PMP Practice Exam Question

PMP Practice Exam Question

While preparing for a critical project task, the project manager discovers that a key piece of equipment needed for the task has not been procured, causing a delay in the schedule. The procurement process will take at least two weeks to complete. What should the project manager have done to avoid this delay?

A) Included the procurement of the equipment in the project’s procurement management plan and tracked its progress.

B) Added a contingency plan in the risk register to handle potential delays in procurement.

C) Logged the delay in the issue log and notified the sponsor immediately.

D) Submitted a change request to adjust the project schedule to accommodate the delay.


Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!


Correct Answer: A. Included the procurement of the equipment in the project’s procurement management plan and tracked its progress.


Explanation:

Effective project management requires proactive planning and tracking to prevent unexpected delays. Here’s why the selected option is the best course of action:

  • A. Including the procurement in the procurement management plan ensures that the acquisition of necessary equipment is scheduled and tracked, preventing delays. This proactive step would have allowed the project manager to foresee the need for the equipment and ensure timely procurement.
  • B. Adding a contingency plan to the risk register is a good practice, but it would not prevent the delay in this case. The issue here stems from the lack of planning, not from an unforeseen risk.
  • C. Logging the delay in the issue log is a reactive measure, which helps manage the problem once it occurs but does not prevent it. The project manager should focus on planning ahead to avoid the issue in the first place.
  • D. Submitting a change request to adjust the project schedule is also a reactive step that deals with the consequences of the delay rather than preventing it. Proper planning would have eliminated the need for this.

By including the procurement in the procurement management plan, the project manager would have ensured that the equipment was available when needed, avoiding the delay altogether.


Bungsu Sinabutar

Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New

5 个月

Answer is B

回复

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    In a project, the team identifies a risk that a critical feature may not be fully developed within the sprint due to…

    7 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the planning phase of a project, you identify a potential risk of a critical supplier failing to deliver on…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are in the process of closing a project and have received feedback from key stakeholders that certain deliverables…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a team meeting, a conflict arises between two team members, and one of them becomes visibly upset and starts…

    3 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initial stages of a project, your team agrees on a set of ground rules to guide behavior and communication…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    As a project manager practicing servant leadership, how would you handle a situation where a team member is struggling…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    You are leading a newly formed project team and notice that team members are unsure about their roles and how their…

    4 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project status meeting, two key team members begin arguing about the best approach to complete a task. Their…

    3 条评论
  • Agile Projects: Redefining How We Build the Future

    Agile Projects: Redefining How We Build the Future

    In a world where change reigns supreme, Agile project management emerges as a transformative approach that embraces…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    During a project, the team completes a sprint and delivers a potentially shippable product increment. However, the…

    2 条评论

社区洞察

其他会员也浏览了