PMP Practice Exam Question
While preparing for a critical project task, the project manager discovers that a key piece of equipment needed for the task has not been procured, causing a delay in the schedule. The procurement process will take at least two weeks to complete. What should the project manager have done to avoid this delay?
A) Included the procurement of the equipment in the project’s procurement management plan and tracked its progress.
B) Added a contingency plan in the risk register to handle potential delays in procurement.
C) Logged the delay in the issue log and notified the sponsor immediately.
D) Submitted a change request to adjust the project schedule to accommodate the delay.
Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
领英推荐
Correct Answer: A. Included the procurement of the equipment in the project’s procurement management plan and tracked its progress.
Explanation:
Effective project management requires proactive planning and tracking to prevent unexpected delays. Here’s why the selected option is the best course of action:
By including the procurement in the procurement management plan, the project manager would have ensured that the equipment was available when needed, avoiding the delay altogether.