Time-Current Curve (TCC)
Shailesh Chetty
Electrification Technology Solution & Integration @ Shell | Digital Transformation
Time-Current Curve usually referred as TCC's are primarily used as a tool to verify equipment under protective zone is properly protected and coordinated with the system.
As a part of Protection Study it is desirable to have the IEC/ANSI protection characteristic of the primary and secondary circuit breaker of the equipment which needs to be protected and coordinated with various criteria/operating conditions.
Usually a time current curve (TCC) is plotted at a specified voltage level and contains following information (as a minimum):
- Interrupting time of an overcurrent device Vs Current.
- Continuous rating of various equipment (Rated Current).
- Damage curves (also called as short-time rating) of various equipment (Abnormal Current Vs acceptable withstand duration of equipment).
- Equipment transients (like transformer inrush, motor starting curves at different voltage levels, combined transformer inrush in a bus etc;).
- Available maximum & minimum short-circuit currents.
Electrical networks with different supply (generator & power utility; only generator etc.) the values of SCC may be very different and consequently, the selectivity, make different results.
- Operating time at through-fault current seen by Relay.
As a good practice on the same sheet adjacent to TCC engineer should attach details of Network i.e; Key protection SLD of the equipment indicating following details as a minimum: Tag of Equipment, IED detail, CT ratio, ANSI codes enabled in IED, Main Equipment data, Interconnecting power cable, Bus rating (continuous and short-time) etc.
An example for Color code (for plotting cures of Relay's indicated on a graph for a switchboard) followed when TCC's are plotted
- Black = Branch
- Pink = Largest
- Red = Main
- Blue = Primary Feeder
- Brown = Upstream
Special Comments which are worth mentioning in a TCC:
- Fully selective or partially selective
- Any suggestion to reduce clearing time if any
- Recommendation to change settings from the interface team
Quality Checks in TCC:
- Nomenclatures for each breaker / Relay Tag on the Final/original report should match with information mentioned in final As-built drawing of switch-gear (i.e; ensure capturing right manufacturer details).
- Settings as captured on Co-ordinations graphs should be within range properly rounded-off to the nearest value (select-able in relay-configuration).
- When mentioning settings in report ensure the ANSI codes are Enabled & programmed in relay to avoid surprises while commissioning at site.
Revised & Updated on 08/02/2015 based on comments received :)
Shailesh Kumar Chetty
Orang lain bisa saya harus bisa
1 年Shere applycation TCC Schneider
Power system studies | PSCAD | PSS-E | TARA | TSAT | P&C | Electrical Design
3 年Simple and informative article. Thank you for sharing. Shailesh Chetty
Student(in), Aachen
7 年Hi I have a question to TCC. Is there a formula to how to plot them? Or what data points/parameters do I need in order to plot them?
Electrical/Electronic Manufacturing Professional
8 年Hi sir, i am doing research in microgrid protection.can you help me?
Senior Marketing & Business development professional in Electrical & Automation business
10 年Very good article