PMP Practice Exam Question
You are managing a software development project with a budget of $200,000. As of today, you have spent $100,000, but the Earned Value of the work completed is $80,000. Based on this information, which of the following actions should you take to best manage the project's budget?
A) Request additional funding since the project is over budget.
B) Accelerate the remaining work to complete the project faster and reduce future spending.
C) Perform a variance analysis to understand the causes of the cost variance and develop a plan to bring project spending back in line with the budget.
D) Reduce the scope of the project to align with the work completed and the budget spent so far.
Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
Best Answer: C) Perform a variance analysis to understand the causes of the cost variance and develop a plan to bring project spending back in line with the budget.
Explanation:
Performing a variance analysis is a systematic approach to identify the reasons behind the project's current cost variance (CV). CV is calculated as EV - AC, which in this case is $80,000 - $100,000 = -$20,000, indicating that the project is over budget. Understanding the root causes of this variance is essential for developing effective corrective actions.
Variance analysis provides the project manager with detailed insights into the factors contributing to the budget overrun. This could include inefficiencies, inaccurate estimations, increased costs, or scope changes. With this understanding, the project manager can make informed decisions about resource allocation, process adjustments, or other interventions needed to control costs and realign the project with its budget.
Based on the findings from the variance analysis, the project manager can develop a comprehensive plan to address the identified issues. This plan might involve renegotiating contracts, optimizing resource utilization, revising the project schedule, or implementing cost-saving measures. The goal is to mitigate the impact of the cost overrun and prevent further budget deviations.
Why Other Options Are Not the Best:
In summary, Option C is the best choice because it focuses on understanding the root causes of the cost variance through a detailed analysis, enabling the project manager to take targeted and informed actions to address the budget overrun. This approach ensures that corrective measures are based on a thorough understanding of the project's financial performance, leading to more effective and sustainable project budget management.
Key Player—Enterprise Process Quality Management Expert | Fintech Certified. Driving Process Excellence, Digital Transformation & SOP Development. Proficient in Process Re-engineering, Governance, Risk & Compliance (GRC)
11 个月c????
Senior Proposal Strategist - Marketing | Strategic Marketing Content Expert
11 个月Performing a variance analysis to understand the causes of the cost variance is key to managing your project's budget effectively. ??
Automation and Manual Testing | Btech (C.S.E) MBA (I.T) | ISTQB Certified Foundation & Advance | Senior Software Quality Analyst | Ex-Magic Software/Mediology Software/OPPO
11 个月c
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
11 个月Answer is C
Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation
11 个月CV=EV-AC, -20 000 , OVER BUDGET. ANSWER C