PROJECT MANAGEMENT -
Dr Kuldeep K. Khanna
Senior Adviser,KPMG India and Former Director & Board Member of Steel Authority of India Ltd (SAIL)
A Book on Project Management By Dr K K KHANNA
Publisher: Bloomsbury India
Address: Bloomsbury Publishing India Pvt Ltd , DDA Complex, Pocket C-6&7 , Vasant Kunj, New Delhi -110070, India
PREFACE
Projects are critical to the success of any organization. These result in new or changed products and services, processes and organizations. Projects help in reducing the costs, improving the quality and customer satisfaction and result in many other benefits. As organizations have recognized the criticality of projects to their success, project management has become a focal point of improvement efforts. These days many organizations are embracing project management as a key strategy for remaining competitive in the current business environment. In the leading organizations, project management is aligned and integrated with the company’s business goals and objectives.
However, in the context of Indian organizations, the scenario is somewhat different. The success rate of implementing projects in India is not encouraging. Time and cost overruns are frequent and even the envisaged benefits are not achieved. I have conducted post completion review of several projects as an Independent Consultant. The observations made during the reviews are indicated below:
§ Business cases were sometimes formulated based on top management intuition and not on well worked financial appraisals.
§ Feasibility report providing multiple options was not prepared before seeking approval of business case to start implementing the project.
§ Feasibility report often considered only one option instead of exploring all possible options.
§ Business decisions being made based on perceived certainty; often not considering risks and uncertainty.
§ Risks were often not identified and analyzed and risk response strategies were not developed.
§ Assumptions made were often not validated.
§ Technical specifications were at times too elaborate and sometimes ambiguous.
§ Procurement often got delayed due to delays in completion of design engineering. Equipment supplies are often delayed.
§ Though networks were prepared at the initial stage of the project, these were hardly updated and used for project monitoring.
§ Volume of civil work in terms of cubic meter of excavation / concreting work and structural work in terms of tonnage of the structures often under estimated.
§ Project implementation strategy envisaged large number of work packages which often increased co-ordination beyond the capacity and capability of the project team.
§ Frequent mid-stream scope changes that led to delays and disputes with the contractors. Change control management (changes in scope baseline, time baseline and cost baseline) often not given importance.
§ Lack of clarity of the responsibility and liability of contractors within a contract with the consortium of several contractors that often led to delays
§ Inadequate and delayed deployment of resources have often resulted time overrun. The resources include both the physical and human resources
§ Frequent delays in payment of contractor’s invoices due to various processes resulting in contractor delaying the project
§ Non sequential supplies often interrupted progress of the project sometimes resulting in stoppage of project work.
§ There have been frequent mid stream changes in the leadership of the project team.
§ The project work had often been temporarily stopped due to inadequate cash flow causing both time and cost overrun
§ Performance guarantee tests, a part of project contracts, were either not conducted by the project owner due to reasons beyond their control or conducted after considerable delays for reasons mostly attributable to them. In projects where performance guarantee tests were conducted, shortfalls in agreed guarantee parameters were often observed thus not achieving the envisaged project benefits. Levying liquidated damages, often small amount as compared to actual production losses in the long term, is no solution. Project on completion should result in achieving all the benefits as envisaged in the business case.
Indian organizations need to strengthen the project management for developing industrial and infra-structural base for India’s economic growth. In India, project management, once considered nice to have, is now being recognized as a necessity for ensuring the successful completion of the projects without time and cost overruns. Some organizations are just getting started with project management. Others have reached a reasonable level of maturity in project management. Training programs to improve project management practices are increasingly becoming the common parts of strategic plans to improve organizational effectiveness.
This text discusses the principles of project management including project management processes and functional areas-scope management, time management, cost management, procurement management, resource management, quality management, risk management, communication management, stakeholder management, commissioning management, integration management, post-completion project reviews and closing of the project. The text also includes how to prepare the business case of the project. The text is primarily on project management for industrial and infrastructure projects in India, but also includes an overview of agile project management for software development. This book is addressed not only to those students who wish to understand and improve upon their project management skills, but also to those functional managers and upper-level executives who must provide continuous support to all projects. This book shall be helpful to the management professionals, project managers, project engineers, consultants and students.
CONTENTS
Chapter-1: What is project?
ATTRIBUTES OF A PROJECT
DIFFERENT TYPES OF PROJECTS
RELATIONSHIP- PROJECT, PROGRAM, PORTFOLIO& OPERATIONS MANAGEMENT
BUSINESS VALUE
BUSINESS CASE
Chapter-2 : What is project management?
PROJECT MANAGEMENT
PRPJECT MANAGEMENT PROCESSES
TEN FUNCTIONAL AREAS OF PROJECT MANAGEMENT
PROJECT PHASES
PROJECT LIFE CYCLE
PROJECT SPONSOR
PROJECT MANAGER
PROJECT TEAM
RESOURCE MANAGERS
THE CUSTOMER
PROJECT STAKEHOLDERS
THE 7-S OF PROJECT MANAGEMENT
PROJECT SUCCESS MEASURES
WHAT ARE THE PERCEIVED CAUSES OF PROJECT FAILURE?
ISSUES THAT NEED ATTENTION BEFORE STARTING A PROJECT
MANAGING THE COMPLEXITIES OF THE PROJECT
Chapter-3: Project Operating Environments
ENVIRONMENTAL FACTORS BEYOND THE CONTOL OF ORGANIZATION
ENVIRONMENTAL FACTORS INTERNAL TO THE ORGANIZATION
ORGANIZATIONAL POLICIES, PROCEDURES & PRACTICES
Chapter-4: Project Organization Structure
ORGANIZATION STRUCTURE
PROJECT MANAGEMENT OFFICE (PMO)
FUNCTIONAL ORGANIZATION
MATRIX ORGANIZATION
PROJECTIZED ORGANIZATION
INTEGRATED PROJECT MANAGEMENT ORGANIZATION
PROBLEM AREAS IN STAFFING THE PROJECT
Chapter-5: Who should be the project manager?
SELECTING THE PROJECT MANAGER
RESPONSIBILITIES OF THE PROJECT MANAGER
SKILLS THE PROJECT MANAGER MUST DEMONSTRATE
PRIMARY SKILLS FOR EFFECTIVE PROJECT MANAGER
Chapter-6: Selecting the right project
Chapter-7: Project Feasibility Study
Chapter-8: Project Detailed Study
PROJECT SCOPE
PROJECT SCHEDULE
PROJECT COST
PROJECT ORGANIZATION STRUCTURE
PROJECT CONTRACTING STRATEGY
PROJECT RISKS
PROJECT BUDGETING
PROJECT FINANCING
PROJECT BENEFITS
FINANCIAL EVALUATUATION
Payback Period Method
Net Present Value Method
Internal rate of return (IRR) Method
Comparing IRR, NPV and Payback
ECONOMIC ANALYSIS
SENSITIVITY ANALYSIS
RECOMMENDATIONS OF DETAILED STUDY
Chapter-9: Project Business Case
BUSINESS CASE
REVIEW OF BUSINESS CASE
PHASE GATE PROCESS
PROJECT CHARTER
Chapter- 10: Project Management Processes
PROJECT MANAGEMENT PROCESSES
PROJECT INFORMATION
PROJECT DOCUMENTS
Chapter- 11: Project Execution
PROJECT MANAGEMENT PLAN
DIRECTING AND MANAGING PROJECT WORK
MONITORING AND CONTROLLING THE PROJECT WORK
MANAGING THE COMMISSIONING OF PROJECT FACILITIES
Chapter-12: Scope Management
COLLECTING REQUIREMENTS
DEFINING SCOPE
CREATING WORK BREAKDOWN STRUCTURE (WBS)
SCOPE BASELINE
VALIDATING SCOPE
CONTROLLING SCOPE
Chapter-13: Schedule Management
DEFINING PROJECT ACTIVITIES
DETERMINING RELATIONSHIP & LOGICAL SEQUENCE AMONG PROJECT ACTIVITIES
ESTIMATING RESOURCES REQUIRED FOR PROJECT ACTIVITIES
ESTIMATINGDURATION OF PROJECT ACTIVITY
DEVELOPING PROJECT SCHEDULE
HOW TO CONTRUCT NETWORK
PERT &CPM NETWORKS
TECHNIQUES TO OPTIMIZE NETWORKS
RESOURCE OPTIMIZATION TECHNIQUES
SCHEDULE COMPRESSION
WHAT-IF ANALYSIS
SIMULATION
PRECEDENCE NETWORKS
COMPARISION OF NETWORK TECHNIQUES:
MONITORING & CONTROLLING PROJECT SCHEDULE
PROJECT MANAGEMENT SOFTWARE
Chapter-14: Cost Management
THREE METHODS OF ESTIMATING COSTS
COST ESTIMATES
COST BASELINE
MANAGEMENT RESERVES
COST MANAGEMENT PLAN
DETERMINING BUDGET
CONTROLLING THE COSTS
REVIEW OF BASELINES
Chapter-15: Procurement Management
CONTRACTOR
PROJECT CONTRACTS
TYPES OF CONTRACTS CONSIDERING CONTRACT PRICE
TYPES OF CONTRACTS CONSIDERING MODE OF PROJECT IMPLEMENTATION
HOW TO MANAGE UNCERTAINTIES OF PROJECT?
PROJECT CONTRACTING STRATEGY
SELECTION OF ACQUISTION METHOD
SELECTION CRITERIA FOR PRE-QUALIFICATION OF BIDDERS:
BID EVALUATION CRITERIA
BIDDING DOCUMENTS
PAYMENT TERMS
TYPICAL CONTRACTUAL CLAUSES IN PROJECT CONTRACT
PROCUREMENT PLAN
CONDUCTING THE PROCUREMENTS:
MANAGING THE PROCUREMENT CONTRACT:
CONTRACT CLOSURE
Chapter-16: Human Resource Management
STAFFING THE PROJECT ORGANIZATION
DEVELOPING THE PROJECT TEAM
MANAGING THE PROJECT TEAM
STAFFING THE PROJECT DELIVERABLE PRODUCTION UNIT
Chapter-17: Physical Resource Management
PHYSICAL RESOURCE MANAGEMENT PLAN
IDENTIFYING RESOURCE REQUIREMENTS
ACQUIRING RESOURCES
CONTROLLING RESOURCES
Chapter-18: Quality Management
QUALITY RELATED CONCEPTS
QUALITY CONTROL TOOLS
PROJECT QUALITY MANAGEMENT
QUALITY MANAGEMENT PLAN
MANAGING THE QUALITY (QUALITY ASSURANCE)
CONTROLLING THE QUALITY
Chapter-19: Risk Management
WHAT IS RISK?
RISK ATTITUDE
CATEGORIZATION OF RISKS
RISK BREAKDOWN STRUCTURE
CERTAINTY, RISK AND UNCERTAINTY
DECISION MAKING UNDER CERTAINTY
DECISION MAKING UNDER RISK
DECISION MAKING UNDER UNCERTAINTY
DECISION TREE
RISK MANAGEMENT
RISK MINDSET
RISK PLANNING
IDENTIFYING THE RISKS
RISK ANALYSIS
RISK EVALUATION
QUALITATIVE RISK ASSESSMMENT
QUANTITATIVE RISK ASSESSMENT
RISK RESPONSE PLANNING
IMPLEMENT RISK RESPONSES
RISK MONITORING & CONTROL
Chapter-20: Communication Management
COMMUNICATION MODEL
COMMUNICATIONS MANAGEMENT PLAN
MANAGING THE COMMUNICATION
MONITORING COMMUNICATIONS
Chapter- 21: Stakeholder Management
IDENTIFYING STAKEHOLDERS
STAKEHOLDER ENGAGEMENT PLAN
MANAGING ENGAGEMENT OF THE STAKEHOLDERS
MONITORING STAKEHOLDER ENGAGEMENT
Chapter- 22: Commissioning Management
TRIAL RUNS
PRELIMINARY ACCEPTANCE
COMMISSIONING MANAGEMENT
TAKING OVER
PERFORMANCE GUARANTEE TEST
Chapter-23: Coordinating and integrating activities across multiple functions
DEVELOP PROJECT MANAGEMENT PLAN
DIRECTING AND MANAGING PROJECT WORK
MONITORING AND CONTROLLING THE PROJECT WORK
INTEGRATED CHANGE REQUESTS CONTROL PROCESS
Chapter-24: Closing The Project
Chapter-25: Post Completion Review
POST COMPLETION REVIEWS
CONCLUSION
Chapter- 26: An Overview of Agile Project Management
MANIFESTO FOR AGILE SOFTWARE DEVELOPMENT
PRINCIPLES BEHIND THE AGILE MANIFESTO
AGILE SOFTWARE DEVELOPMENT METHOD
AGILE PROJECT MANAGEMENT AND SCRUM
SCRUM
COMPLEXITY IN SOFTWARE DEVELOPMENT
SCRUM FOUNDED ON EMPIRICISM
SCRUM – ITERATIVE & INCREMENTAL PROCESS
SCRUM VALUES
SCRUM TEAM
SCRUM FLOW
IDENTIFYING PRODUCT REQUIREMENTS FOR SOFTWARE DEVELOPMENT
SPRINT
SCRUM ARTIFACTS
AGILE PROJECT MANAGEMENT SOFTWARES
Founder and President at Global Monarch FZC UAE
1 年Waiting for yr call khanna Sahib. 98110 64814
Founder and President at Global Monarch FZC UAE
1 年Mubarak ho Khanna Sahib Hope you remember me from a lo g time ago. Would be happy to connect.
nil at Retired & can assist & give consultation in pipe industry
3 年Congratulations
Sr. Manager at Tata Steel
3 年Congrats sir..where can I get this book..
Self Employed
3 年Hearty congratulations sir