PMP Practice Exam Question

PMP Practice Exam Question

Your team is developing a new mobile application. During a sprint review, it was identified that the integration of a third-party payment gateway might not be as straightforward as initially thought, posing a significant risk to the project timeline. As a project manager, what is the most appropriate approach to address this risk?

A) Proceed with the current plan without changes, and deal with any issues as they arise during integration.

B) Conduct a thorough risk analysis and create a detailed risk mitigation plan before proceeding with the integration.

C) Replace the third-party payment gateway with a simpler alternative to avoid integration complexities.

D) Work collaboratively with the team to develop a spike to investigate and resolve the integration complexities.


Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, essential for your exam application. Enroll now for the ultimate exam readiness!


Best Answer: D) Work collaboratively with the team to develop a spike to investigate and resolve the integration complexities.

Explanation:

The correct answer is D because it aligns with Agile principles of collaboration, empirical process control, and iterative problem-solving. In Agile, a 'spike' is a specific type of user story that is used to research, investigate, or explore uncertainties or complex tasks in a project. In this scenario, dedicating time and resources to a spike focused on the payment gateway integration will allow the team to gain a better understanding of the challenges and develop a more informed solution.

Option A, proceeding without changes, ignores the identified risk and goes against the Agile principle of responding to change and continuously adapting the plan based on feedback and new information.

Option B, conducting a thorough risk analysis and creating a detailed mitigation plan, is more aligned with traditional project management approaches. While risk analysis is important in Agile, it is typically done in a more iterative and less formal way, integrated with the development process rather than as a separate extensive planning exercise.

Option C, replacing the payment gateway with a simpler alternative, might seem like a quick solution but may not be feasible or desirable based on the project requirements or stakeholder expectations. This approach could also lead to compromises in functionality or quality.

Option D is the best approach in this context. By using a spike, the team can dedicate a time-boxed period to explore the integration challenges. This approach allows them to experiment, learn, and adapt their approach based on empirical findings, which is at the core of Agile methodologies. Once the spike is completed, the team will be better equipped to handle the integration, having reduced the uncertainty and risk associated with this aspect of the project.

Mourad OUANNES

Formateur PMI-ATP PMP-ACP-CAPM/SAFe6 SPC(SA-SSM-POPM-RTE-SP-LPM-DEVOPS) /ISTQB Fdtion V4-Test Manager /PSM I II -PSPO I-icSM-icPO-icSTD /PRINCE2 V7 Accrédité /ITIL 4 Fondation Accrédité- ITIL CDS -ITIL DPI/DEVOPS Fdation

10 个月

D

回复

要查看或添加评论,请登录

Sabri C.的更多文章

  • PMP Practice Exam Question

    PMP Practice Exam Question

    During the initiation phase of a project, the project manager realizes that team members have different interpretations…

    2 条评论
  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    A project manager is developing the Work Breakdown Structure (WBS) for a product launch project. The project manager…

    1 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    A project manager is leading a project with diverse stakeholders who have varying interests and priorities. Recently…

  • The Importance of Communication in Project Management

    The Importance of Communication in Project Management

    In the world of project management, communication is the backbone that holds a project together, from planning to…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    A project manager is preparing for a project kickoff meeting with the project team and key stakeholders. To make the…

    2 条评论
  • PMP Practice Exam Question

    PMP Practice Exam Question

    A project manager is negotiating a contract with a new supplier for a long-term project. The project has a strict…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    A project manager notices that one of their team members, who typically performs well, has recently become less engaged…

  • PMP Practice Exam Question

    PMP Practice Exam Question

    During a project, a team member reports to the project manager that a critical piece of equipment needed for a task is…

    3 条评论
  • Defining Acceptance Criteria: A Key to Project Success

    Defining Acceptance Criteria: A Key to Project Success

    Clear and effective acceptance criteria are vital in ensuring project deliverables meet the standards expected by…

  • CAPM Practice Exam Question

    CAPM Practice Exam Question

    A project manager is in the process of closing a construction project. The project deliverables have been handed over…

社区洞察