Understanding the Contract on your project...

Understanding the Contract on your project...

Understanding the contract is of absolute importance to the success of your project. Do you know how many days you have to give notice of a variation? What do you do when there is a delay event – are there particular rules on this?

Projects are not simple. Knowing how to act in difficult situations is imperative. At the start of any project, you should always complete what I call a ‘Contract Audit’ document.

What is a Contract Audit?

A Contract Audit is a questionnaire on key items in the contract asking all sorts of questions. These could range from “what is Notice period to commence on site?” to “what is contract procedure for raising/issuing Valuations?”

Over time this document will be adapted or updated but the idea is simple:

  1. The QS, completes the questionnaire and, in doing so, creates a 2 to 3 page document which summarises the contract.
  2. This document is shared with the project team who have it as a handy guide throughout the project.
  3. The project team meet and discuss the Audit at the outset of the project to create an agreed strategy for certain situations.

For example?

You’re working with a new client who you want to build a long-term relationship with but the Contract includes the following Clause:

It shall be a condition precedent to [your] right to an extension to the Period(s) for Completion that [you] shall have given written notice to the Employer of the matter which is causing or may cause delay within 5 days of the delay first occurring…

You know that if you want to claim the time and money (which of course you do!) then you have to give notice within 5 days of the event happening, but you don’t want to seem ‘contractual’ and alienate the new client.

So what do you do?

One way to ‘quietly’ deal with the issue of a 5-day notice is to write a Weekly Project Report which very simply records the state of play (basically your client’s delays) and gives early warning of issues without appearing ‘contractual’ by sending a letter.

In this instance, the Contract Audit works wonders: it highlights the risk to the whole team and allows you to set Project Procedures the whole team can buy into.

This is just one example of how a Contract Audit can help set the tone for your project management. There are many ways of protecting and/or increasing your project margins.

Without a doubt understanding the contract and focusing your team from the very beginning is fundamental and this can only stem from thorough analysis and understanding of your contract. If you’d like to access a Contract Audit template and a template Weekly Progress Report, get in touch via email.

----------

This article originally appeared on C-Link.com

Paul Heming writes at C-Link.com where he shares ideas for Quantity Surveyors and Project Managers on how you can progress in your career by increasing profits on your projects. Subscribe for updates to receive exclusive content.


要查看或添加评论,请登录

Paul Heming的更多文章

  • Missing the boat: are lenders miscalculating construction risks to their detriment?

    Missing the boat: are lenders miscalculating construction risks to their detriment?

    Fundamentally, a lender cannot, and does not, want to step in and rectify a site that’s gone wrong. Replacing a single…

    2 条评论
  • Project Lifecyle #12 - Notices to Commence

    Project Lifecyle #12 - Notices to Commence

    A Notice to Commence (NTC) is a formal communication from the Client to the Contractor stating the date the Contractor…

  • Take value and enter PCSA Agreements

    Take value and enter PCSA Agreements

    Pre-Construction Services Agreements (PCSAs) are used to appoint design and build Subcontractors to carry out services…

    1 条评论
  • The Importance of Project Reviews

    The Importance of Project Reviews

    For whatever reason, there is a whole list of names given for Project Review meetings in Construction. Depending on…

  • Game Theory & Subcontract Procurement...

    Game Theory & Subcontract Procurement...

    We’ve discussed cash-flow and its importance to running a project. Good cash-flow gives you flexibility and control…

  • Cash is your best friend!

    Cash is your best friend!

    Cash is your best mate… In all lines of business ‘Cash is King’, but in construction, it’s more critical than most…

    1 条评论
  • Removing Risks and Taking Opportunities.....

    Removing Risks and Taking Opportunities.....

    In any industry, for a project to be a success, a defined project strategy is critical – Construction is no different…

  • Recovering monies in a design claim...

    Recovering monies in a design claim...

    Last week we discussed the various tools to use to make sure you can claim for time lost during the design period. I’m…

  • Reacting to delays during design

    Reacting to delays during design

    I’ve already mentioned that where Construction Contracts include design, my experience is that the success or failure…

  • Managing the Design Process

    Managing the Design Process

    Where Construction Contracts include design, my experience is that the success or failure of the project typically…