Project management forms(soft copies)-Part-1-Project Charter

Project management forms(soft copies)-Part-1-Project Charter

Reference book: A Project Manager's Book of Forms by Cynthia Snyder

Please note: I filled and submitted these forms in my projects, I am highlighting only one project in this series, these forms are hand filled and submitted in hard copies, converting them in soft copies are time-consuming, also I am a human being, I can make errors, and I am accepting that i am not an authority in this subject, but with my rare knowledge and continuous learning from my mistakes, I successfully executed multiple projects in my professional life.


PROJECT CHARTER


Project Title: Construction of 4no: of 11 KV LILO/Ring-substations

Project Sponsor: Board of Directors (Employer)

Project Manager: Engr. Qazi Arsalan Hamid

Date Prepared:  X*/X*/XXXX*

Project Customer: Media Groups and City Government (MGCG)


Project Purpose or Justification:

Supply electrical power to newly constructed buildings of West administration units


Project Description:

4 nos: of Substation with an area of X by L, each substation is consisting of 1MVA 11/0.440 KV Transformer panel, LV panel, after construction and placement Testing of All HV and LV types of equipment must be conducted in presence of Client Rep, Duration 4 months from the Award letter


High-level Project and Product Requirements:

The project awardee must follow IEC standards for All types of equipment and local building construction codes, upon completion each Substation must supply 1000A with complete safety, All HVCBs, LVCBs, protection relays and fuses must be aligned with the existing protection scheme.

 

Summary Budget:

$A=X+Y+Z

*.X Local Currency (LC) for construction expenditures (Engineering and Design Cost included)

**. Y (LC) for Procurement (SAT and FAT considered in this cost)

***. Z (LC) for MOB-DEMOB

Please Note: defines penalties in signed contract award documents must be deducted from the Project contractors at the time of final settlement

 

 Initial Risks:

·      Administration Permits to Work

·      Fund Approval issue from Sponsor

·      Weather condition

·      Delay in human Resource Provision

·       Delay in Resource Provision

 

No alt text provided for this image
No alt text provided for this image
No alt text provided for this image
No alt text provided for this image

 Part 1-Status: Completed