Risk Based Maintenance: Slash PM Workloads by up to 40%

Risk Based Maintenance: Slash PM Workloads by up to 40%

As maintenance practitioners, we have a responsibility to make the most out of our scarce resources. Especially since maintenance is often subject to pretty tough budget cuts. We need to be as efficient as we can when it comes to our preventive maintenance. That’s why good preventive maintenance programs don’t try to fix everything. They are risk-based.

In this article, I want to discuss what Risk Based Maintenance (RBM) is all about. I’ll share with you how I worked with teams of experts to use Risk Based Inspection (RBI) to reduce inspection workloads by up to 40% in different plants around the world.

What is risk based maintenance? Simply put, it is a type of preventive maintenance where you assign your scarce resources to assets that carry the most risk of failure. For example…

Equipment that carries very high consequence of failure will be subject to more frequent maintenance and inspection. And low risk equipment may be maintained at a much lower frequency and possibly with a much smaller scope of work. What makes risk based maintenance unique is, BOTH the frequency and the scope of maintenance are continuously optimised. And this optimisation is based on the findings from your actual maintenance and your risk assessment.

Let me explain this visually.

Risk-based Inspections

Let’s assume we have six pieces of equipment shown below, where we have the results of their initial maintenance inspections.

Through a risk-based assessment, we then evaluate whether we need to…?

  1. keep doing inspections at the same frequency and the same scope of work,?
  2. or whether we can extend the frequency?
  3. or reduce the scope of work,?
  4. or potentially reduce the frequency and increase the scope of work.


Based on our initial maintenance inspections and risk assessment, let’s say we found a couple of things that should be changed for the next cycle—?


Equipment 1 – We’re quite concerned about a certain failure mode, and we want to inspect it much sooner than we had intended. Not only that, but we’re also no longer concerned with some failure modes. So the scope is actually somewhat reduced.?


Equipment 2 – We’re actually not so concerned anymore. And we decide to extend the interval and reduce the scope of work.?


Equipment 3 – We need more data to make a reliable assessment, but we’re not that concerned that we decide to accelerate the next inspection. So we keep both the frequency and the scope of the inspection the same.??


Equipment 4 – When we analysed the equipment, we realised that the failure modes we’re inspecting for simply are NOT applicable in our operating context. So we removed this inspection from our program completely.??


Equipment 5 – This is similar to equipment two, in that we’ve decided to extend the inspection interval, and we are going to reduce the scope of the inspection somewhat.?


Equipment 6 – The rate of deterioration is actually less than we thought so we extend the inspection interval, but we are actually concerned that it could apply to more components of the equipment. So the scope is enlarged.?


From these findings, our next cycle would then look like this.?


All this simply means is that the scope and frequency of your maintenance for the next cycle changes according to the findings from your previous cycle and risk assessment.?By doing this type of maintenance, you make the most of your resources.?


The Problem with Risk Based Maintenance?

Now, a common problem you might encounter is that, after a while, all your maintenance and inspection tasks can end up all over the place (like the one above).?So instead of having all your inspections neatly every three years, you have them all spread around.

And when these inspections require equipment shutdowns and potentially plant shutdowns, that can become a really complex issue.?This is when you hear people say, “All right. Well, let’s stop this RBI nonsense. We have shutdowns every four years. So let’s just inspect everything every four years.”?

Sure. That’s easy, very easy. But it’s not wise from a business perspective.?Because that way, you will never move beyond your yearly, two yearly or four yearly outages.?So you really do want to apply the risk based maintenance principles.?

How do you solve this problem??

Now looking at our overall equipment condition and the target date for the outage. We really want to defer our outage to align with the required dates for equipment five and six represented by the red line here.?


But the concerns around equipment one and three won’t let us do that without doing more work.??So now it’s time to see if there’s any additional inspections or mitigations we can come up with that might allow us to move equipment one and three further to the right.?On careful review, we may conclude that we really need more data for equipment one to be able to assess its condition so we can’t really do much.??

We had planned to get a visual inspection during our next cycle, but since we’ve moved that target date to the right represented by the red line, that will be too late.???We’re not comfortable moving it that far to the right. So we come to the conclusion that we will need to do something different.?


Non-intrusive inspection techniques?

On review, we find that actually we could use a much more advanced, non-intrusive inspection technique.?This technique doesn’t involve entering the vessel, or equipment/plant shutdowns. But this non-intrusive inspection technique would be a lot more expensive (which is why it was never done before).?

But if we spend the extra money on this more advanced technique, we get the data we need. And if we get positive results, we may actually defer the internal visual inspection until the new date shown by the red line.?So this is all about risk management and an economic trade-off in a sense.?

?Is the value of deferring the outage to the new target date (represented by the red line) sufficient to justify doing this expensive non-intrusive inspection early??


What does this all mean??

This might all seem complicated and theoretical.?But this is exactly how we used Risk Based Inspection (RBI) to reduce inspection workloads by 30% – 40%.?We used a combination of extension of inspection frequencies, as well as reducing the inspection scopes.?So doing less work, less frequent.??

By using RBI with advanced non-intrusive inspection techniques, we were able to extend outage intervals in the past.?And it was a win on all fronts.??

It was good for the companies I worked with because we kept producing for longer.?

  1. We deferred the shutdown.??
  2. It was good for personal safety because we eliminated several man entries into certain vessels.??
  3. And it was good for process safety as we got a much better understanding of the integrity of the equipment that we inspected by these more advanced inspection techniques.?

There are different approaches for RBI both quantitative and semi-quantitative and there are various external industry standards that describe RBI including API through API580 and API581.

The Biggest Benefit???

In complex continuously operating plants, often the biggest benefit of risk based maintenance to the business is not so much the reduction of the work… but the reduction in downtime.?For example…?

Inspecting pressure vessels is often done during shutdowns, often full plant shutdowns. And very often the pressure vessel inspections are on the critical path of the shutdown. So when you reduce the inspection scope of work, you can typically reduce the length of your shutdown. And that is often worth a lot of money.?

And although many of us are familiar with a risk-based approach for inspecting pressure equipment, you can apply the same principles to other categories of equipment too e.g. pressure relief valves or certified electrical equipment. We discuss this in much more detail in our new online training course Developing & Improving Preventive Maintenance Programs (PM100).

Summary?

We have scarce resources. That’s why we need to assign them to assets that carry the most risk of failure. This is what risk based maintenance is all about.?What makes risk based maintenance unique is, BOTH the frequency and the scope of maintenance are continuously optimised based on the findings from your actual maintenance and your risk assessment.??

A common problem with risk based maintenance is that all your maintenance and inspection tasks can end up all over the place, instead of having them neatly every few years. That can become a really complex issue when inspections require equipment shutdowns and potentially plant shutdowns.?

To solve this problem, see if there are any additional inspections or mitigations you can come up with that might allow you to move equipment further to the right of the schedule.?It might be worth spending extra money on more advanced inspection techniques so you can actually defer the internal visual inspection to a more convenient date.?

This is all about risk management and an economic trade-off in a sense. In complex continuously operating plants, often the biggest benefit of risk based maintenance is not so much the reduction of the work… but the reduction in downtime.?

When you reduce the inspection scope of work, you can typically reduce the length of your shutdown. And that is often worth a lot of money.?


P.S. Whenever you're ready, here are 3 ways we can help you on your Road to Reliability:

1. Want to train your team on how to improve your plant's maintenance reliability?

Enroll your team in one of our most popular online training courses:

Implementing Maintenance Planning and Scheduling—increase your maintenance workforce by 35% without hiring anyone. Reduce costs, improve safety and increase morale.


Developing and Improving Preventive Maintenance Programs—achieve higher reliability and availability whilst doing less maintenance. Acquire the knowledge and tools needed to create a highly effective and efficient Preventive Maintenance Program.


2. Want to know how effective your Planning and scheduling really is?

Use our Planning & Scheduling Scorecard?to assess your performance and receive a personalised PDF report with recommendations on how to improve.

Use our Wrench Time Calculator?to easily calculate how much value your organisation is missing out when you neglect your Planning & Scheduling.


3. Want to start your journey on the road to reliability?

Download the Reliability Academy eBook?and discover a simple, proven framework that you can use to achieve a highly reliable plant for your organisation. Unlike other overly complicated models that use 10 to 20 elements, the Road to Reliability framework only uses 4 elements to achieve great results.


Gordon Tatershall

Reliability Engineer

1 年

@Erik What is described is in Risk Based Maintenance requires full commitment by a company supporting maintenance leadership and a maintenance leadership with first hand experience with equipment and have a role to be very immersed in assessing the information from PM tasks and being able to expediently make adjustments to the computer generated PM tasks and by pass those already generated for several months into the future and waiting to be released. This absolutely relies upon the quality of information being returned by tradespeople/operators. Is it possible, yes, I have had a go. In my experience it requires a both a significant culture change and general interest at every level and particularly so in the designing into EPCM systems the ability to make on the run adjustments ( and not committee decisions to approve changes of PM tasks) It takes a lot of effort to keep on track with the range of stakeholders involved and is far from frictionless. I suspect is more suited to manufacturing industries of sufficient size to invest in roles of experienced Mtce personnel who understand equipment, production risk, redundancy or spares onhand and financial impact to the specific business. A lot of mtce culture is reactive these days.

回复
Carlos Valerio

Inspector NDT equipos rotativos

1 年

Interesting publication Erik Hupjé. Risk Based Inspection (RBI)?is very usefull for optimizing the scope of a Turnaround.

Patrick Ethier

Design and Reliability Engineering leader. AI implementation in heavy industry.

1 年

Well said! Add some online monitoring and you can save a lot by having a solid risk based approach.

要查看或添加评论,请登录

Erik Hupjé的更多文章

社区洞察

其他会员也浏览了