PMP Practice Exam Question
As the project manager of an Agile software development project, you notice during the sprint review that the project team has consistently been unable to meet the sprint goals for the past two iterations. Team members express that the sprint durations are too short to accommodate the planned amount of work. What is the most appropriate action for you to take first?
A) Extend the duration of future sprints based on team feedback.
B) Conduct a sprint retrospective to identify root causes and potential improvements.
C) Reprimand the team for poor performance and enforce stricter deadlines.
D) Immediately increase the team size to accelerate work completion.
Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course , featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
Correct Answer: B) Conduct a sprint retrospective to identify root causes and potential improvements.
领英推荐
Explanation
The scenario provided depicts a common challenge in Agile project management: the team is unable to meet the sprint goals repeatedly. This could indicate issues with sprint planning, scope estimation, team dynamics, or other underlying problems affecting team performance. Agile methodologies emphasize continuous improvement, adaptability, and team collaboration to address such issues.
Option Analysis:
Why Option B is the Best Answer: Conducting a sprint retrospective is a foundational practice in Agile methodologies. This action allows the team to:
By choosing to conduct a retrospective, you demonstrate a commitment to Agile principles, fostering a team-oriented, flexible, and reflective approach to project management. This action not only addresses the immediate issue but also cultivates an environment conducive to ongoing improvement, which is critical for maintaining high performance in an Agile setting.
Manager | PMP?| SAFe 6.0 SM| Scrum Master| Servant Leadership| CertifiedScrumMaster ?|ISTQB certified agile tester | Power Steering |Infotainment I ISO26262| ASPICE| Team Coach
5 个月Option B, since in sprint retrospective we need the root cause and find out the reason and work on action plan about to prevent in future.
Planning Manager (Projects) at George Kent Malaysia Berhad
5 个月Qurratuaini Amri This kind of question pun bagus untuk practice. Kat sini banyak soalan yg bagus
Pharmacovigilance Specialist | Medical Affairs | PMP
5 个月Hi Sabri, is the complexity of exam questions the same of yours?
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
5 个月Answer is B
Key Player—Enterprise Process Quality Management, Fintech Certified. Driving Process Excellence, Operational Efficiency, and SOP Development. Specializing in Process Re-engineering, governance and Improvement
5 个月B