What is a Management of Change (MOC) System?

What is a Management of Change (MOC) System?

A system that helps ensure that risks associated with change are understood and properly managed, allowing you to meet your goal of safe and reliable operation.

Managing Change in Manufacturing and Production Facilities

Change is all around us. As soon as a plant or processing facility is commissioned, operators and engineers begin to think of ways to make it better. Changing business conditions require changes to raw materials, finished products and operating parameters. Vendors develop new and improved equipment and instruments. Equipment needs to be bypassed or temporary repairs need to be made to reach the next turnaround. Leak-repair clamps are installed to stop environmental releases.

Changes like these will require updating procedures, modifying the existing equipment or adding new equipment. A robust management of change system can help prevent these improvements from creating problems ranging from off-spec product to catastrophic events.

Why Do We Need A Management Of Change System?

The incidents that occurred in 1974 at the Nypro UK plant in Flixborough and in 1984 at the Union Carbide plant in Bhopal, India, are examples of change gone terribly wrong.

At Flixborough, a 20-in. pipe was installed, bypassing a damaged reactor to allow the plant to operate while the reactor was repaired. Three months later, the temporary pipe failed releasing 30 tons of flammable cyclohexane. The ensuing vapor cloud explosion killed 28 workers, injured 89 workers and members of the public and destroyed the plant. The piping design and supports had not been reviewed by an engineer or technical authority prior to making the change, and risks associated with hydraulic surge in the piping during process upsets had not been fully addressed.

In the Bhopal incident, a runaway reaction resulted in the release of methyl isocyanate (MIC). The MIC cloud left the plant and drifted over the neighboring town killing thousands and injuring tens of thousands. The effects of the MIC release are still felt in Bhopal today. A contributing factor in the incident was the temporary bypass of some plant safety systems. Risks associated with safety system bypass at the same time as a runaway reaction were not considered and properly managed.

As illustrated here, improperly managed risks can have serious and sometimes fatal consequences. Because of these incidents, other accidents in the U.S. and inconsistent change management practices in the chemical and refining industries, OSHA enacted the process safety management (PSM) regulation in the early 1990s. One of the key components of the PSM regulation is management of change (MOC).

What Are The Benefits Of MOC?

  • It minimizes unplanned adverse impacts on system integrity, security, stability, and reliability for the business process being altered or added.
  • It maximizes the productivity and efficiency of staff planning, coordinating, and implementing the changes.
  • It provides a stable production environment.
  • It ensures the proper level of technical completeness, accuracy of modifications, and testing of systems before implementation.
  • It provides an appropriate level of management approval and employee involvement.

MOC System

The MOC system must address changes that range from minor changes to major capital projects as well as handling temporary and permanent changes. This can be accomplished in many ways. Some companies have developed “one-size-fits-all” MOC processes that are used for every change. Other companies find it easier to have multiple MOC systems. The multiple systems can be split based on the type of change (equipment vs. procedural), the duration (temporary vs. permanent) or the size of the change (minor vs. major). The decision to use an electronic MOC process should also be considered. The important thing to remember is that the MOC process or processes should be flexible, easy to use and fit your plant culture. Avoid following the MOC process for bona fide replacements-in-kind (RIKs).

A basic MOC process contains the following steps:

  • Initiation
  • Preliminary review
  • Risk assessment/technical review
  • Approval to design/construct
  • Design/construct/pre-commissioning
  • Pre-startup safety review (PSSR)
  • Approval to start up
  • Follow-up activities

In the initiation step, any employee should be able to propose a change to a procedure, equipment or technology of the PSM-covered process. The MOC forms should allow the initiator to document the what, why and when of the proposed change. The initiator then forwards the information to one or more members of the facility management team for review and approval.

The preliminary review consists of a “go/no go” decision based on the information supplied by the initiator. This may include discussions between the initiator and the reviewers to clarify the details of the proposed change and alignment with the facility’s needs. If the decision is made to proceed with the change, the preliminary reviewers should, as much as they are able, provide feedback on the technical basis for the change, impact on safety and health and the time frame to accomplish the change. If the change is temporary, the preliminary reviewers should also ensure that the date that the temporary change will be reverted to normal is included in the MOC documentation.

The risk assessment/technical review step is one of the most important activities within the MOC process. It is critical to involve the facility engineer, technical authority or someone with a deep understanding of the PSM-covered process in this step. The risk assessment should match the complexity of the change. For minor changes, it may be okay to ask the question “What if?” More complex changes require tools like process hazard analysis or failure mode-effect analysis. Some companies find it useful to include a risk assessment checklist in their MOC process. The checklist includes questions like “Does this change involve a shutdown or safety system?” and “Does this change increase or decrease the pressure, temperature or flow rates within the process?” The completed checklist can be the risk assessment or it can point the user toward a more sophisticated risk assessment tool or additional review by safety, environmental or technical experts. Regardless of the risk assessment method, it is important to document what could reasonably go wrong and the steps required to prevent it within the MOC prior to obtaining approval to design/construct.

The approval to design/construct step is typically granted by the facility superintendent(s) or manager(s). These people are committing resources toward completing the change and agreeing that the change can safely be made based on the information provided.

Most of the “real work” is accomplished in the design/construct/pre-commission step. In this step, final designs are completed, piping and equipment constructed, procedures updated, redline drawings created and equipment installation verified. If the design changes during this step, another round of risk assessment and approval is critical to ensure that risks associated with the new design are properly managed.

The PSSR step consists of the set of verifications and assurances that each portion of the work associated with the change has been properly completed. The PSSR items are typically assigned to multiple people, including facility engineers, operations leaders and maintenance leaders. A PSSR must include the following items:

  • Equipment meets the design specifications and has been properly installed
  • Adequate safety, operating, maintenance and emergency procedures have been developed or existing procedures modified accordingly
  • Process hazard analyses have been completed for new facilities and recommendations have been resolved or implemented before startup
  • Employees involved in operating the PSM-covered process have been trained on or notified of the change as appropriate
  • Safe work practices have been revised accordingly
  • Process safety information used by employees (e.g., piping and instrumentation diagrams, equipment spec sheets) has been updated accordingly
  • Items that will be needed in the future have been assigned for completion. This typically includes items like coordinating spare parts inventory with purchasing.

Once the PSSR is complete, the MOC is forwarded to the facility superintendent or manager for startup approval. By granting startup approval, the manager or superintendent is confirming that the requirements of MOC and PSSR have been completed properly and that the change is safe to start or to make active. Because of this, the superintendent or manager should have a solid, working understanding of the facility MOC process as well as the requirements of OSHA’s PSM standard.

As mentioned, follow-up activities need to be assigned to individuals for completion. The MOC process should be robust enough to ensure that these items are not forgotten as the next project or initiative moves to people’s inbox. Most companies will not close an MOC until the follow-up activities are completed.

Improving the MOC Process

The best way to ensure that the MOC process is working is to conduct periodic self-assessments or reviews. The review may be conducted by anyone with a solid understanding of the MOC process and should include a representative number of MOCs for the last 3 to 6 months. It is often better to have a person outside the department perform the review. This gives a level of independence to the review and helps find problems that someone inside the system may overlook. Many companies use a checklist or other guide to help obtain consistent results. The results can be used for individual coaching or to indicate areas of the MOC process that need to be improved.

It is also very important to compile safety information on the products, equipment, materials or processes that are changing and make them easily accessible, so they can be updated when affected by MOCs.

Common MOC Problem Areas & How to Avoid Complexity

Some MOC processes attempt to be a “one-size-fits-all” system. As a result, they are so complex that the users find it difficult to complete an MOC. This can lead to frustration and can also cause people to bypass the process for small changes because it is not worth the effort to run a small change through the system leading to some changes not being adequately managed. To help avoid this, consider having separate MOC processes that are specifically tailored for small changes or changes to procedures and documentation. Another method of handling this is to have a simple base MOC process that includes supplemental checklists or features that are only used when needed.

Notification & Training of Affected Employees

This is one of the gray areas of the PMS regulation. A facility is required to train and/or notify affected employees of the change, but there are no requirements to document the training or notification associated with the MOC. To avoid problems in this area, it is best to follow the “If you did not write it down, you did not do it” approach. Some plants have a binder in the control room or maintenance shop with copies of the MOC and rosters so that the employees can review and sign off. Others use electronic systems or e-mail to document the communication or training. Either method is fine as long as the facility ensures that employees returning from time off due to shift schedules, vacation, etc., review the MOC information on their first shift back to work.

Startup Before Approval is Granted

Occasionally, changes are made active prior to receiving startup approval. Reasons for this include emergency changes that need to be made during weekend or night shifts, superintendent or manager vacation or misunderstanding that another approval is needed before startup can occur. To handle changes when the approvers are not available, some facilities delegate approval authorization to facility operations leaders and shift leaders. Others have a rotating on-call process where other superintendents and managers approve another department’s MOCs. In the case of misunderstanding regarding the second approval for startup, well-written MOC procedures with clear expectations for each step are critical. Flowcharts and process maps can also be helpful.

Not Completing Follow-Up Activities

No magic bullet will ensure that follow-up activities are completed. Some companies use electronic systems that automatically send notices and generate tracking reports. Even these systems can fall short if the facility is not diligent in closing the loop and holding the assigned people accountable to complete the tasks. Periodic reviews, as described here, can also help identify when follow-up activities are not completed.

Temporary Changes That Last Forever

Pipe leak-repair clamps and bypass lines that have been around a long time are both examples of temporary changes that evolve into semi-permanent and permanent changes. Some companies attempt to avoid this situation by setting limits for how long temporary changes can be in effect. MOC expiration dates of 120 to 180 days are typical. Other facilities conduct technical reviews and reauthorize temporary MOCs on a quarterly, semiannual or annual basis to ensure that the operating conditions have not changed and that the temporary change is still safe to operate and not becoming permanent. Like follow-up activities, diligence and periodic reviews are the best ways to prevent temporary changes from evolving into permanent changes.

Conclusion

The Management of Change system will help a facility meet the OSHA PSM regulations, but the benefits can reach beyond compliance. A simple, yet robust, MOC system can help ensure that risks associated with change are understood and properly managed, employees are trained on how the change affects them, accurate procedures are in place for maintenance and operations, equipment files are up to date and spare parts are available when they are needed. When these elements are in place, a facility can meet their goal of safe, reliable operations.

See what our Management of Change system can do for your company.

Schedule a personalized demo, email [email protected] or visit www.fldata.com for more information.

Frontline Data Solutions - 281-313-8200

Sindi Steele

Sales Development, High Tech, Lead Gen Automation, MasterMinds, Roundtables, Email Automation, LinkedIn Automation, Done For You, SaaS, Mother of UFC Fighter

2 周

Brad, thanks for sharing! We are hosting a live monthly roundtable every 1st Wednesday at 11am EST to trade tips and tricks on how to build effective revenue strategies. It is a free Zoom event where everyone can introduce themselves and network. We would love to have you be one of my featured guests! We will review topics such as: -LinkedIn Automation: Using Groups and Events as anchors -Email Automation: How to safely send thousands of emails and what the new Google and Yahoo mail limitations mean -How to use thought leadership and MasterMind events to drive top-of-funnel -Content Creation: What drives meetings to be booked, how to use ChatGPT and Gemini effectively Please join us by using this link to register: https://forms.gle/iDmeyWKyLn5iTyti8

回复
Liliana Dias

Sales Specialist at Full Throttle Falato Leads

5 个月

Brad, thanks for sharing!

回复
Uchenna Dike

HSE Supervisor working for Shell Petroleum Development Company

2 年

What are the various asset MOC tools?

回复
Palani Selvam Murugaiya

Environmental Health Safety Manager

3 年

Thank you very much for sharing this. Get knowledge about MOC.

回复
Sharon Lahart

EHS Director Consultant & Trainer

6 年

Breda Salley

要查看或添加评论,请登录

社区洞察

其他会员也浏览了