PMP Practice Exam Question
You are managing a project to develop a new software application. The project is in the execution phase, and you have just completed the second iteration of the product. During a review meeting, a key stakeholder expresses concern that the current features do not meet their expectations, which could impact the project's delivery timeline and budget. What should you do next?
A) Continue with the planned iterations, assuming that the stakeholder's concerns will be addressed in the upcoming iterations.
B) Request additional budget and time from the sponsor to incorporate the stakeholder's feedback immediately.
C) Organize a meeting with the stakeholder to understand their concerns and prioritize their feedback in the next iteration.
D) Escalate the issue to senior management to seek guidance on how to proceed.
Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course , featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
Best Answer: C) Organize a meeting with the stakeholder to understand their concerns and prioritize their feedback in the next iteration.
领英推荐
Explanation:
Option C demonstrates proactive stakeholder engagement, which is a critical aspect of project management. By organizing a meeting to understand the stakeholder's concerns, you are acknowledging their importance and ensuring their needs are considered. This approach aligns with the PMBOK? Guide's emphasis on effective communication and stakeholder management.
Given that the project is being developed in iterations (suggesting an agile or iterative approach), it is essential to incorporate feedback regularly to ensure the product meets stakeholder expectations. This choice allows for the adaptive and flexible nature of project management, where changes and enhancements are integrated based on stakeholder feedback and project realities.
By prioritizing the feedback in the next iteration, you avoid unnecessary delays and additional costs that might arise from immediate and unplanned changes. This approach ensures that the project remains agile and responsive without compromising the established timeline and budget constraints.
Why Other Options Are Not the Best:
In summary, Option C is the best choice because it directly addresses the stakeholder's concerns in a manner that is consistent with good project management practices, such as effective stakeholder engagement, adaptive planning, and efficient use of project resources. It ensures that the project remains aligned with stakeholder expectations while maintaining the flexibility and responsiveness characteristic of iterative project methodologies.
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
7 个月Answer is C
Transition Project Manager| Professional Scrum Master (PSM I?)| Business Transitions and Transformation
7 个月C
Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation
7 个月C , Otherwize Ask the PO , to investigate This point with the KEY STAKEHOLDER.