What is the Critical Path in Project Management?

What is the Critical Path in Project Management?

A network diagram is a graphical representation of the sequence of project activities and the dependencies among them. There are two types of network diagrams, activity on arrow (AOA) and activity on node (AON). The most common network diagram uses the AON diagram technique, in which boxes represent activities. The complex and dynamic nature of development projects make this tool especially valuable because it helps the project manager identify the potential interactions of project activities that can be easily missed otherwise. The value of the network diagram is that it provides visibility and control over the project schedule. It also helps determine the total duration of the project and its critical path, or path with the longest duration.

The figure below shows an example of a project network diagram that includes the duration estimates and dependencies; the diagram also shows the dependencies among the activities and how these can form parallel paths.

No alt text provided for this image

The Critical Path is Path A, it is the path in the network diagram with the longest total duration (100 days). Activities on the critical path cannot be delayed, or the whole project will be delayed, unless the loss of time can be offset somewhere else on the critical path. To find the critical path, add up the duration of the activities for each possible path through the network, to determine which has the longest total duration. The difference between the longest total duration and the shortest path(s) is the total amount of float or slack for the noncritical path activities.

Float or Slack is the amount of time that an activity or a task in a project network can be delayed without causing a delay to subsequent activities or tasks and the project completion date.

The critical path is in essence the shortest time a project can be completed, even though the critical path is the longest path on the project. It is not the path with the most critical activities or the shortest path on a project network diagram. There are cases in which a network diagram may have two critical paths that have the same total duration.?A benefit of Critical Path Analysis (CPA) is that it helps identify the minimum length of time needed to complete a project. Where there is a need to accelerate a project, the CPA will help identify which project activities you can compress or fast-track?to accelerate and complete the project within the available time.


Want to learn more? Register for the next session of our online course Effective Project Management and start building your project management skills. Register here?https://www.pm4dev.com/elearn/ecourses/eepm.html??

Basan Shrestha

Monitoring and Evaluation Specialist at Prime Minister Employment Programme (????????????? ?????? ?????????)

1 年

Example: In a household latrine construction project, minimum 25 days are required from digging a hole to completing audit. Within that period construction to community training could be conducted side by side. Reference PMD Pro1 Guide.

回复

要查看或添加评论,请登录

Rodolfo Siles, PMP, MScM, BSc Eng.的更多文章

  • What is Adaptive Project Management?

    What is Adaptive Project Management?

    The fundamental concept underlying adaptive project management is that scope is variable, and within specified schedule…

  • Do You Know the Difference Between Risks and Issues?

    Do You Know the Difference Between Risks and Issues?

    Risk and issue are two words that are often confused when it comes to their usage. The word ‘risk’ is used in the sense…

  • What are the phases of the Information Management Cycle?

    What are the phases of the Information Management Cycle?

    Information Management is the channeling of the information resources and information capabilities of the project to…

  • Managing Quality to Meet Stakeholder Expectations

    Managing Quality to Meet Stakeholder Expectations

    Quality management (QM) is the process for ensuring that all project activities necessary to design, plan and implement…

  • Why you need a project marketing plan?

    Why you need a project marketing plan?

    The goal of marketing your project is to raise awareness and build strong stakeholder support by saying how your…

  • How to do an Effective Project Close

    How to do an Effective Project Close

    The practice of project close-out finalizes all project activities completed across all phases of the project to…

  • The Adaptive Project Management Cycle

    The Adaptive Project Management Cycle

    A project management methodology follows a cyclical approach throughout the life of the project. The cycle represents a…

    2 条评论
  • Who is Responsible for Project Quality?

    Who is Responsible for Project Quality?

    While the project manager has overall responsibility for the quality management process, some projects may also have…

    3 条评论
  • Making the Right Presentations

    Making the Right Presentations

    Here are some tips to help you prepare for your next project presentation. The purpose of any presentation, written…

  • The Problem with Project Management in Development Organizations

    The Problem with Project Management in Development Organizations

    The problem with project management in development organizations is that all too often it is seen as an afterthought…

社区洞察

其他会员也浏览了