A Program Management Approach: Dispute Avoidance (Part 1)
“Disputes are apt to sour one’s temper and disturb one’s quiet.”
Benjamin Franklin
While contentious and unfavorable in terms of collaboration, formal initiation of dispute proceedings remains a fact of life in the complicated business of construction.?With so much on the line from all stakeholders, including often tremendous risks and benefits, pending the successful completion (and future operation), disputes can often take on an exaggerated form when compared to building industry norms.
An Enlightened Approach to the Resolution of Problems and the Avoidance of Disputes
Construction projects, in general, are very susceptible to disrupted progress and unrestrained costs when problems are not solved as they arise. Unresolved problems escalate to claims and claims escalate to disputes. On a super tall project, this reality is indeed magnified exceptionally.?
The Complexity of Super Tall.?When one focuses on super tall buildings, one is typically looking at the following complexities (at a minimum), all of which can too easily lead to claims and disputes:
Proactive Avoidance of Claims & Disputes
In any dispute, particularly in the building and construction industry, it pays great dividends to not only be aware of potential issues in advance, put also proactive and collaborative when they inevitably arise.?This section explores certain specific techniques for maintaining positive proactivity at the project and business level.
Alternative Dispute Resolution (ADR).?ADR is the acronym for "Alternative Dispute Resolution". The "alternatives" adopted by the construction industry are intended to be alternatives to formal dispute resolution; namely, formal arbitration and litigation in courts. What formal binding arbitration and litigation have in common is the loss of control of the resolution of problems that have escalated to the level of "disputes" by submitting those disputes to determination by a third party—the arbitrator or a judge.?
While some in the industry may be heard to say that they find themselves in arbitration or litigation because that is what their contract requires or at the direction of their legal counsel, the reality is that there is no valid explanation why reasonable members of a construction project team cannot solve problems at the field or at business levels before they escalate into claims and then disputes appearing to require formal dispute resolution.?
领英推荐
ADR covers a broad spectrum of processes that may be availed of by those team members from early intervention up until the time when formal dispute resolution may commence to control the resolution of these matters themselves. Clearly, aside from the obvious benefits of avoiding the costs and distraction of formal dispute resolution, the use of these processes avoids uncertainty as to project costs and scheduled completion for all stakeholders.
Problem Solving & Dispute Resolution Protocols at the Project and Business Level.?The most appropriate place to solve problems that have the potential to escalate into disruptive and expensive impacts on a project is at project level in the first instance, and absent resolution at the project-level, at the higher levels of the stakeholders involved. Simply stated, a problem that is solved at the project or business level never becomes a claim thus the potential for disruption and unnecessary expense is avoided.
Clearly, this concept is simple enough, but experience indicates that it can be more elusive than might appear. There is a tendency in the industry to try to resolve issues in the field however when that cannot be achieved, the tendency is to "preserve" the positions of the parties to a later resolution and "move on" with the work. Because this approach appears to yield to the overwhelming need to maintain project progress it may be thought of as a good "resolution."?Imagine a 100-story project with a problem arising on the 60th floor. "Moving on" is of course attractive, however, in too many circumstances it is not "resolution" at all from many different perspectives.?
The project that operates on the "preserve/move-on" approach sets an ultimate path towards deferred confrontation at an inopportune time for the stakeholders and usually to the detriment of the Employer. Major projects that have operated by this approach have proceeded seemingly well for a period only to have the accumulated volume of unresolved problems (by then elevated to claims and disputes) create a stumbling block to progress and even threaten the very continuation of the project. One need only consider the highly publicized threats of the contractor consortium on the Panama Canal expansion to discontinue the work absent a resolution of their claims and the counter-threat of the Employer to terminate the consortium to realize how accumulated unresolved issues can lead to confrontations that threaten the very viability of a project.?Furthermore, the culture of deferral of the resolution of problems to future resolution can be a self-fulfilling prophecy as problems that could be solved with minimal effort are also thrown into the preserve/move-on category and efforts are not even made to resolve them.
For the Project Manager, the timely resolution of open issues affords a realistic platform to monitor and control project schedule and budgets as contrasted with managing the project based upon outdated and therefore unrealistic schedules and budgets. Holding to artificial finish dates on a CPM schedule due to the lack of resolution of a request for an extension of time deprives the Manager of the ability to manage the project as it could and should. The same applies to budget management.
Similarly, the value of prompt resolution of problems at the project level when they arise cannot be overstated from the perspective of all the other project participants. For example, if the main contractor encounters a situation where it believes it is being told to perform more or different work than it contracted to perform in Area "A" and asks for a resolution of that issue, the prompt resolution of that situation at the project benefits all the parties as follows:
Three “Rungs” of Project Level Dispute Resolution Protocol.?The achievement of resolution of problems at the project level is best accomplished by the creation of a formal protocol that encourages a culture that supports the goal.?Each project stakeholder should designate one person, by name, to have responsibility for the resolution of problems and disputes at the project level. Once selected, the top executives of all stakeholders should meet jointly with the all designated individuals and communicate to them the importance of prompt resolution of problems and disputes and state their support for the principle as well as their expectation that the designated individuals will succeed in achieving this goal. The communication of that support from the top tier of company management is a critical element of this protocol.
The second rung of the dispute resolution protocol is the designation of a higher level person from each participant who will meet with the other designated persons if the field level representatives are unable to achieve a resolution within a stated time; e.g. say, within 5 business days of the date that the issue was raised. The protocol will state how many days this second rung has to resolve the matter. Those people designated at this level should meet with their counterparts and develop an understanding of and appreciation of each other before the process actually commences. The existence of a personal appreciation of each other leads to successful results.??
The third and final rung is the designation of a senior executive of each project participant who will meet with her counterparts if the lower levels have not achieved resolution within a specified number of days.?
The reality is that most employees wish to be successful in their positions. They do not want their superiors to consider them ineffective. Thus, when a person is designated to have the responsibility to find solutions, repeated failures to do so reflect badly upon that person and his counterparts in the process.?For that reason, this protocol should lead to more resolutions at the lower rungs which is the better resolution in any event.
Later in this chapter alternatives to contentious claims and disputes practices are discussed in the section about "ADR."