The true essence of construction contracts
Osama Saad, MBA, PMP, PSP, CCP, PMI-SP
Reinventing planning and project control. I help planning engineers prepare progress reports in seconds and analyze the project with one click I Power BI, Project Control, Delay Analysis and Claims Consultant & Trainer
The construction industry is very complex and highly competitive. Projects are:
As a result, risks can arise during the pre-construction, construction, and post-construction phases. Some are insurable, such as damages and natural disasters, while others—like delayed site possession or late design changes during construction—are not. A well-structured construction contract is the art of effectively managing and fairly allocating these risks.
Balance vs. One-Sided Contracts
Overloading risk onto one party can lead to disputes, inflated pricing, or project failure. If the employer states in the contract that the contractor will not be reimbursed for any delays related to excavation activities and must manage any unforeseen site obstructions independently, the contractor will account for this significant risk and prepare for the worst-case scenario, which may involve prolonged work periods and the deployment of substantial resources. Consequently, the contractor will submit a significantly higher bid.
To manage this risk, the employer can clarify the scope and include a clause that reimburses the contractor for unforeseen conditions, preventing inflated prices. Similar approaches are used to manage other risks among different parties. These risks include, for example:
Technical Risks
Logistical Risks
Financial Risks
Political & Regulatory Risks
Environmental & Sustainability Risks
Safety & Health Risks
Contractual & Legal Risks
Operational & Execution Risks
Before the relevant clauses are drafted to manage the project risks, the questions below must be answered:
1- Who is in the best position to control or mitigate the risk?
2- What is the financial impact of the risk, and who can best absorb it?
3- What is the likelihood and severity of the risk occurring?
4- How does the risk allocation affect project pricing?
5- What are the legal and regulatory requirements?
6- Can the risk be insured, and who should bear the insurance cost?
7- What are the consequences if the risk occurs?
8- What dispute resolution mechanisms should be in place for risk-related issues?
9- Is the risk allocation approach fair and balanced?
Why do we need a construction contract?
Why can’t we just shake hands? A construction contract is essential due to the inherent conflict of interest between the employer and the contractor:
A well-structured construction contract manages this conflict while also providing a mechanism for handling uncertainties, such as incorporating additional scope through variation orders or amending the contract when an extension of time is granted. Standard FIDIC contracts have become widely adopted because they clearly define responsibilities, have been extensively tested, and are both comprehensive and fair. Even most bespoke contracts are influenced by FIDIC forms. Additionally, particular conditions are added to tailor contracts to specific project needs, local laws, and additional risk management considerations. Drafting a contract involves implementing a comprehensive risk management strategy, structured around the following key stages: Identify, Assess, Analyze and Prepare risk response strategies to mitigate and manage these risks effectively. Ultimately, a contract is the primary tool for risk allocation in construction projects.
Regards,
Construction Consultant at RM Global Consultancy - Consultant to Buildings & Factories L&T - Regional Manager Mumbai L&T
1 天前Hi Osama, I have signed several contract documents and executed projects in millions of dollars. Barring very few, the contract document once signed was put in a shelf and locked and never even dusted till the job was handed over to the client. This is the best way to handle a contract document. When it is a two way business, both parties would like to avoid disputes in their own interests. Only thing, not to keep anything pending. And for some reason, if you are postponing something, it would be better to forget it. Regards Ramesh
Sales Executives Alumin Structures Zim
2 周Very helpful
SBCA Licensed Architect/Engineer, Project Managment, Project Controls Consulting, Cost Consultant, Quantity Surveying, Structural and Architectural Design and Drawing, Building & Town Planning and Projects Control
2 周can we work together on partnership basis on project planning and controls
Great insights on risk allocation in construction contracts! A well-structured contract not only protects all parties but also ensures efficiency and cost control. In our experience, financial transparency and streamlined expense management also play a key role in preventing disputes and keeping projects on track. Looking forward to reading your article!
PMI-PMP? Certified Project Manager | Project Coordinator | Contract Administrator
2 周A contract should indeed be balanced, and contract administration must be conducted fairly and impartially, ensuring fair and reasonable treatment of both parties to achieve a successful project.