Understanding Remaining Useful Life (RUL) with the P-F Curve
Photo by Jayphen Simpson on Unsplash

Understanding Remaining Useful Life (RUL) with the P-F Curve

TL;DR: Remaining Useful Life is the time between the point of measurement and the Functional Failure of the asset.?

Recently, there has been an influx of Industry 4.0 companies promising their product/application would help predict the Remaining Useful Life (RUL) of a physical asset. Each uses a mix of machine learning algorithms to estimate the RUL based on the data available. This is their value proposition. But what is this 'life'? Is it a constant value or a range? If it’s predicted, does that mean the culmination of the efforts to manage assets? Can we rely on this calculation and base all other Maintenance Work on it? I intend to explain the Remaining Useful Life in this article by comparing it with a well-known concept.

Maintenance & Reliability Professionals are familiar with the P-F Curve. It’s the graphic representation of an item’s Resistance to Failure against Time. The curve says two things: 1) Each failure is preceded by a symptom; 2) Resistance degrades over time. The point where the symptom of an impending failure is observed is called Potential Failure and the point where the resistance becomes unsatisfactory is called Functional Failure. The time interval between these points is the P-F Interval. ?

No alt text provided for this image

The versatility of the P-F Curve enables it to capture the behavior of all the known asset failure patterns. Even if an asset exhibits infant mortality or a constant failure rate pattern, they can be represented in a P-F Curve because the asset will show some symptom of impending failure before the actual failure. In the extremely rare case of no indication & a snap failure, the P-F Curve is drawn as a short steep curve with the P and F points very close. Regardless of the curve shapes, the Functional Failure is the point of failure (or unsatisfactory performance) and hence the total time taken for the asset to reach this point is its 'Useful Life'. In other words, it’s the time for which the asset will perform its function satisfactorily. If we measure the useful life left from a different point along the curve instead of the beginning, then we get the 'Remaining Useful Life' from that time. Let’s say you have an asset that has been running for 6 months, and you want to know how many more months it will function without failure. You get this by measuring the time between now (t) and the Functional Failure. Observation point can be anywhere; if it is at the potential failure point then RUL is same as P-F Interval.

No alt text provided for this image

Predictive algorithms, used by Industry 4.0 apps, will generalize the system data to fit into these curves and measure the time to functional failure. Since the historical data contains variations (from conditions, design, and operations), each point on the curve is a probability distribution (pdf). i.e., the same P-F Curve when repeated will exhibit a distribution of curves. Because of this, the Functional failure point is also a distribution. Evidently, measuring the time between two distributions will also give a distribution. Hence, we have the Remaining Useful Life of an asset as a range of values with a probability of occurrence.?

No alt text provided for this image

Predictions carry uncertainty with it and the curves above show how the uncertainty is quantified. One advantage of the algorithms is that as time progresses and more data is fed, the uncertainty reduces. So, the RUL estimation will be more uncertain at the beginning of asset life and will get certain as the asset reaches its functional failure. To avoid reporting distributions, use the median of the RUL distribution to denote the RUL as a singular value. Given this interpretation, we can finally define:

“Remaining Useful Life (RUL) is a probabilistic estimate of the time period until which the asset will continue to perform its intended function under stated conditions” ?

Estimating RUL with high accuracy is just the first part. Maintenance Work must leverage this information with other factors to tie-in with the broader framework to effectively manage assets.

This article came out of a conference paper I co-wrote with Gary Josebeck for RAMS 2022 Conference: “Demystifying the P-F curve & Augmenting Machine Learning for Maintenance Optimization”

Alan Dunne

5G Wireless Product Development

2 年

Strong article Arun. Nicely done. In the last PF curve of the article you have the distribution of RUL centered around the age value for "absolute" failure point (i.e. where resistance to failure is at zero). Based on earlier paragraphs I would have thought that you would have centered the distribution at the age value for "functional" failure, where resistance to failure is slightly above zero yet asset performance is no longer acceptable. Any comments on this thought? Also, I think there is a category of systems or assets where the system functions, or does not function, in a binary behaviour. There is no observable or measurable degradation until the point of failure, even though there is degradation occurring "under the hood" . I can think of a lot of discrete digital electronic systems I have worked on over the years that exhibit this characteristic and essentially are true exponential failure law systems. These system also tend to go functionally obsolete before they functionally fail and are replaced accordingly. This is especially true in system where the underlying digital electronic hardware is no longer supported by the controlling software which is constantly being "upgraded" and delivered to the field.

回复
Shantanu Samajdar, P.Eng, CMRP?

Maintenance | Reliability | Manufacturing

2 年

Arun Gowtham Gary Josebeck, CRE, CMRP, CRL is an amazing teacher having the pleasure to work with on a project was a great learning experience.

Héctor Velázquez Martínez

Reliability Tech. RCM & FMECA (Vib Analysts Cat.II, IR Level.II, Ultrasound L.I Motion Amplification L.I) SAP Plan&Sch. MachineLearning Operations

2 年

Arun Gowtham very Nice article. Have You already developed this algorithms in a real world industrial pump, fan or the like? Saludos

回复
Gary Josebeck, CRE, CMRP, CRL

Partnering with clients to build Reliability, Availability, and Maintainability (RAM) into their physical assets.

2 年

It was a pleasure working with you Arun on developing the Dynamic P-F Curve concept to forecast an ever changing RUL and establish a new forecasted Potential Failure point. With the help of these algorithms and continuous monitoring sensors, we'll have a better insight to Planning and Scheduling our maintenance activities than every before.

要查看或添加评论,请登录

Arun Gowtham的更多文章

社区洞察

其他会员也浏览了