Shaft Construction and Support Methods

Shaft Construction and Support Methods

The importance of minimizing public impact and need to avoid interfering with other structures and utilities in the area often requires the design and construction of vertical shafts during a tunneling project.

These shafts can be used permanently for ventilation, elevator access, utility pipelines, underground storage, etc. or operated temporarily to provide access during construction. Temporary shafts are typically backfilled when the tunnel is completed.

Two of the most important elements in design and construction of shafts are the method of excavation and technique used to support the shaft against different design loads, such as earth pressure, groundwater, and live and seismic loads.

Shafts excavation in soft ground is normally done with a crane using a clamshell bucket to hoist the muck from the shaft and drop it into a hopper/stockpile or directly into a truck on the surface. Shaft excavation in rock is usually performed by the drill-and-blast method.

A quick description for some of the more common methods follows.

Soldier Piles and Lagging are an earth retention technique that uses vertical steel piles with horizontal lagging to retain soil. Piles are drilled or driven at uniform intervals along the planned excavation perimeter. Lagging (wood, steel. or precast concrete panels) is inserted behind the front pile flanges as the excavation continues.

Liner plates provide a relatively light-weight, easy-to-handle, safe support for soft ground excavation (typically for smaller shafts). The liner plate assembly distributes and transmits the load to the surrounding earth. The plates can be galvanized or coated, and holes with plugs can be included to facilitate the grouting between plates and the ground.

Caissons are relatively watertight retaining structures and an ideal concept for shafts in wet ground or underwater situations. When creating the caisson shaft, typically cast-in-place or precast concrete sections/segments are constructed from the surface. Once the caisson reaches a set height, the concrete forms or segments are added to the top to create the next section (lift) of the caisson. Precast segments are used more widely in Europe. The segments are like the ones used in the TBM tunnels, bolted and gasketed together to form a ring. Rings are added at the top when used as a caisson or at the bottom when the ground has a safe stand-up time.

Rock Dowels/Bolts (+ Shotcrete/Mesh) are used for the construction of shafts in rocky ground conditions. Typically dowels or bolts are drilled radially from the shaft in calculated horizontal and vertical distances to provide reinforcement for the rock. It is common to use shotcrete (strengthened with wire mesh or fibres) to further secure the rock face.

Sheet Pile Walls are constructed by driving prefabricated sections of sheet materials with an interlocking edge into the ground. Soil conditions may allow for the sections to be vibrated into the ground instead of it being hammer driven. The full sheet pile wall is formed by connecting the joints of adjacent sections in sequential installation. Sheet piles are most commonly made of steel but can also be formed of timber or reinforced concrete.

Secant Piles are a series of drilled columns constructed in such a way that the columns overlap each other to form a continuous wall for the shaft structure. The construction sequence involves drilling every other column (primary) and then returning after the concrete has partially set to drill and pour the overlapping column (secondary) between the primaries. The concrete in the columns can be all low strength, all high strength, or a combination of low strength primary and high strength secondary. Steel piles or reinforcing steel are typically placed in the secondary columns.

The Slurry Wall method is typically used to build shafts through a series of reinforced concrete walls typically in areas of soft earth close to open water, or with a high groundwater table. Before the construction of slurry walls, it is common to use guide walls to facilitate proper vertical and horizontal alignment for slurry wall excavation. The guide walls also prevent soil loss near the surface and act as containment for the introduction of bentonite slurry. Care is generally required to obtain acceptable verticality (~0.5% is typical.

Ground Freezing is a shaft construction technique used to provide temporary earth support and groundwater control when other conventional methods, such as dewatering, shoring and grouting, or soil mixing, are not feasible. The ground freezing process involves drilling and installing a series of closely spaced pipes and circulating a coolant through them. The refrigerated coolant extracts heat from the ground, converting the soil pore water to ice resulting in an extremely strong and impermeable material.

Conclusion

Regardless of what method of construction is employed, there are numerous other issues to be considered before the design of the shaft is finalized. From the logistics point of view for example, the location of the shaft in relation to tunnel alignment, muck transportation routes, and sensitive buildings in the area, all need to be looked. Technical challenges include the estimation of groundwater seepage and methods of dealing with water inflow, such as excavation of sump and the use of a water pump with enough capacity to handle the maximum anticipated flow.

 Suggested Readings and References:

R J. Jenny, M. Grieves, J. Bickel - Tunnel Engineering Handbook – 2nd Ed. | Websites: [dsitunneling.com, kellerfoundations.ca, deepexcavation.com, schnabel.com, deltace.com, groundfreezing.com] | K. M. Nemati [Temporary Structures - UOW] | J. Rush - Shaft Design and Construction | V. Luongo - Shaft Construction in Toronto


#tunnels #tunneling #tbm #construction #design #shaft #mining #engineering #trenchless #shaft #construction



Dhaval Desai, P.Eng, PMP

Civil Discipline Manager - Integrated Design (Energy and Resources - North America)

4 年

Always an interesting read. Not just this one but previous ones too. Provides an excellent overview.

Eric Bennett

Eric Bennett, Consultant, and President and Owner, Erock Associates llc

4 年

A nice overview!

回复

要查看或添加评论,请登录

Keivan Rafie的更多文章

  • Slurry TBMs

    Slurry TBMs

    Slurry TBMs are considered “soft ground” tunnel boring machines (along with earth pressure balance TBMs) that use…

    2 条评论
  • Horizontal Directional Drilling (HDD)

    Horizontal Directional Drilling (HDD)

    In the tunnel and civil engineering world, finding better methods to complete projects with minimal impact on the…

    5 条评论
  • Trenchless Methods: which one works best for your project?

    Trenchless Methods: which one works best for your project?

    Trenchless methods are ways to install, repair, and renew underground pipes, ducts, and cables with minimal or no…

    1 条评论
  • Sequential Excavation Method Tunneling (SEM)

    Sequential Excavation Method Tunneling (SEM)

    Sequential Excavation Method (SEM) is a type of tunnel design and construction that started to gain popularity in the…

    4 条评论
  • Auger Boring

    Auger Boring

    Horizontal auger boring, also known as auger boring, horizontal earth boring, or jack and bore, is one of the most…

    4 条评论
  • Tunnel Survey and Alignment Control

    Tunnel Survey and Alignment Control

    Survey and alignment control is an essential part of tunnel projects all around the world. Projects need to apply such…

    5 条评论
  • Tunnel Lighting

    Tunnel Lighting

    The safety of a transportation tunnel depends highly on the ability of the motorists to see the interior and objects in…

    1 条评论
  • Dry Shotcrete

    Dry Shotcrete

    Dry Shotcrete, then known as “gunite”, was invented in 1907 by American taxidermist Carl Akeley to repair the crumbling…

    2 条评论
  • Understanding Dust in Tunneling and Underground Projects

    Understanding Dust in Tunneling and Underground Projects

    The natural atmosphere that we breathe contains not only gaseous components but also large numbers of liquid and solid…

    5 条评论
  • Risk Management for Tunnels

    Risk Management for Tunnels

    All tunnel projects face unknowns and uncertainties during planning, design, construction, and/or operation. With…

    11 条评论

社区洞察

其他会员也浏览了