Project Management: The Forgotten Toolkit
A Possible Intersection Point
There is a possible intersection between the CMMS product and project management using WO actuals, WBS budgets and Schedule activity progress. The joining element would be the WBS cost account code. Some CMMS products have the ability to create this WBS (work breakdown structure). This feature enables the project manager to lay out the scope, deliverables, and budgets. The application might include a Project Cost Report. When this WBS is linked to a schedule, then progressing can be multiplied times budget to get earned value.
Example Projects
Facility architects manage new construction and alterations. And when a new building is delivered there can be hundreds of assets. These new assets need to be given the right maintenance strategies and maintained at optimum cost. In other industries, outage management is a primary concern. Either way, cost effective asset management starts inside the CMMS.
The Elusive Weekly Maintenance Schedule
There are many reasons this process can go sideways. Consequently, 90% of all sites have never successfully created an automatic, resource-leveled weekly schedule. Some just print out a list of open work and hand that to the maintenance staff to figure out. Some just focus on emergency and urgent work blended with generated PM work orders. The problem lies with "all the other work" in the backlog as to how best to manage. And even if all the work orders had a craft estimate, questions still exist as to which ones should be done first, and, how much work should be scheduled based on craft availability. This link shows the Weekly Schedule Order of Fire activation screen.
Once Upon a Time
Once upon a time there was a company that marketed project management software. They sold scheduling software and project cost tracking. These two products could be integrated through a work breakdown structure (WBS) at the cost account level to provide the ideal project management system. This software included a full function scheduler that could manage any size project -- and plot graphics of all types (bar charts, histograms, and network diagrams). At one time, maybe 50% of all nuclear power plants in construction/startup and operational phase used this software.
Then the Mainframe Died
Change happens. The mainframe software for the most part did not convert over to today's technology. Although the new technology is absolutely brilliant, there was some lost functionality. By lost I mean, the current CMMS with scheduling interfaces have weak progressing and graphic capabilities. But beyond that, there is also a general lack of knowledge in the CMMS community regarding WBS design and purpose.
领英推荐
Project Management Best Practices: 1-2-3
I am trying to recall the lessons learned 30 years ago from my project management classes. I was told that if you build a large project (e.g. construct a nuclear power plant) you should first create a WBS. This design ensured that no scope was forgotten, and it provided scope management (additions) once underway. The cost account (CA) element would typically store the budget values. The WBS was also a good place to capture dollar transactions (movement between cost elements). Lastly, it was the WBS-CA that provided an intersection point for CMMS work order actuals and schedule activity percent complete for cost reporting.
The next step in project definition was to start creating fragnets. This is where the scheduler performed interviews similar to a newspaper reporter. Typically the scheduler interviewed the construction and system engineers. Often times the scheduler would draw a logic diagram on paper (pen on paper). This technique enabled the scheduler to identify activities and logic ties almost as fast as the person speaking. The scheduler then combined all of these independent fragnets into a master schedule where it was flowed and leveled.
Once the master schedule was finalized, a pretty looking bar chart with logic ties, under a timeline, was produced for readability purposes so that all stakeholders could clearly see dates for intermediate milestones, and of course, the project finish.
10 Requirements of the Ideal Project Management System
In a perfect world, it would be much easier if the CMMS could be set up to support project management best practices -- and work management. Maybe it can't do total float calculation and fancy bar charts, but it should be able to do everything else -- including a resource leveled weekly maintenance schedule. Here are 10 future-world requirements:
Outage Manager Requirements
An outage manager depends heavily upon the outage scheduler(s). He also needs staff that can apply system operations knowledge to schedule and scope control. Once the required critical path is identified, then other work can be added so long as it does not extend the critical path or place the outage duration at risk. If you were an Outage Manager for a nuclear power plant how would you make best use of project management software?
How Much Software Do You Need?
You can buy software to do anything. But why not take a harder look at the CMMS and see what can be configured internally. Through clever use of applications, and configuration capabilities, output can be generated which performs project management best practices.
Scheduling Specialist for High-Variety, Order-Driven Production and Resource-Constrained Projects
5 年John Reeve, You wrote, "In a perfect world, it would be much easier if one (CMMS) software package existed that accomplished most of the following:.........." Any decent CMMS software should be able to meet all the 10 requirements easily when a best-of-breed scheduling software is integrated with it. The most difficult one among those 10 requirements is "Produce a resource leveled weekly schedule; automatic; single-click action". Powerful, versatile and flexible scheduling tools like Schedlyzer Lite can easily do it in a second even for a thousand activities. I do not think any scheduling software based on critical path method (CPM) can be really good for general operations scheduling with automatic resource-leveling. I know only one exception to this among project management software. I talked to you about integration of scheduling software with a CMMS software in a conference in Houston 2 or 3 years ago.
Senior Reliability Consultant
5 年Fluke's Emaint software has project and Gantt charting built in to it's project module. I've also used Microsoft project which is good. I personally prefer to have as many of my solutions in one software as possible.
Asset Management Professional .. Over 19 years of field experience within 2 countries at "Oil n Gas, Fertilizer, Steel Indusrty and Facilities Management".
5 年There is an integration module that connect MS Project to maximo , and another integration module that has a visualizer to reschedule any specific WOs within Maximo .. eventually you can import the project tasks/WOs from maximo and MS Project doing strong progress report by it and issuing cost report by MAXMO
Transformation Leader | PMO Director | Fin | IT | Budget | Planning | Risk | PPM | Benefit Realization | Metrics | ERP | EAM | Cloud | Data | SaaS | O&G | Energy | Aerospace | Manufacturing | Consulting
5 年]Project Open[ . . . Happy to connect you with the owners. I set up new PMOs with it because you can integrate with almost any gantt solution. The is an open source / freeware version.
Managing Director /Owner at Blu Sky Engineering & Consulting
5 年These will improve communication, work management control, availability forecasting overview etc etc , who or which CMMS platform will start creating this?