Tips for Prospective PMPs - Edition 25
Eddie Merla
PMO Consultant | PMP Trainer and Coach | Co-author of "Communicate, Lead, and Transform" | Speaker | #pmptrainer #projectmanagement
Welcome to the 25th edition of Tips for Prospective PMPs. This newsletter provides tips, advice, and lessons for those project managers pursuing the PMP?.
This edition includes an article on an introduction to procurement contracts for projects and access to 5 practice questions and mini-lessons.
Contracts for Projects
Project managers should be aware of the relevant components of a contract to a project and the various types of contracts that may be used in the procurement of services, products, or solutions.
Term and Completion Contracts
When work is to be provided by the seller, contracts can either be term or completion contracts. Term contracts end when the term has been completed. For example, the buying organization may enter into a contract with the seller to provide consulting services for a six-month term. The contract, in this example, terminates when the six months have expired.
On the other hand, a completion contract ends when the contracted work has been completed. For example, the buying organization may contract the seller to remodel a suite of offices. The contract will not be completed until the suite of offices has been remodeled per the contract terms.
Statement of Work (SOW)
Another consideration for contracts is the statement of work (SOW). The approach to the? SOW may vary depending on the level of detail and planning required. In general, two different approaches to the SOW may be taken:
Three General Types of Contracts
Let’s take a look at three general types of contacts used on projects:
Fixed-price contracts. A fixed-price contract is typically used for a well-defined product or work. The buyer and seller negotiate and agree to a price upfront. The price of the contract is what the buyer will pay and this price will not change unless a change order approved by the buyer modifies the work. The seller’s profit will be included in the price of the contract.
Generally, the seller has more risk in a fixed-price contract. If the work takes longer or becomes more costly than planned, the seller’s profit will be at risk. To mitigate the risk of losing profit or suffering a loss on the project, the seller should ensure that the work is clearly defined in the statement of work. The contract should define any assumptions to protect the seller’s risk.
There are three types of fixed-price contracts:
Cost-reimbursable (or cost-plus) contracts. This type of contract may be best suited where the parameters of the work to be performed are not well defined. This type of contract reimburses the seller for the actual costs incurred on the project plus a negotiated fee or profit. The risk on cost-reimbursable contracts is typically shared between the buyer and the seller. There are three variations of this type of contract:
Time and materials (T&M) contracts. This type of contract may be best suited when the statement of work cannot be defined clearly. This contract may also be useful for contracting a specific type of labor or expertise over a defined timeframe. This type of contract is considered a hybrid type of contract as it typically includes aspects of both fixed-price and cost-reimbursable contracts. Typically, the rate is a fixed price while the term may be open-ended.
The buyer incurs more risk than the seller because the contract tends to be more open-ended and is not tied to a specific outcome. The buyer can mitigate this risk by providing not-to-exceed limits or term limits. For example, a buyer contracts for a specialty engineer at the rate of $200 per hour with a not-to-exceed ceiling of $40,000 or 30 days. The contract terminates when the costs reach $40,000 or 30 days have elapsed, whichever occurs first.
Contracts for Agile Contracts
When contracting for agile projects, the following should be considered:
Summary
When your project can benefit from outside services or contracted support, consider the various types of contracts and the best fit for the work to be performed. Awareness is the first step towards building a buyer/seller relationship.
If you are studying for the PMP? exam, understand the terms introduced in this article and the different types of contracts.
Eddie Merla, PMP
Article 2: Five Practice Questions and Mini-Lessons
Check out our schedule of upcoming PMP? prep training:
#pmp #pmpprep #pmptraining #pmpcertification
Download our free PDF mini-book: Kickstart Your Journey to PMP? Certification