PMPv6 Changes Summary
Yasser Auda
Cisco VIP , .:|:.:|:. CCIE#45694 CCSI#34215, CISSP, MSc Computer Networking & Cyber Security
If you preparing for PMPv6 exam, here is a list of notes you should take care of:
1-Read "AGILE PRACTICE GUIDE" book ISBN: 978-1-62825-199-9 since PMP now is completely running with Agile spirit.
2-Time Management Knowledge Area name changed to Schedule Management
3-Human Resources Management Knowledge Area name changed to Resources Management
4-Estimate Activity Resources moved from Time Management to Resources Management
5- Three new process added :
- Manage Project knowledge (executing) process added to Integration Management
- Implement Risk Responses (executing) process added to Risk Management
- Control Resources (monitoring & controlling) process added to Resources Management
6-Nine process renamed
7-Process Close Procurement REMOVED and details of it added to Close Project or Phase process
8-New chapter for the role of project manager has been added (chapter 3)