Generate Weekly Schedule inside CMMS

Generate Weekly Schedule inside CMMS

Most sites have fewer planners than they need. And most sites have very large backlogs (of which you can't simply wave a wand and make it go away). And, these backlogs are mostly unplanned. So, what do we do?

The scheduling solution would need to know the craft availability for the coming week. These hours would be by craft and also include any planned absence information.

No alt text provided for this image

Here is a picture showing my preferred process. All work orders must have a "rough estimate" applied based on Lead Craft. This prerequisite means that resource leveling will work.

No alt text provided for this image

The purpose of making a weekly schedule is as follows:

  • Create an agreed-to list of work for an advance period of time. It seems one week out provides the needed forecast time, but not so far out that accuracy is reduced. The goal is an accurate schedule, so that the work force knows this to be absolute truth, and that they should do everything possible to complete these tasks.
  • By creating an agreed-to list of work, you are enhancing departmental and work force coordination; job safety; and optimizing backlog reduction. Operations can evaluate permit requests in advance. Warehouse can stage (and even deliver) materials. And, Safety (HSE) can show up for high-risk jobs having plenty of notice.
  • Schedulers can bundle like work together (even though different work orders) to benefit from one clearance or LOTO.
  • By using the various fields on the work order (such as priority), management is happy that critical work is being performed.
  • The weekly schedule creates a "set of work" (for the week) from which Daily Plans can be created. This set of work should not be altered.
  • By freezing this "set of work", work order compliance can be obtained on the following Monday.

Schedule Generation: You have Choices

This is an advanced process of which there are many prerequisites. From the Doc Palmer book, you will find an illustration showing CREW WORK HOURS AVAILABILITY FORECAST. This form is intended for the Planner/Scheduler to fill out manually each week on Thursday deducting each job for the weekly schedule from crew availability. Well . . . this would be a time consuming process.. An automatic leveling capability is needed to create a "set of work" for the week.

In Summary

There are thousands of sites around the world using asset management systems. Unfortunately, 80-90% have never successfully created an automatic resource-leveled weekly schedule.

Interesting post! I think they key here really is the "Daily review" meeting. This will give everyone in the maintenance department the opportunity to discuss the work that has been planned for the day before but wasn't executed. Scheduling software can help you prioritize, but it's still people who need to execute the work.

赞
回复
John Reeve

Book author, CRL, CMM and CMMS champion.

9 å¹´

concern is valid but...easily addressed. The creator of the schedule sets Availability Factor at some percentage . ..eg 70% But note, there are some Administrators who go off the rails on this and insist on scheduling 100%. Either way it is not a software issue/challenge.

赞
回复
Michael Meehan, CRL, CMM

CEO and Senior Consultant at Reliability Dude, LLC

9 å¹´

There are certainly situations in which "break-in work" can disrupt a detailed, planned schedule. The benefit is that now you still have the planned jobs planned and can "push" them as required to the next slot. This is an exercise in creating order out of chaos and giving up because it's not perfect is the wrong thing to do. The longer you iterate this process, the fewer break-ins you will see, and simply because of the fact that reactive maintenance costs 3 to 4 times what planned maintenance costs, it pays to stick to your guns. I did a calculation at a solar manufacturing facility I worked at, and our reactive costs were 2.75 times our planned costs...and that was in a brand-new greenfield built plant. Imagine the gains in a 30+ year old plant like I am managing now......

赞
回复
John Reeve

Book author, CRL, CMM and CMMS champion.

9 å¹´

thanks Carlos. I did respond to Craig offline. In the AMS I can generate many months in advance for PM or PdM. And these already have future dates - thus not a problem. But..... repair work ...is the challenge. Either way we call this maintenance weekly schedule of which 80% have never succeeded.

赞
回复

要查看或添加评论,请登录

John Reeve的更多文章

  • Company, Community, Country, Planet

    Company, Community, Country, Planet

    "It is not enough to do your best; you must know what to do, and then do your best." // Deming Asset management can be…

    4 条评论
  • Failure Reporting and Failure Analysis

    Failure Reporting and Failure Analysis

    The Asset Manager Has Questions for His Senior Staff What if the Data is Bad? Bad data can be due to poor processes…

    4 条评论
  • Advanced Processes are the Backbone of HRO

    Advanced Processes are the Backbone of HRO

    Webinar Link: https://www.uptimeai.

    3 条评论
  • The Problem with Weekly Maintenance Scheduling

    The Problem with Weekly Maintenance Scheduling

    Most organizations agree that weekly scheduling is an industry best practice. That said, most organizations do not have…

    7 条评论
  • Establish a Reliability-Centric Asset Management System

    Establish a Reliability-Centric Asset Management System

    5 Steps to Operational Excellence The goal of a reliability-based, asset management system is to enhance operational…

    6 条评论
  • The Significance of Chronic Failure Analysis using a Bad Actor Report

    The Significance of Chronic Failure Analysis using a Bad Actor Report

    Synonyms for chronic: recurring, repeating, persistent, lingering, routine, sustained Chronic failure analysis is a…

    4 条评论
  • Do You Have a Defective CMMS System?

    Do You Have a Defective CMMS System?

    Ideally, a CMMS is seen as a critical business system, which means the system is used to optimize ROA, enhance craft…

    3 条评论
  • Is the CMMS Really Too Hard to Use?

    Is the CMMS Really Too Hard to Use?

    Status Quo Fewer than 5% of all companies establish an asset management framework that truly integrates maintenance…

    13 条评论
  • Project Scheduling Requirements for Asset Management

    Project Scheduling Requirements for Asset Management

    How are Asset Management and Project Management Related? The CMMS toolkit includes work breakdown structures and work…

    8 条评论
  • Strategic Roles Are Essential for Continuous Improvement

    Strategic Roles Are Essential for Continuous Improvement

    Background How Can Organizations Add Efficiency and Grow Faster Than the Competition? Any organization that wants to…

    7 条评论

社区洞察

其他会员也浏览了