Public Access Stairs
At the 11th hour, before cutting off access into an apartment block, the developer discovered that his proposed scaffold solution was not building code compliant, and could not be used as a Public Access Stair.
Within 24 hours of contacting Australian Scaffolds, we’d visited site, determined the scope of work, and developed a design for these 2 Public Access Stairs.
This Public Access Stair was more challenging than most due to the tight site boundary constraints, and steeply sloping ground.
Despite the challenging conditions, Australian Scaffolds were still able to install the public access stairs within 1 shift.
Another example of how Australian Scaffolds can aid your project, and help you to work SAFER, SMARTER, FASTER.
To learn how Australian Scaffold can aid your project, contact Terry on [email protected]