PMP Practice Exam Question

PMP Practice Exam Question

You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables do not fully meet their expectations. What should you do to ensure the project is closed properly?

A) Document the stakeholder feedback, update the lessons learned register, and proceed with the project closure

B) Reopen the project and initiate change requests to address the stakeholders’ concerns before closing

C) Postpone the closure process until all stakeholder expectations are met, regardless of project constraints

D) Close the project as planned and inform the stakeholders that no further changes are possible at this stage


Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer:

A. Document the stakeholder feedback, update the lessons learned register, and proceed with the project closure


Explanation:

Closing a project involves ensuring that all deliverables meet the acceptance criteria established during the planning and execution phases. However, addressing stakeholder feedback at this stage does not necessarily mean reopening the project. Instead, it is essential to document the concerns, capture lessons learned, and formally close the project according to the agreed scope and criteria.

Documenting stakeholder feedback ensures that their concerns are recorded for future reference. Updating the lessons learned register helps the organization identify areas for improvement in future projects, such as better alignment with stakeholder expectations or enhanced communication during project execution. Proceeding with the closure ensures that the project remains within its constraints and avoids unnecessary delays.

Reopening the project to address feedback after the agreed deliverables have been accepted could lead to scope creep, additional costs, and schedule overruns. Postponing closure indefinitely to meet all stakeholder expectations is impractical and can jeopardize the project’s success by extending it beyond agreed boundaries. Closing the project without acknowledging stakeholder feedback might damage relationships and miss valuable insights for future projects.

By balancing the formal closure process with thorough documentation of feedback and lessons learned, the project manager ensures compliance with project management best practices while fostering continuous improvement.


Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

3 周

Answer is A

回复
Leonel Santos

IT Project Manager | MBA | Máster Project Management | Scrum Fundamentals Certified | Telecommunication Engineer

1 个月

Iam Not Clear with the Answer. If the project has been Not Closed why closed with the Stakeholder Claim ? Why Not Postpone the close for a few days, resolve the claim or all the claim and Close the project ?

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team notices that the codebase has become increasingly complex, making it harder to implement new…

    1 条评论

社区洞察

其他会员也浏览了