In the project Baseline Schedule Review Checklist, the following points can be considered. Among these points are defining the scope of the project, ensuring that resources are available to complete it, and assessing any risks that could delay its completion. Additionally, the project should be reviewed for any dependencies with other projects. It is important to note that this is only a guide, and some items might not apply to the contract or be redundant.
- 1. Proper identification of the Schedule?
- 2. Submittal Contents?–
- 3.?Contract/ Schedule completion date?–
- 4. Time/seasonal Restrictions?–
- 5. Substantial Completion Date?
- 6.?Regulatory/ Permit requirement?
- 7. Milestone?
- 8. Contract Access Restrictions?
- 9. Submission Timing?
- 10. Work Breakdown Structure?
- 1. Calculate the Schedule
- 2. Data Date?
- 3. Out-of-sequence CPM calculation rules?
- 4. Schedule Errors?
- 5. Imposed Finish Date?
- 6. Total tasks or activities?
- 7. Insufficient Details?
- 8. Milestone Ratio?
Deliverables, Submissions and Procurement
- 1. Contractor Design Submission?
- 2. Submittal Duration?
- 3. Submittal Contents?
- 4. Procurement and Long Lead Items?
- 5. Fabrication Activities?
- 6. Fabrication Activity Detail?
- 1. General Check?
- 2. High Duration?
- 3. Zero duration activities?
- 4. Wet weather allowances/buffer?
- 1. Activity Distribution Histogram?–
- 2. Mechanically incorrect dates?
- 3. Actual Dates?
- 4. Proper activity types?
- 5. Proper measurement of activity completion?
- 6. Missing activity description?
- 7. Duplicate descriptions activity?
- 1. Activity Codes Structure?
- 2. Activity Codes Assignment?
- 3. Duplicate activity codes definitions?
- 4. Blank activity codes values?
- 5. Report levels and requirements?
Work Breakdown Structure (WBS) Codes
- 1. Missing Work Breakdown Structure definitions?
- 2. Duplicate Work Breakdown Structure names?
- 3. Work Breakdown Structure assignments?
- 4. Work Breakdown Structure definitions?
- 1. Calendar?
- 2. Holidays/non-working days?–
- 3. Activity Calendar Assignments?
- 1. Logic?
- 2. Summary activities?
- 3. Workable sequence of activities?
- 4. Missing Logics in Milestone?
- 5. Missing Predecessors?
- 6. Missing Successors?.
- 7. Open Ends Logic?
- 1. Negative Float?
- 2. High Float or Excessive Float?
- 1. Lead or Negative Lag?
- 2. FS relationship should not have positive lags (Values greater than zero)?
- 3. Large lags would be better coded as separate activities?
- 4. Lags that do not overlap the activity?
- 5. Lags longer than the activity’s duration?
- 6. Any lag other than zero?
- 1. Imposed finish date?
- 2. Free float constraints (as late as possible constraints)
- 3. Expected finish constraints?
- 4. Mandatory constraints?
- 5. Start On constraint?
- 6. Contractual constraints?
- 1. Critical Path Definition?
- 2. Critical Path continuity?
- 3. Percent Criticality?
- 4. Critical Path Reasonableness?
- 5. Multiple, simultaneous near-critical path?
- 1. General Checks?Direct Labour and In-Direct labour?Cost Resources?
- 2. Resource Level Schedule?
- 3. Resources?
- 4. Missing Resources?
- 5. Resource congestion?
- 6. Milestone and Summaries with Resources?
Project Scheduler - GPSF - M.C. Dean
2 个月thanks
Expert Delay Analyst & Quantum Consultant
1 年An excellent summary BUT Inclement weather should be added as non-working days to the calendar on affected tasks.