PMP Practice Exam Question

PMP Practice Exam Question

During a crucial phase of a construction project, you identify a significant risk that could potentially delay the project timeline. As the project manager, how should you determine the most appropriate risk management option?

A) Perform a Qualitative and Quantitative Risk Analysis to assess the impact and probability of the risk, then use a Decision Tree Analysis to compare the cost and benefits of different responses including mitigation, acceptance, transfer, or avoidance.

B) Immediately notify all project stakeholders about the risk and hold a meeting to decide on a course of action based on majority opinion.

C) Delegate the responsibility of managing this risk to the project team member who is most familiar with the area where the risk has been identified.

D) Postpone any decision-making on this risk until there is more information available, focusing on other areas of the project in the meantime.


Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, essential for your exam application. Enroll now for the ultimate exam readiness!


The Best Answer is A.

Let's analyze each option one by one:

A) Best Answer:

  • Qualitative and Quantitative Risk Analysis: This involves evaluating the severity and likelihood of the risk. Qualitative analysis allows for ranking and prioritization of risks based on their potential impact on project objectives, using tools like risk probability and impact matrices. Quantitative analysis further quantifies the risk in terms of potential cost or schedule overruns, often using techniques like Monte Carlo simulation or sensitivity analysis.
  • Decision Tree Analysis: This tool helps in visualizing and making decisions by mapping out different possible outcomes and their associated probabilities and impacts. It enables a clear comparison of the costs (both monetary and in terms of project resources) and benefits (in terms of risk reduction or avoidance) of each risk response strategy.
  • Comprehensive Approach: By combining these analyses, you get a full picture of the risk's impact on the project, allowing for a well-informed decision. This approach ensures that the chosen risk response is aligned with project goals and provides the best balance between cost and benefit.

B) Informing Stakeholders and Majority Decision:

  • While stakeholder engagement is crucial in project management, relying solely on a majority vote for risk response can be problematic. This approach does not guarantee that the decision made will be the most effective, as it might not consider all aspects of the risk.
  • Stakeholder perspectives can be subjective and varied, leading to potential conflicts and decisions that may not be in the best interest of the project's success.

C) Delegation to a Team Member:

  • Delegation can be effective for certain tasks, but when it comes to significant risks, it requires the oversight and experience of the project manager.
  • The team member, despite being familiar with the area of risk, might not have the full perspective or authority to decide on the best course of action for the entire project.
  • This approach could lead to inconsistent risk management practices and overlook the interdependencies of different project areas.

D) Postponing Decision-Making:

  • Delaying decisions on identified risks can lead to escalation of the risk, potentially causing a more significant impact on the project.
  • Proactive risk management is key in project management; it's better to address risks early with a well-thought-out plan rather than reacting to them when they materialize.
  • This approach can be seen as avoiding the problem, which might not always be feasible, especially in cases where the risk has a high probability of occurrence.

Mourad OUANNES

Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation

1 å¹´

A

赞
回复
Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

1 å¹´

Answer is A

赞
回复

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察

其他会员也浏览了