Project Managment: Drilling
Sachum .A. Wapa
Geotechnical Engineer |Engineering Geologist| Projects| Civil Projects|
Assumptions:
Scenarios:
Scenario 1: Normal Conditions
Scenario 2: Challenging Conditions
Scenario 3: Accelerated Timeline (Overtime).
Budget Breakdown
Cost Item Unit Rate Quantity Total Cost (USD)Mobilization/Demobilization$5,0001$5,000Rig Cost (Scenario 1)$2,000/day/rig45 days × 2 rigs$180,000Rig Cost (Scenario 2)$2,000/day/rig65 days × 2 rigs$260,000Rig Cost (Scenario 3)$2,000/day/rig38 days × 2 rigs$152,000Geological Supervision$1,000/day Duration (varies)$45,000 - $65,000 Consumables$30/m900 m$27,000Reporting and Management$1,000/day5 days$5,000Contingency (10%)10% of total cost-Variable
Project Schedule
Task Duration (Days) (Scenario 1)
Duration (Days) (Scenario 2 )
Duration (Days) (Scenario 3)
Thats a story for another day.