Renison Paste Backfill Plant Nearing Completion

Renison Paste Backfill Plant Nearing Completion

Bluestone Mines Tasmania Joint Venture has a strong capital investment program which speaks to our confidence and commitment to a long ongoing future of the Renison Tin Mine. This includes the construction of a new paste backfill system.?

Surface and underground construction is well under way and will soon be culminating in plant commissioning and the filling of our first stope. Paste backfill allows us to maximise ore recovery whilst reducing our environmental impact.?

The paste system will deliver an average of 50m3/hr of paste when operating. A portion of the mill tailings stream will be thickened, mixed with cement and transferred 1100m underground via a network of vertical drill holes and horizontal pipework.?

Other environmental projects, including a new contaminated water treatment plant, sewerage treatment plant, oil/water separator and upgrades to surface fuelling infrastructure, will also be delivered as part of the Paste Backfill Plant. These investments will further reduce our impact and deliver better operational outcomes for the business.

#bluestonemines?#mining?#tin?#tasmania?

No alt text provided for this image
No alt text provided for this image
No alt text provided for this image
No alt text provided for this image
John Lamb

Making a difference in Tasmania!

2 年

Great to see, well done team Renison!

Phil Jones

Thinking about retirement, Mining Mechanical Maintenance Specialist at Phil Jones Mechanical

2 年

Fun when pipework blocks up. Ensure lines are flushed out ?

Glenn Van Vlemen

Experienced mining operational and project development manager.

2 年

要查看或添加评论,请登录

Bluestone Mines Tasmania Joint Venture Pty Ltd的更多文章

社区洞察

其他会员也浏览了