Running a Target Value Delivery Sprint
BACKGROUND
The owner created a strategic projects group to deliver three replacement hospitals. The project team used Last Planner System (LPS), A3 Thinking, and Target Value Delivery (TVD) to seek sound outcomes in project schedule, project decision-making, and project budget. The same design team moved from the first to the second project, with the opportunity to build on successes and lessons of the previous project.
OBSTACLE
The team from Replacement Hospital 1 achieved excellent results in LPS and A3 Thinking, but struggled to achieve any savings through their TVD effort. When the client presented the project to the Board they were instructed to reduce the cost by $50 million. Also, neither project was under an IPD contract with profit at risk, making TVD more difficult.
APPROACH
We rolled out the TVD challenge to the team on Replacement Hospital 2:
We developed and promoted standard TVD work in the cluster groups to drive the effort:
We facilitated TVD ideas workshops in the cluster groups
领英推荐
RESULT
Over the 8-week period, the team came up with over $35 million of potential savings ideas and were able to convert $22 million into savings to the project. The team continued the effort after the TVD Sprint and lowered the cost further.
LESSONS LEARNED
The owner truly supported TVD. The project team had excellent access to decision makers with the right people in place to make financial decisions on behalf of the project.
RECOMMENDATION: Ensure engagement of the owner with financial authority to make decisions?
Design to a detailed estimate. The designers got on board and were effective. They routinely generated millions of dollars of savings ideas and worked diligently to convert ideas into actual savings.?
RECOMMENDATION: Prepare designers for frequent sharing of incomplete information and encourage them to design to an estimated allowance
True continuous estimating is crucial. The trades actively participated in the effort and became efficient at estimating with incomplete information instead of waiting for packages. RECOMMENDATION: Coach the trades to price based on discussions, criteria, and past experience so ROMs can be developed quickly
Construction industry business leader | Owner’s advocate | CMAA Certified Instructor | Story teller | Published author
5 个月Great post. Thanks for sharing, Romano.
Lean Project Cultures result in Respect, Greater Client Value, Increased Profits, Less Waste and Happier Lives
5 个月What a great blend of approaches/tools! Thanks, Romano!
Project Executive
5 个月I like the idea of the “sprint”. Nice report and love the tips. Thanks for sharing, Romano.
Senior Designer, LEED AP ID+C
5 个月The sage has spoken. I appreciate what you're releasing from your well of wisdom!