What a proper baseline can do for your project?

What a proper baseline can do for your project?


Author: Mathew Hazenberg


A baseline sets the ambition for a project – what is the project aiming to achieve, within what time frame and within what budget? It is, without doubt, the key management tool for any project.?


Despite this, teams are rarely given enough time or resources to develop a robust project baseline. However, when they are, we have seen that the clarity, focus and alignment it fosters across a project’s organisation is invaluable – and fundamental to the project’s success.


Why do we need a project baseline?


A baseline helps align the entire project team around a common plan, and it provides a reference point from which to evaluate:

  • Delivery performance – are we on track to deliver our commitments?
  • Change – how does a change of scope, time or cost affect what we committed to deliver?
  • Outcomes – did we deliver what we said we would?

?

When do we set a project baseline?

?

Baselines should be set ahead of major decision points (feasibility approval, major contract awards, etc.) so that there is a documented, coherent definition of the expected project outcomes, scope, schedule and cost on which those decisions were made. It is vital that enough time and resources are dedicated to producing it, given it will become the yardstick for the project.

?

What makes a good project baseline?

?

A project baseline should:?

  1. Define expected outcomes or benefits, as well as scope, timeframes and cost, to keep them within sight and under change control.
  2. Provide the “golden thread” between benefits, requirements, scope, time and cost to support rigorous change management. The key challenge here is to cover scope comprehensively and break it down in a way that reflects how the project will be contracted, delivered and commissioned.?
  3. Allow for risk and uncertainty, with allowances assigned transparently to discrete scope elements and events to ensure changes to risk exposure can be understood as the project progresses.

?

A baseline is only valuable when all stakeholders trust it and buy into it (whether or not they are happy with what it tells them). This requires three things:

  1. A mandate from the top making sure the baseline development is seen by all as a priority task and overseen and signed-off by senior leadership.
  2. A rigorous development process drawing on all the latest data, knowledge and expertise from across the organisation.
  3. Continuous, independent assurance to challenge the project team to uphold the highest standards in producing the baseline and to highlight key areas of uncertainty.

?

When should you update the baseline?

?

Firstly (as mentioned earlier), the baseline should be updated at key decision points through the project development process to reflect the latest understanding of the project and the level of certainty in the scope, time and cost.

?

Other than this, when to update a baseline can often be a contentious issue because of different perspectives; a project sponsor and a project director may have differing views, for example. However, it makes sense for a baseline to be updated in the following circumstances:

  • When external influences on the project – those outside of the accountable party’s control – result in changes to the project requirements, scope, timeline or cost, making it unfair to measure performance against the original baseline.
  • When project requirements or scope have changed so significantly that the original baseline is no longer useful as a measurement reference.

?

Whether these revised baselines are translated into revised targets and KPIs for organisation-level (and individual-level) performance management is another subject!

?

When done properly, developing the baseline forms an integral part of all other project development activities (design, planning, estimating, etc.) and takes just as long. All too often, we see incoherent baselines pulled together in a few weeks just to tick a box.

?

Investing time and effort in developing a coherent, detailed and realistic baseline at the start of a project pays back multiple times over and is one of the most clear-cut investment decisions leadership can make. Let’s make sure project baselines receive the dedicated time and resources they need!

?

Tim Scofield

Project Director at Turner & Townsend

1 年

Interesting article Mat and one close to my heart. An integrated and consistent approach baselining facilitates the central nervous system of the project.

要查看或添加评论,请登录

社区洞察

其他会员也浏览了