PMP Practice Exam Question

PMP Practice Exam Question

You are managing a software development project with a budget of $200,000. As of today, you have spent $100,000, but the Earned Value of the work completed is $80,000. Based on this information, which of the following actions should you take to best manage the project's budget?

A) Request additional funding since the project is over budget.

B) Accelerate the remaining work to complete the project faster and reduce future spending.

C) Perform a variance analysis to understand the causes of the cost variance and develop a plan to bring project spending back in line with the budget.

D) Reduce the scope of the project to align with the work completed and the budget spent so far.


Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer: C) Perform a variance analysis to understand the causes of the cost variance and develop a plan to bring project spending back in line with the budget.

Explanation:

Performing a variance analysis is a systematic approach to identify the reasons behind the project's current cost variance (CV). CV is calculated as EV - AC, which in this case is $80,000 - $100,000 = -$20,000, indicating that the project is over budget. Understanding the root causes of this variance is essential for developing effective corrective actions.

Variance analysis provides the project manager with detailed insights into the factors contributing to the budget overrun. This could include inefficiencies, inaccurate estimations, increased costs, or scope changes. With this understanding, the project manager can make informed decisions about resource allocation, process adjustments, or other interventions needed to control costs and realign the project with its budget.

Based on the findings from the variance analysis, the project manager can develop a comprehensive plan to address the identified issues. This plan might involve renegotiating contracts, optimizing resource utilization, revising the project schedule, or implementing cost-saving measures. The goal is to mitigate the impact of the cost overrun and prevent further budget deviations.

Why Other Options Are Not the Best:

  • Option A (Request additional funding): While requesting additional funds might seem like a straightforward solution to budget overruns, it does not address the underlying issues causing the variance. Without understanding and addressing these root causes, the project may continue to experience cost overruns, making this a potentially short-sighted and unsustainable approach.
  • Option B (Accelerate the remaining work): Accelerating the work to complete the project faster might increase costs in the short term due to overtime, additional resources, or other factors associated with rushed work. Without first conducting a variance analysis, this approach risks exacerbating the project's budget issues rather than resolving them.
  • Option D (Reduce the scope of the project): Reducing the project's scope might bring costs in line with the budget but could compromise the project's objectives and deliverables. This option should be considered carefully and typically as a last resort, as it may not align with stakeholder expectations or project goals. Without a variance analysis, there's a risk of making decisions that could negatively impact the project's value and outcomes.

In summary, Option C is the best choice because it focuses on understanding the root causes of the cost variance through a detailed analysis, enabling the project manager to take targeted and informed actions to address the budget overrun. This approach ensures that corrective measures are based on a thorough understanding of the project's financial performance, leading to more effective and sustainable project budget management.




Razan Alif

Key Player—Enterprise Process Quality Management Expert | Fintech Certified. Driving Process Excellence, Digital Transformation & SOP Development. Proficient in Process Re-engineering, Governance, Risk & Compliance (GRC)

11 个月

c????

回复
Aaron B.

Senior Proposal Strategist - Marketing | Strategic Marketing Content Expert

11 个月

Performing a variance analysis to understand the causes of the cost variance is key to managing your project's budget effectively. ??

Anshul Dewan

Automation and Manual Testing | Btech (C.S.E) MBA (I.T) | ISTQB Certified Foundation & Advance | Senior Software Quality Analyst | Ex-Magic Software/Mediology Software/OPPO

11 个月

c

回复
Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

11 个月

Answer is C

回复
Mourad OUANNES

Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation

11 个月

CV=EV-AC, -20 000 , OVER BUDGET. ANSWER C

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察