Unilateral Appointment of Sole Arbitrator: HC opines on maintainability of s.11 Petition after filing of an s.13 Application
White and Brief - Advocates & Solicitors
A full service law firm offering specialized legal solutions.
Recently, the High Court of Himachal Pradesh, in the case of BMD Pvt. Ltd.[1], opined on whether a Petition under Section 11 of the Arbitration & Conciliation Act, 1996 (“the Act”) would be non-maintainable before the Court after filing of an application under Section 13 of the Act to challenge the appointment of an arbitrator
Indian courts have constantly reiterated that the principle of party autonomy
Background of the Dispute
The parties of the instant case are embroiled in a web of judicial applications under the Act ensued by their initial association in 2011 for the execution of a hydroelectric project in Himachal Pradesh. The Respondent extended a sum of INR 6 to the Petitioner as an upfront premium which was then followed by a project report. However, in this report, it was found that the proposed plan is technically and financially unviable which prompted the Respondent to seek a refund of the said premium from the Petitioner.
On Petitioner’s continued disregard towards the Respondent’s request for a refund, the Respondent served a legal notice in 2019 indicating that it shall be treated as a notice of initiation of arbitration proceedings (under the terms of the underlying contract) if the upfront premium along is not refunded within 15 days from the date of the said notice.
In 2020, a Section 11 (6) application was filed by the Petitioner to request the appointment of an arbitrator which was then followed by a Section 13 application on the part of the Respondent to challenge the appointment of the arbitrator.
Arguments Posed by the Parties
The Petitioner, arguing in favour of the Sec 11 application, submitted that the unilateral appointment made by the Respondents is invalid in law as the Petitioner had previously informed the Respondent that it is going to approach the Court for the Himachal Pradesh High Court for appointment of the arbitrator.
Whereas the Respondent challenged the maintainability of the Petitioner’s Section 11 application before the Court on the grounds that it has already filed a Section 13(2) application, challenging the appointment of the arbitrator chosen by the Respondent, therefore, it is estopped from filing the said application for appointment of the arbitrator. It further claimed that due to the Petitioner’s lack of response to the Respondent’s arbitration notice, the Petitioner can only challenge the arbitrator under Section 13 of the Act.
Rule
Issues Discussed
1. Maintainability of Section 11(6) Application
The Court explained that the Petitioner’s lack of response to the Respondent’s arbitration notice within the stipulated time can be understood as its deemed consent to the appointment of the arbitrator indicated in the said notice by the Respondent.
Relying its understanding upon the precedent set in the SP Singla case[3], the Court is of the opinion that the party which failed to object/respond to the notice of appointment of an arbitrator within 30 days, the party estopped itself from laying a challenge to the appointment of an arbitrator, once it had given deemed consent to the same, by not responding/objecting within the stipulated time.
2. Maintainability of Section 11 application considering the pending Section 13 application
Relying on the Honourable Supreme Court’s decisions set in the SP Singla Construction case[4] and Swadesh Kumar Agarwal case[5], the Court held that once parties have invoked arbitration proceedings and an arbitrator has been appointed, subsequent applications under Sec. 11(6) of the Act shall not be maintainable considering that it has consented to the arbitrator’s appointment via submission of an application to terminate the arbitrator’s appointment under Sec. 13 of the Act.
4. Whether the Court can exercise its powers under Section 11 of the Act when the arbitrator is already appointed and whether the appellant should be left to raise challenges at an appropriate stage in terms of remedies available in law.
After the close perusal in the case of Antrix Corporation Limited v. Devas Multimedia Private Ltd. (2014) 11 SCC 560, and S.P. Singla (supra) the Hon’ble SC held that after the appointment of an Arbitrator is made, the remedy of the aggrieved party is not under Sec. 11(6) but such remedy lies under Sec(s) 12 and 13 of the Arbitration Act. If any party is dissatisfied or aggrieved by the arbitrator's appointment in terms of the agreement by another party/parties, his remedy would be by way of a petition under Section 13 of the Act and, thereafter, filing an application for challenging the award
领英推荐
Final Decision of the Court
The terms of the underlying contract expressly provided that the concerned parties shall endeavour to settle any disputes amongst themselves, at the first instance, through mutual negotiations
In the instant case, the dispute was referred to arbitration after making due efforts to settle through mutual negotiations. Also, as previously stated, the arbitration notice issued by the Petitioner clearly states the name of the arbitrator it wishes to appoint.
Law clearly states that any challenge to the tribunal’s jurisdiction
Final Takeaways & Insights
The decision in Perkins Eastman Architects DPC & Anr. v. HSCC (India) Limited[10], has gone a long way in clearing various legal hurdles in the appointment of arbitrators under the prevailing law. Initially, the courts played a key role in the appointment of arbitrators under Section 11 of the Act, however, now, arbitration institutions have taken over.
In the case on hand, the aggrieved party subjected itself to the tribunal’s jurisdiction by making an application under Section 13 of the Act. The Court’s judgment in the instant case can be taken as a precedent by individuals and entities engaged in an arbitration agreement or proceeding to ensure thorough appreciation of the terms applicable for the appointment of the tribunal under their contract.
In the future, courts are likely to handle such cases while balancing the need to ensure the independence and objectivity of arbitrators with the fundamental principle of arbitration agreements and the court's limited ability to interfere with the parties' stated bargain as set forth in the arbitration agreement.
**********
Disclaimer: The content of this piece published by White & Brief Advocates & Solicitors is intended for informational purposes exclusively and is not intended to be a piece of legal advice on any subject matter. By viewing and reading the information, the reader understands there is no attorney-client relationship between the reader and the publisher. The contents of this informational piece shall not be used as a substitute for professional legal advice from a licensed attorney, and readers are encouraged to consult legal counsel on any specific legal questions they may have regarding a specific situation.
[1] BMD Pvt. Ltd., Arbitration Case No. 5 of 2020.
[2] PASL Wind Solutions Private Limited v. GE Power Conversion India Private Limited; 2021 SCC OnLine SC 331
[3] SP Singla Construction v. State of Himachal Pradesh (2019) 2 SCC 488
[4] SP Singla Construction v. State of Himachal Pradesh (2019) 2 SCC 488.
[5] Swadesh Kumar Agarwal v. Dinesh Kumar Agarwal, Civil Appeal Nos. 2935-2938 of 2022.
[6] Antrix Corporation Limited v. Devas Multimedia Private Limited (2014) 11 SCC 560.
[8] Section 12, Arbitration & Conciliation Act, 1996. Grounds for challenge.
[9] Section 13, Arbitration & Conciliation Act, 1996. Challenge procedure.
[10] Perkins Eastman Architects DPC & Anr. v. HSCC (India) Limited, Arbitration Application No. 32 of 2019.