Two Wrongs Don't Make a REZ
Credit: Neoen Australia

Two Wrongs Don't Make a REZ

Disclaimer: this is my personal opinion based on observations and analysis and does not represent my employer in any way.

I’ve been reading the ESB Post 2025 submissions and most feature support for Renewable Energy Zone (REZ) development, but there’s not much clarity on who should pay for it and how to design it. In fact, there’s no real definition of what a REZ is!

Ultimately there’s a disconnect between “more transmission” which is what we need and “doing a REZ”. There’s a lot of focus from everyone on theoretical scenarios in which bad investments happen, rather than focus on how to maximise benefits in the design phase. For example, the ESB are thinking about how they can stifle generators outside a REZ, even though those generators may be better projects than ones in the REZ. This comes from developers saying they don’t want to have their REZ entitlements eroded by generators connecting elsewhere.

Let’s start with the concept of a REZ - what is a REZ anyway?

What do we actually want in a high renewables grid?

One way to conceptualise a REZ is as a radial line encompassing the functions of a baseload generator. There’s wind, solar and storage within a neat package, outputting familiar functions as the current coal fleet does.

This is not an efficient or least cost solution, although easier to conceptualise. Radial lines are less reliable and provide fewer flow paths for generation. This also means a larger amount of congestion or storage is required to improve utilisation of the line, either of which results in higher cost energy.

Instead of conceptualising REZs let’s consider existing successful generation zones. They have an energy resource, thoroughfare to/between loads, and general open access for generation. An extension of the shared network, not a distinct feature. Existing generation zones have 3 or more strong, redundant, and often geographical spread lines to carry flows to load centres.

We have a long, stringy grid with weak points that could be improved for security/reliability and also to increase access to renewable resources. This augmentation is necessary given coal generators are coming to the ends of their lives, and understandably consumer groups want to know that new assets will be well utilised.

Germany and Denmark are building a clever example: they built a link connecting their countries to three offshore wind farms in the Baltic Sea allowing maximum utilisation of the line. At high wind energy is exported to both regions, at moderate wind it is exported to the higher priced region, at zero wind the line acts as an interconnector between regions.

For our high renewables future, what are the ideal characteristics for the network augmentations?

  1. Windy. We need a diverse range of good wind resources, ideally about 500 km away from each other to catch the edge of weather systems which provides an occasional source of anti-correlation. Solar resource is ubiquitous anyway, and we can top utilisation up to the brim with a little solar in the gaps. Building transmission solely to access solar resource will mean low utilisation and higher transmission costs to consumers.
  2. Allows flow between loads. This allows for trade & reliability, and redundant connection significantly reduces security risks on interconnectors. More trade is necessary in future because the renewable resources of a single state are too highly correlated.
  3. Non-radial, geographically separated lines. Radial lines and lines in close proximity are more likely to cause a major contingency.

Where are the opportunities?

No alt text provided for this image

This is a stylised Excel depiction of the highest voltage lines the NEM. If you imagine it like a rope ladder you can see there are some redundant rungs where a breakage doesn’t result in falling off. But there are quite a few routes where a single rope fraying could topple you.

In blue are the strong generation zones:

QLD has a large one with multiple strong lines to which all the coal is connected – slowly being joined by solar and wind.

NSW has coal north of Sydney, wind near Canberra, and hydro at Snowy. Strong redundant lines the whole way between them.

VIC has a great connection from Latrobe Valley to Melbourne but it’s merely decent in the west.

SA has successfully converted the strong, redundant lines that once transmitted coal to now carry wind and solar.

What could we build out to make the NEM stronger while also gaining new supply?

The SA-NSW Interconnector (SNI) is going ahead and provides an interesting new loop. In terms of connections it ticks the box, but the wind resource isn’t so diverse so let’s give it 2.5 out of 3 from the characteristics above.

VNI west is coming up next, strengthening Melbourne-Snowy. It provides necessary redundancy for the overworked interconnector and is safely away from bushfires. It can help Snowy get peaking capacity into VIC and opens up existing wind zones (no diversity). Overall, it’s still really strategic, but we should stick to 2.5 stars.

QNI Major comes later, but it another great option because it conveniently encompasses the New England REZ planned by NSW, as long as the path is through the windy tablelands. This one gets the full 3 stars because the wind unlocked in northern NSW/southern QLD is quite distinct compared to other options. If NSW want 8 GW up here, they should probably also run a third interconnector to carry all that flow.

Basslink2 likewise gets 3 stars because TAS wind is substantially different to other regions. Ideally it wouldn’t connect to Loy Yang to provide some more security, otherwise we should downgrade it to 2 stars.

Not on the cards at the moment, but a second VIC-SA interconnector could be built as an extension of the Ballarat-Bulgana upgrade. This would complete a second Melbourne to Adelaide route and would hopefully capture a slightly different wind regime between the large VIC and SA wind regions. If it just results in more wind in existing areas, it only gets 2.5 stars.

No alt text provided for this image

With all our upgrades we’ve got a much stronger rope ladder. We’ve got more opportunities to connect generators, and more opportunities to share generation between regions – reducing curtailment of renewables and reducing peaking capacity requirements. Large generator trips are no longer catastrophic as we have redundant lines and generators in other areas.

Who plays and who pays?

We need a federal package to help rollout this infrastructure because nobody wants to handle the risk. Really this is the only successful way we’ve done nation building infrastructure projects before. All the historical generation zones relied on government funding to build out several redundant lines at once. The model used in the past has been to build it and socialise the costs later once the benefits are established. The states can’t do it alone, and most of the value of new transmission is diffused across the entire NEM not just in local pockets.

TransGrid raised some interesting points in their P2025 submission, mentioning that “the wider economic benefits [on top of RIT-T] … could inform contributions from taxpayers for the ISP projects.”

They go on to mention the short horizon in the RIT-T for measuring benefits compared to asset life and the disparity in discount rate for consumers, and a social discount rate governments would normally consider for infrastructure. In this regard, the federal government could realise the long term benefits of transmission by underwriting the difference in NPV of a 3% discount rate over 50 years vs. a 6% discount rate over 25 years. This could reduce initial consumer payments by almost 50%.

I’d like to add to this that the federal government is a major beneficiary of nation building infrastructure like this because two thirds of electricity consumption is by businesses, and any savings businesses get translate into higher corporate taxes.

Having federal funding assistance avoids a major issue unfolding which is that consumer groups don’t want to pay for transmission*. Even though the benefits of increased supply competition swamp the costs of transmission, consumers (and states) don’t want to risk that new transmission is a white elephant.

To that end governments and regulatory bodies are trying to put some of the cost on generators (even though it’s more costly to consumers this way). The generators in turn are asking for rights to that transmission because they don’t want freeloaders given use of the transmission they helped fund.

This in turn is encouraging the ESB to progress the latest incarnation of COGATI, with a new addition to prevent anyone connecting who isn’t “part of the plan”. The ESB proposes that existing generators get a form of grandfathering on access and are no worse off, new generators in a REZ get some kind of rights and are better off, and new generators outside a REZ get no rights - and the basis risk of LMP. This means a new generator outside a REZ is significantly more difficult to finance as you cannot guarantee you can meet a contract with a customer and you could often be paid nothing for electricity that was happily used by consumers.

This is a terrible waste as many good projects would not proceed and it reduces the options for new supply. This inevitably ends in higher costs to consumers, encourages rent seeking from the lucky oligopoly generators, and means higher emissions as the gaps are filled with gas.

In fact, the proposal means that as existing development projects will be riskier once the new rule comes in and we may face a supply crunch where developments in prescribed REZs don’t exist, but other good projects are struggling to gain finance.

If we want to progress to a strong, effective mesh network it will be really tough to determine who’s rating belongs where. Any redundant loop will open up capacity on parallel and adjacent lines, making it difficult to determine the border of a REZ.

There is a risk of course, that someone builds an asset that produces an outsized growth in congestion and harms otherwise efficient investments. If we want a mechanism to block the most inefficient generators then let’s do that directly, instead of blocking anything not chosen as a winner by central planners or governments.

This means providing existing or committed generators with a weak entitlement that congestion will not be allowed to grow excessively. To be clear, consumers always benefit from new supply even if it is inefficient, but in the long run a more stable investment environment with a greater pool of supply is a stronger lever on prices.

The benefit of open access is that it can allow the optimum mix of generation to evolve over time. The more rights we give generators, the less fully we can utilise the transmission network, and the more supply is inhibited, both of which hurt consumers. Protecting consumers from short term mismatches between the cost and value of transmission is not best handled by generators with higher cost of capital, but governments who can absorb this risk against the long term benefits of an efficient, effective, and open platform for trade.


*The current NEM transmission network is worth about $20b. A major overhaul of $10b** would massively improve the network. That’s a 50% increase in the regulated asset base which would increase the cost per kWh by 1 cent all things being equal.

However, if we start electrifying industry, vehicles, and heating the increase in electricity demand will also reduce the per-unit cost of transmission. In AEMO’s Step Change scenario, EVs alone would provide an 11% increase in demand by 2030.

** fun comparison – Australia spends $30b each year on superannuation fees. 1.5 times the total replacement cost of transmission. Yet we fret about spending anything on critical infrastructure.


Gordon Davis

Director, Risk Advisory at EY

3 年

Interesting analysis. It highlights the need for the federal government to take a strategic, long term view of the energy future which they have stubbornly refused to do. This type of investment in capacity building could be a way for them to stay away from the decarbonization messaging they seem to want to avoid, and promote job growth at the same time. It would be good to provide the capacity and then let the market lead the way.

Catherine Way

Co-Vice President Australia (Interim)

3 年

Great analysis, Tom.

回复
James Ha

Head of Research, APAC at Aurora Energy Research

3 年

10/10 for the title alone. I saw it in WattClarity’s daily wrap and had to check it out. Very much agree on the challenges for getting major transmission projects across the line when the benefits are spread across the NEM! Resolving the “who pays” question should be a top priority for governments, especially the Commonwealth.

Jevon Carding

Electrifying Ideas

3 年

Well said Tom. I agree that transmission development is unnecessarily inhibited by fear of over-build. Consumers also face a risk of increased cost arising from under-build, but our processes for approving and funding infrastructure are skewed toward policing the over-build risk with little attention paid to avoiding under-build. Likewise it is fair to challenge proposals to weaken the open access regime. Generation developers find preferential access rights conferred by the proposed REZ framework attractive because they fear that transmission development will not keep pace with generation development. If investors in generation had reasonable confidence in a robust transmission development program, then they would have less fear of economically inefficient levels of network congestion, and may not feel changes to the open access principle or the marginal loss factor regime were necessary.

Jonathan Ben-Tovim

Principal at ACIL Allen Consulting

3 年

Thanks for this great article Tom. This problem is a good example of a complex problem where a hard systems approach has been used but a soft systems soft systems approach is likely to be more appropriate. For example, the ISP and RIT-T use a hard systems operational research approach to forecast and plan the future transmission development plan of the NEM. However, hard systems thinking does not accurately represent the reality whereby project developers are guided by profit based models (rather than least cost plans) and guided by other economic, political, community and environmental factors. Currently there is no framework to coordinate transmission and generator development and achieve an outcome that is agreeable for all stakeholders. A more holistic soft systems approach whereby all relevant stakeholders (federal and state governments, TNSPs, AEMO, developers and consumers) coordinate and plan project development is likely to improve this situation. We don't need all the time consuming, expensive and complicated mathematical models and forecasts which are going to be inaccurate anyway to identify which lines to build. I think your approach of asking questions as you did in your article to the relevant stakeholders and gaining feedback and consensus is more useful.

要查看或添加评论,请登录

Tom Geiser的更多文章

  • How good are the LNP's nuclear locations?

    How good are the LNP's nuclear locations?

    Peter Dutton dropped his parties nuclear power plant locations this morning. Let's have a look at them and if they are…

    92 条评论
  • Draft ISP 2024 “Hot take”

    Draft ISP 2024 “Hot take”

    Like many of you other nerds I’ve been poring over the recent draft Integrated System Plan (ISP) release and listened…

    25 条评论
  • NEM Weather Relationships

    NEM Weather Relationships

    There goes an argument that because wind and solar is correlated in the NEM that transmission between states is of low…

    10 条评论
  • Timestamping Renewable Energy Certificates is a Bad Idea.

    Timestamping Renewable Energy Certificates is a Bad Idea.

    There a pretty neat idea going around where corporations want to measure the fraction of renewable energy they have…

    31 条评论
  • Cost-based Modelling is Doing Consumers a Disservice.

    Cost-based Modelling is Doing Consumers a Disservice.

    [disclaimer: this is my personal opinion and bears no representation of my employer] The AEMC recently published a…

    17 条评论
  • The clean energy transition won’t run out of minerals.

    The clean energy transition won’t run out of minerals.

    Introduction What do climate deniers, Guardian journalists, nuclear fanboys and resource startup CEOs have in common?…

    30 条评论
  • Fact check: ESB congestion modelling

    Fact check: ESB congestion modelling

    The ESB released the Post-2025 market design advice last week. Accompanying it, is the summary report given to the ESB…

    18 条评论
  • A Climate Policy for Scott Morrison with Zero Cost to the Economy

    A Climate Policy for Scott Morrison with Zero Cost to the Economy

    This is a fun thought experiment on how the Australian Government could produce a climate policy without affecting…

    8 条评论
  • Small Solar Should Embrace Control

    Small Solar Should Embrace Control

    ABC’s 7:30 Report had a piece this week on the plan by AEMO to curtail small rooftop solar installations under certain…

    36 条评论
  • Transmission Regulation is Broken

    Transmission Regulation is Broken

    Australia's transmission investment regulations are not fit for purpose. They never were, but we didn't notice until…

    26 条评论

社区洞察

其他会员也浏览了