A robust design and certification methodology for installing foundations of geographically distributed infrastructures
Ehsan Moradabadi
CEng MIEI | PhD in Civil Engineering (UCD) | Registered Geostructural Engineering Consultant | Technical Design (Geotechnical and Structural) | Feasibility Studies | Team Building | Project Management | Training
Assume that you have a series of foundations (e.g. foundations of bus stop poles; foundations of #windturbines or ESB poles, etc.) distributed in a large geographical area (e.g. a county, a country, or a large area of the ocean), how is it possible to ensure that the design output would be safe and also cost effective?
One may say that the worse case design scenario can be resulted a safe output. However. It is obvious that the result is not optimised. On the other hand, an engineer may say that having proper design input parameters give you different design options making the output optimised. The question then arises how we can manage gathering the design parameters in a proper way and design some options on one hand and ensure that the design options will be properly installed/constructed in different geographical points that may not be possible to properly survey in advance, on the other hand.?In other words, a robust design and construction of?geo-structures distributed in a very?large geographical area rely on the harmonised contribution of all different parties involved in the project. This is not achievable without having a systematic approach in design and to arrange the required interaction between PSDP (project supervisor for the design process) and PSCS (project supervisor for construction stage) and involving Health Safety and Environment (HSE) concept in all design and construction steps of the project.
The below procedure is a robust design methodology suggested by the author under directorship of David Lally to Transport Infrastructure Ireland for installing bus poles distributed in a large #geographical area of Ireland and it was successfully implemented. The similar methodology can be adapted for installing foundations of #windfarms or other geographically distributed #infrastructures .
Description of the proposed design methodology
Regarding the number of the bus stop poles and their distribution in a large geographical area, collecting all design input data and prediction of geotechnical behaviour at the beginning of the project are difficult. To overcome this, according to Eurocode 7, an ‘ observational method’ (also known as ‘learn-as-you-go method’ in geotechnics) can be employed for the project. This helps that the project economically executes due to increasing knowledge of the properties and behaviour of the ground.?
Figure 1 shows the proposed, designed methodology for the project. The project starts with the reviewing all available information provided by the client. This can be including (but not limited to):
1- The coordination of the poles?
2- Conceptual design drawings
3- Clients criteria for design and construction
4- Acceptable design regulations and standards
5- Vendor lists and information
6- Products/material specifications and installation methods
7- Traffic information?
8- Previous available design reports or drawings (good practices)
A desk study is necessary for collecting essential data for designing the foundations and the investigation program. The examples of information and documents that can be used for providing a desk study report include:?
1- Local climate condition
2-?Characteristic wind pressures
3- Topographic maps
4- Previous experience from the area (i.e. consulting with local governmental offices, City Councils, local labs, etc.)
5- Previous investigation close-by to the location of the bus stop (i.e. collecting geotechnical, geological and hydrological information from GSI, EPA, CFRAM etc.)
6- Buried services (i.e. collecting data from local agencies, city councils or online services)
7- Road geometry and traffic consideration for each bus stop
8- Previous geotechnical investigation in the area
The desk study helps to screen the relevant data for each bus stop and provides pre-design information. In case the desk study shows that more information may be needed for the design process, a rapid site visit will be executed for a specific area or a bus stop. The rapid site visit does not include the detail site investigation. To avoid any askew in the design process, the collection of data and processing them will be according to acceptable standards and regulations. The below codes are acceptable standards, can be used for the project:
? Eurocode 1- Actions on structures
? Eurocode 2- Design of concrete structures
? Eurocode 3- Design of steel structures
? Eurocode 7-Geotechnical design
? BS EN 40- Lighting column (Design and verification, the specification for characteristic load)
? AA-STR-06004 and 06028 Early thermal cracking of concrete
? AM-STR-06007 The assessment of reinforced concrete half-joints
? AM-STR-06038 The management of sub-standard road structure
? AM-STR-06042 Structural review and assessment of road structure
? AM-STR-06051 The conservation of the road structures
? AM-STR-06052 The protection and repair of concrete road structures
? CC-GSW-01500 Guidance on Specification for Traffic Control and Communications
? TII Specification for Works Series 000 to 1700?
? TII Specification for Traffic Control and Communications
领英推荐
? TII regulations and guidance for Drainage?
? TII regulations and guidance for Ducts
? TII regulations and guidance for Pavement?
? Other relevant TII documents
Following the desk study and a rapid site visit, a pre-design process is necessary to:
1- Specifying rules for the design of foundations and repair of previous pavements or structures affected by the new construction
2- Reviewing the design concept according to the regulation and available concepts or previous design practice provided by the clients?
3- Specifying design parameters
4- Categorising regions for a group of bus poles based on site characteristics achieved in the desk study process
5- Specifying required tests and validations
6- Planning of new site investigations for each pole and region (see next section for more detail)
The pre-design process provides a basis for developing modelling scenarios of the main design process.?Different scenarios are developed based on soil conditions (categorised during desk study for a group of poles), the geometry of the bus stops and loading cases and values (especially regarding the wind load characteristic value of each bus stop /region of the group of bus stops). The design output consists of design alternatives, drawings, schedules and diagrams for each alternative and relevant design restrictions and considerations.
Regarding different scenarios and the existing uncertainty in the ground conditions of each or group of bus stop poles in different regions, the design specification, sizing and considerations for construction phases can be different. Thus, the design output includes different alternatives for sizing of foundations, specifying the reinforcement, and so on. The suitability of each alternative for each bus stop can be proved after site investigation and surveying during the construction phase. The arrangement for interaction between PSDP and PSCS to prove the suitable alternative for a specific site is described in the next sections. The designer certifies the design and provides the inputs information for risk assessment. This can be done through issuing design schedules, reports or design certification forms.?
Subsequently, a design risk assessment is proceeding for each alternative to identify the hazard during the construction period and to provide measures for eliminating the hazard or reducing the risk of construction to an acceptable level. This process includes planning for safety and health and describing the way that measures of safety and health plan would be controlled. In case the project supervisor for the design process (PSDP) was ensured about safety in design, the design will be issued for approval to PSCS and the client representative (if needed). This process may include providing safety assessment schedules, reports and certification forms.
Notably, the design is not issued for construction, unless a new site investigation, described in the next section, prove that the ground condition of a target bus stop (i.e. executed for construction), is suitable for one of the pre-defined design alternatives.
In case the new site investigation shows that one of the design alternatives is appropriate regarding the ground condition, the design is eventually issued for construction. This process may be needed a post-validation of design and providing as-built drawings, regarding the condition of the ground and other constructional issues. While there will be extra attention to provide suitable design alternatives according to information reviewed during the desk study process, it is possible that the site investigation shows that none of the pre-defined design alternatives is suitable for a specific bus stop, considering the nature of proposed method (i.e. observational).?Meanwhile, the design needs to be revised based on the new geotechnical site investigation and is issued for construction only after reviewing a new risk assessment.?
Proposed surveys and investigations
As aforementioned above, the suggested observational method for the project consists of surveying and geotechnical investigation during the construction period.
A preliminary survey executes during the construction period for each bus stop to collect all the necessary physical information and details of topography and drainage. Considering the buried services for each bus stop, the location of the bus stop is firstly prepared. This may include a minor site levelling or a slightly deep excavation, regarding the design considerations issued for the location.
During site preparation, detailed geotechnical data are collected using a static cone penetrometer (i.e. by using an AMS static cone penetrometer). The static cone penetrometer provides an in-situ measurement for soil consistency. The result can be reported as standard penetrations (Test N values) that are convertible to strength (unconfined compression) and cohesion of the soil or CBR values. The proposed in-situ test is also helpful for verifying the suitability of the hard stand of a bus stop after construction.
The above data in addition to a detailed description of the soil, drainage conditions and buried services and topography, etc. are referred to the designer/ PSDP for reviewing. As there is a database for the pre-assumed conditions of each bus stop (collected during the desk study process), the new survey enables comparing of observed ground parameters with the presumed conditions. Subsequently, as mentioned in the previous section, providing one of the design alternatives was suitable for the site condition, the designer/PSDP issues the final design for construction.?
Arrangement for obtaining any necessary consents
During the desk study process, the arrangement will be necessary to collect design data from:
Arrangement for inspection and certification of the works
The periodic inspection and certification of the project will be done by the PSDP as below:
Arrangement for interaction with the PSDP and the PSCS
A project supervisor for the design process (PSDP) is appointed for the project to ensure the coordination of the work of designers throughout the project. Satisfying HSA (health and safety authority) criteria to ensure safety in different aspects of the project, the PSDP 1) identifies the hazards, 2) guides designers for eliminating the hazard or reducing the risk, 3) communicates with the project supervisor of construction stage (PSCS) regarding safety and health plan and 4) notifies the authority and the client of non-compliance with any written issued directions.?
Regarding the suggested methodology in previous sections and HSA criteria, the PSCS and the PSDP interact to ensure the safe managing of the project in below areas:
Figure 2 shows a sample design output of the design.
Figure 2- A sample of design output (the geographical coordinations and bus stops were masked for the purpose of this article)