Project EGAT Police - Mission acompleted
BEST Logistics Sp. z o.o., Szczecin, Poland

Project EGAT Police - Mission acompleted

We did it. ?Today, we delivered the last heavy weight components of the EGAT Police Project to the “Port Barkowy” of Police. The last unit - a 200-ton coldbox - we took over from MV Eemslift Nadine.

Over a period of 9 months, a total number of 26 vessels came to the seaports of Szczecin, Swinoujscie and Police offloading here approx. 19.000 tons of heavy and oversize cargo. We provided with ro/ro-vessels, pontoons and inland barges, total 46 voyages. All has been delivered to the “Port Barkowy” of AZOTY Police. Additionally we realized 667 road transports directly from the port of Szczecin to the construction site.

Es wurde kein Alt-Text für dieses Bild angegeben.

Highlights of the project were the 5 pcs. of Storage Tanks with 65 m length and 600 t weight each, but the Splitter with 95 m length and 900 t weight beat all.

Es wurde kein Alt-Text für dieses Bild angegeben.

This project was the largest contract in our 20-year history. We would like to thank everyone involved for the perfect collaboration.

Es wurde kein Alt-Text für dieses Bild angegeben.



Robbert de Reus

Communications & Marketing Officer at Verbrugge International

3 年

Great Job Andreas!

回复
Piotr Maj

Managing Director w Fast Baltic Sp. z o.o.

3 年

Congratulations Andreas for all the BEST crew.

回复
Ilker Demirtas

Head of Chartering bei HSW Logistics GmbH

3 年

Well done Andreas ! :)

回复

要查看或添加评论,请登录

Andreas H?fner的更多文章

  • Two jobs for floating crane CONRAD CONSUL

    Two jobs for floating crane CONRAD CONSUL

    On Tuesday we had 2 tasks for the floating crane CONRAD CONSUL in Gdansk. First, a gas turbine coming from Sweden was…

    1 条评论
  • Project Ostro??ka has gained momentum

    Project Ostro??ka has gained momentum

    The hot phase has begun. 21 pcs.

  • The (last) eagle has landed

    The (last) eagle has landed

    Two years of preparation and one year of realization have passed. The delivery and placing on foundations of the second…

    1 条评论
  • convoy of barges on the Odra river

    convoy of barges on the Odra river

    A tunel boring machine has been loaded to five barges and pontoons. As subcontractor to DB Schenker Polska we arranged…

    1 条评论
  • First oversize load has passed the new lift at Nierfinow

    First oversize load has passed the new lift at Nierfinow

    It has not been a week since the new ship's lift in Niederfinow was opened by the German Transport Minister Dr. Volker…

    3 条评论
  • DOLNA ODRA - 1st GT on its foundation

    DOLNA ODRA - 1st GT on its foundation

    While I was on holiday our team did complete the delivery of the first gas turbine to the DOLNA ODRA Power station. In…

    1 条评论
  • new highlight for BEST Logistics

    new highlight for BEST Logistics

    This weekend we did realize a very special job. After several months of preparation, a 534-ton converter could be sent…

    8 条评论
  • same day - another challenge

    same day - another challenge

    While we drove the 455-ton stator to the foundation in the DOLNA ODRA power plant on Monday, at the French river port…

  • DOLNA ODRA power plant - logistics is gathering pace

    DOLNA ODRA power plant - logistics is gathering pace

    The starting shot has been fired. After two years of intensive preparation the on-shore deliveries of the components…

    1 条评论
  • 1000 tons of transformers shipped to Lubmin

    1000 tons of transformers shipped to Lubmin

    On behalf of Viktor Baumann GmbH & Co.KGWe have just shipped 3 pieces of transformers, each weighing 335 tons, to the…

    4 条评论

社区洞察

其他会员也浏览了