Sub-clause 3.5 of FIDIC 2017 (Engineer's Instructions) and Sub-clause 3.3 of FIDIC 1999 (Instruction of the Engineer)
Rajeshkumar (immediate deployment) Rajendran LLM LLB BE MRICS MCIArb
A senior leader with an impressive background in Commercial, Contracts, & Claims Management, overseeing multimillion-dollar projects. With two decades of experience, the majority gained in Dubai, Qatar & Saudi Arabia.
The position concerning the Engineer's Instruction (EI) underwent some changes from the 1999 edition to the 2017 edition of the FIDIC contract. In the 1999 edition, the default position was that an EI was not considered a Variation unless stated otherwise. The Contractor could rely on the Engineer's assessment and was obligated to comply with the instruction promptly. If the Contractor later discovered that the EI constituted a Variation, they were required to give a Notice of Claim.
In the 2017 edition, an additional obligation was placed on the Contractor. They were now required to assess whether the EI constituted a Variation. If it did, the Contractor had to give a Notice to the Engineer before commencing any work related to the EI. While there were no expressed sanctions for the Contractor's failure to give such a Notice, it could potentially create a hurdle for the Contractor's claim.
The modified position in the 2017 edition may have diluted the Engineer's responsibilities owed to both the Employer and the Contractor. It could also potentially encourage ill-practices, as some Engineers might give EIs without stating that they constitute Variations, despite knowing otherwise. Similarly, Contractors might give unwarranted Notices. These practices could negatively impact the project.
The benefits of the modified position for the Employer are questionable, and it seems to provide no clear benefit to the Contractor or the overall project. It is important to consider the potential implications and effects of these changes on the parties involved.
Sub-clause 3.5 of the FIDIC contract states that the Engineer may issue instructions to the Contractor that are necessary for the execution of the works. The Contractor is obligated to comply with these instructions, unless they constitute a Variation, do not comply with applicable laws, reduce the safety of the works, or are technically impossible. If the Contractor believes any of these conditions apply, they must give a Notice to the Engineer with reasons before commencing any work related to the instruction. If the Engineer does not respond within seven days, the instruction is deemed revoked, and otherwise, the Contractor is bound by the Engineer's response.
If an instruction given by the Engineer constitutes a Variation (a change to the scope or character of the Works), the procedures outlined in Clause 13 (Variations and Adjustments) of the FIDIC 1999 Red Book will apply.
领英推荐
Some differences between sub-clause 3.5 of FIDIC 2017 (Engineer's Instructions) and sub-clause 3.3 of FIDIC 1999 (Instruction of the Engineer) are as follows:
Similarities between the two sub-clauses are as follows:
In summary, while there are similarities between the two sub-clauses, there are some differences as well. The FIDIC 2017 edition explicitly addresses the situation where an instruction is deemed a Variation, while the FIDIC 1999 edition refers to Clause 13 for Variations. Additionally, the FIDIC 1999 edition includes a provision for confirming oral instructions in writing, which is not present in the FIDIC 2017 edition.
Associate Director - Procurement & Contracts | Master of Laws (LL.M.)
7 个月Good article Rajesh