Review of Contractor’s Progress Report and Schedule
As a Project Controls Engineer working with the Owner, Main Contractor, or PMC, it is necessary to thoroughly review the updated schedules and progress reports submitted by Contractors. The schedule serves as a primary communication tool and a basis for evaluating the progress of work.
However, Before starting the review process, acknowledge the project controls team’s efforts.
Please concentrate on the following areas.
1) Contract Document: This document guides the review process. It typically addresses reporting requirements and outlines the format, structure, content, recipients, frequency, and necessary supporting documents.
2) Approved Schedule Baseline: It is essential to have the native file (.XER version) of the approved schedule to compare the progress updates. If the baseline is not yet approved, the latest commented file may be used, and the schedule basis should be updated to record it.
3) Involvement in the Project: Your review's effectiveness depends on your involvement. Access the latest meeting minutes, updates on change orders, project decisions, and pending actions with deadlines and responsible persons.
4) Supporting Documentation: The schedule update must include a progress narrative detailing key activities completed in the reporting period and planned for the next cycle. The report should cover critical path activities, concerns, needed inputs, hindrance log, risk register, and invoice status. Depending on contract requirements, include document, material, and construction registers, along with S-curves, manpower histogram, and photos.
5) Existing Procedures and Best Practices: The review process should align with the organization’s existing procedures. The project controls team is advised to refer to best practices available for their specific industry.
Tools and Techniques
Review Checklist: It is advisable to develop a review checklist tailored to your specific requirements. This checklist should encompass key indicators that can assist in the review process, such as data accuracy, scheduling discrepancies, the availability and correctness of supporting documents, among others. Additionally, it aids in maintaining consistency and a structured review process within the team.
Analysis : Check for data mismatches or manipulation, verify variances, and examine deleted, added, or modified activities. Review the critical path, leads, lags, constraints, relationships, milestones, calendars, and any changes that could be made since the last approved update for gaining advantage at a later stage. Use scheduling software features for this analysis.
Outcome
What additions would you make to the review process? How can we ensure the schedule review helps achieve project objectives?
Please share your thoughts…
Chief Project Planning, Tata Steel
1 周During contractor/ subcontractor schedule review one key aspect is interfaces - where one party has to provide/ receive inputs from other. If not defined and identified clearly in schedule there bounds to be problems.
Useful tips
Delivering Excellence in EPC Projects | Project Control | Planner | Scheduler | Civil Engineering - Geotechnic & Water Resource enthusiast
1 周What are your concerns in reviewing contractor's schedule aside from - critical path - nearly critical (total float 7-14 days) - long lead item - major item?
Consultant - Planning
1 周Navin, by educating Client's/ owners engineers you are making life difficult of contractors engineers ??????????
Certified Project Management Professional | Infrastructure Leader | High-Rise, Airport & Healthcare Expert | Primavera P6 & MS Project | QA/QC & FIDIC Compliance | PRINCE2, PMP, RMP,SP,Certified | GCC & India Experience
1 周Very helpful