Retrofit of ties into Existing Building Stock
Ok, me again with a few more ramblings.
Still trying to get a handle on the Building Safety Act, the Building Safety Regulator/HSE and how that impacts the industry going forward.
Also heard a few rumblings that a few buildings are earmarked for demolition recently which also lit a fire up my arse to really try and bottom this out and understand it a bit more. I don't think the demo approach will apply, they'd have to demolish and rebuild every relevant building (5 storeys and above) within England and Wales that didn't comply.
So I've mostly been trying to get our risk assessment documents pulled together over the last few weeks. Gone through the IStructE's Manual for Risk Assessments which we've based our documents on (makes sense) and then we've thrown in HSEs:
As an appendix, with a little influence from:
And back to the old classic:
Whoever wrote that last one by the way, stand up and take a bow.
So key take aways from the various HSE guidance:
Yep. All makes sense.
Lets call best practice horizontal and vertical ties which would make every existing building code compliant.
To satisfy the law.... that's disproportionate collapse (Building Regs, Schedule 1, Part A).
cl.4.(3). Building work shall be carried out so that, after it has been completed: Any building which is extended or to which a material alteration is made; complies with the applicable requirements of Schedule 1 or, where it did not comply with any such requirement, is no more unsatisfactory in relation to that requirement than before the work was carried out.?
That last line is a big one which opens up the need for a risk assessment.
Ok, they talk about 3 things here... risk, hazard and consequence. The Hazard is a gas explosion for instance and there is a likelihood value attached to each hazard, the likelihood of a gas incident happening each year is 1 in 1,510,000 for instance. Your chances of being killed canoeing are about half of that. And a gas event falls within the As Low As Reasonably Practical (ALARP) region on the tolerability scale. Neither acceptable or unacceptable, but you should make the effort to reduce the risks where possible.
Now risk = likelihood x consequence.
领英推荐
And gas explosions in existing building stock are deemed low likelihood but high consequence events because much of the existing building stock isn't resistant to disproportionate collapse (horizontal and vertical ties). This leads us onto the Building Safety Act which requires Safety Case Reports and the disproportionate collapse strategy identified for each building.
This is for both relevant (5 storeys and above) as well as high-risk buildings.
Now I used to panic when I read that, as I'm sure many other people within the industry did too. But its only really mirroring what the current Building Regulations are saying in that a change of use then has to be compliant. If anything, the BSA are just making a better paper trail for that to happen.
The HSE also want people to follow best practice, or industry guidance for example. And the current recommendations from the IStructE Disproportionate Collapse and Robustness book (1st edition) is to undertake a risk assessment for vertical extension for instance. This is echoed by the HSE guidance.
Cool. So a holistic approach is acceptable.
Whoop. Good to know.
Now this brings us to the rambling sketch on the header of this article.
I see feasibility reports from other consultants all the time and each one of them says 'building doesn't conform to disproportionate collapse, horizontal and vertical ties needed' and leave it there kicking the problem further down the road for someone else to sort with the client none the wiser as to how to move forward with this and if a project is worth pursuing or not.
So I had a go. And I think its a load of nonsense to try and retrofit ties back into a building, ignoring the cost, there are so many technical and practical hazards that arise from this, let alone the logistical challenge of trying to juggle in-situ residents with temporary housing nearby during the works. It doesn't work.
But. I'm taking my ramblings and drawing them up in CAD with CDM risks highlighted and a sequence of works where needed because the HSE say...
We could be dealing with multiple fatalities within the building stock, so I'm gonna suggest we go down the rigorous route.
i.e. you can't just do the quick calculation to determine a gross level of disproportion and then say 'it costs too much so it doesn't work'. They want to see proper evidence of us considering ties into the structure, what does that look like? How are you going to do it? Have you considered all buildability aspects? How will it impact on the existing residents? This all has to be demonstrated if we are to stand any chance of justifying that we have reduced the risks ALARP.
In essence - its a lot of work for not a lot of output. We're almost giving a design solution and saying it doesn't work. But that's our duty as consultants to demonstrate that in a way that can be communicated to others easily and proves that we're taking our statutory duty seriously and not just winging it because we don't know any better.
I think before the BSA, there's a slim chance I would have been asked for all of this as a designer. Now though... I think engineers are going to have to be prepared for the question.
Driving Business Growth and Ensuring Project Excellence
1 年Great
Associate Director, Structures, Bureau Veritas Building Control, supporting my Building Control Surveyor colleagues. Fellow of the ICE. Lead author of "Structural Robustness and Disproportionate Collapse in Buildings"
1 年A good read. Thank you. I hope other engineers are reading all this stuff, too!
Senior Managing Director
1 年Sean Hanlon Thank you for sharing this insightful post. I found it to be very informative and thought-provoking.