  • Someone may think is just a simple simulation but during simulation, you will notice or discover you are doing other types of phenomena simulation required.
  • As we can see in this post for point-on wave simulation, will notice other phenomena like ferro-resonance, and zero-missing.
  • Thus, this post is called Subtleties Inside Simulation.

POW Switching Controller

  • In certain cases, surge arresters are not suitable mitigation method to avoid slow front over-voltage SFO or switching over-voltage SOV.
  • Point of wave switching eliminates any transient over-voltage at the line remote end, in terms of equipment aging point of view.

SOV 1.8 PU at remote end even with SA


The multiple-run component is used for 100 runs for POW switching


Phase-A switching at zero-crossing point on the wave

  • Once phase-A switched at 0.2 sec, phase-B switched 120 deg as phase shift.
  • In terms of time, 120 deg in a 60Hz system is 5.3ms {0.2+0.0053}

Phase-B shifted 120 deg or 5.3ms in the 60HZ system


  • As the upstream circuit breaker operates in single-pole operation for POW switching, engineering judgment for ferro-resonance observation is required to avoid reactor saturation.
  • Also, you can notice zero-missing phenomena in the reactor current due to a compensation ratio of more than 50%.

Also, during the simulation, please observe zero-missing phenomena of the reactor current (more than 50% compensation)


Reactor magnetizing parameter V-I