But we need to keep reminding ourselves of the failures of the past so that they are not repeated.
Susanne Madsen is the author of The Power of Project Leadership and The Project Management Coaching Workbook. You can read more about Susanne's coaching, training and consulting services on www.susannemadsen.com.
Retired at none
6 年The 3 examples make for v interesting review. I wonder would the 3 have been approved with the benefit of hindsight? Surely they would have been. T5, the MB and SOH are all now regarded as iconic triumphs, even if the programmes themselves experienced significant delays & cost overruns vs. the original plans plus considerable humiliation for some. Therefore, I wonder if the issue with programmes is often less to do with inadequacies on the control side of the project management equation (quality, cost & time) and instead more to do with difficulties project sponsors & leaders have in quantifying and articulating the potentially huge benefits of their programmes.??
Asset & Wealth Mgmt. | Change Mgr. | Front Office Process Redesign | Chartered Project Manager
6 年I think this shows the importance of getting the planning done properly and having contingency. Too often the budget constraints poor handovers play a role in addition to the other factors such as sponsor engagement, business buy in and proper solution design with clear agreed deliverables across the project lifecycle.
I craft value-filled knowledge and transformation experiences. I also help manage mega projects.
6 年Yes, nice reminder, Susanne. Although our projects may not be as sensitive or large, when it goes terribly wrong, it can feel horrible. I'm very fond of good risk management and I believe practicing risk management makes it..better. One thing I've learnt is that assumptions are a minefield for risks. Always keep close tabs on those. Thank you.