RO System Startup Checklist & Procedure

RO System Startup Checklist & Procedure

No alt text provided for this image

□ Corrosion resistant materials of construction are used for all equipment from the supply source to the membrane including piping, vessels, instruments and wetted parts of pumps

□ All piping and equipment is compatible with designed pressure

□ All piping and equipment is compatible with designed pH range (cleaning)

□ All piping and equipment is protected against galvanic corrosion

□ Media filters are backwashed and rinsed

□ New/clean cartridge filter is installed directly upstream of the high pressure pump

□ Feed line, including RO feed manifold, is purged and flushed, before pressure vessels are connected

□ Chemical addition points are properly located

□ Check/anti-siphon valves are properly installed in chemical addition lines

□ Provisions exist for proper mixing of chemicals in the feed stream

□ Dosage chemical tanks are filled with the right chemicals

□ Provisions exist for preventing the RO system from operating when the dosage pumps are shut down

□ Provisions exist for preventing the dosage pumps from operating when the RO system is shut down

□ If chlorine is used, provisions exist to ensure complete chlorine removal prior to the membranes

□ Planned instrumentation allows proper operation and monitoring of the pretreatment and RO system

□ Planned instrumentation is installed and operative

□ Instrument calibration is verified

□ Pressure relief protection is installed and correctly set

□ Provisions exist for preventing the permeate pressure from exceeding the feed/concentrate pressure more than 5 psi (0.3 bar) at any time

□ Interlocks, time delay relays and alarms are properly set

□ Provisions exist for sampling permeate from individual modules

□ Provisions exist for sampling raw water, feed, permeate and concentrate streams from each stage and the total plant permeate stream

□ Pressure vessels are properly piped both for operation and cleaning mode

□ Pressure vessels are secured to the rack or frame per manufacturer’s instructions

□ Precautions as given in Loading of Pressure Vessels (Section 4.1 & 4.2), are taken

□ Membranes are protected from temperature extremes (freezing, direct sunlight, heater exhaust, etc.)

□ Pumps are ready for operation: aligned, lubricated, proper rotation

□ Fittings are tight

□ Cleaning system is installed and operative

□ Permeate line is open

□ Permeate flow is directed to drain (In double-pass systems, provisions exist to flush first pass without permeate going through the second pass)

□ Reject flow control valve is in open position

□ Feed flow valve is throttled and/or pump bypass valve is partly open to limit feed flow to less than 50% of operating feed flow


Source: www.watertreatmentguide.com

Josphat Njuguna

Graduate Chemical & Process Engineer |EBKGE

1 年

Very informative

回复
Tina Deng

RO&NF Membrane and Sheet Leader Manufacturer,[email protected],M.:+86136 6739 3762

4 年

Hi , dear Ghulam Rabbani, please kindly consider KeenSen RO & NF membrane in the future projects ,Welcome contact : [email protected] , Mobile: +86136 6739 3762

Muhammad Ali

HVAC, Solar, LV, BMS and Utilities (Sale & Services)

4 年

Informative

super song

worm gear wafer butterfly valve,flange butterfly valve,electric,pneumatic butterfly valve manufacturer

4 年

congratulation

Mohamed Thahir Sheik

Sr.Mechanical Engineer at KEO International Consultants

4 年

congratulation

要查看或添加评论,请登录

Ghulam Rabbani (??? ?????) ???? ???? ????的更多文章

社区洞察

其他会员也浏览了