PMP Practice Exam Question
You are managing a software development project. During the execution phase, you realize that a piece of work was missed in the initial planning phase. This work is critical for the project's completion and aligns with the project's scope. What is the FIRST action you should take?
A) Add the work to the project schedule and notify the team.
B) Perform a quality audit to understand why it was missed.
C) Update the project management plan and issue a change request.
D) Inform the stakeholders about the delay and added costs.
Looking for more practice exam questions like this? Enroll in our 42-hour online BEST SELLER PMP Exam Prep course, featuring approximately 1,600 practice questions. By doing so, you can supercharge your PMP Exam preparation and earn 42 Contact Hours, which is essential for your exam application. Enroll now for the ultimate exam readiness!
领英推荐
Best Answer: C) Update the project management plan and issue a change request.
Explanation:
When a piece of work that aligns with the project's original scope is discovered during project execution, the first step is not to immediately add it to the project schedule or to inform stakeholders about potential delays and additional costs. The priority is to formally integrate this new work into the project management plan, ensuring it is reflected accurately in all relevant project documents and plans. This ensures that all project parameters, such as schedule, cost, and quality, are adjusted accordingly to accommodate this change.
The process of updating the project management plan involves:
Option C is the correct choice because it encapsulates the formal process required to manage changes in a project. While informing stakeholders (Option D) and adding the work to the project schedule (Option A) are necessary steps, they come after the formal approval of the change. Performing a quality audit (Option B) might be helpful for internal process improvement but does not address the immediate need to integrate the missed work into the project plan.
This approach aligns with the Project Management Institute's (PMI) best practices for project change management, ensuring that all changes are controlled and documented, minimizing their potential impacts on the project's success.
Project Program Management Specialist Advisor
6 个月I’m going to say B. For the simple fact you have to analyze the work to be able to link it to requirements for the plan. You have to know how the missing work relates to the business case and\ project success criteria for a change request. The artifacts you use or submit are only as good as the information contained. If you as the manager either don’t understand or can not logically show how the missed work leads to project success… I’m not sure how you’re going to convince anyone else. Why would a change request get approved? At that point you run the risk of the work being perceived as scope creep or fluff and it may not be funded.
Upgrade Knowledge for Better Future | Explore More Knowledge and Learn Something New
6 个月Answer is B
Key Player—Enterprise Process Quality Management, Fintech Certified. Driving Process Excellence, Operational Efficiency, and SOP Development. Specializing in Process Re-engineering, governance and Improvement
6 个月C