‘Perhaps the biggest update to come out of the Building Safety Act secondary legislation is the approach to change control’
Building Safety Act Consult
Here to navigate you through the Building Safety Act
Perhaps the biggest update to come from the Building Safety Act secondary legislation that was released in August 2023, is the matter of change control. From the Building Safety Act, we knew that some changes were going to require approval from the Building Safety Regulator (BSR) for works to higher-risk buildings (HRBs), but the secondary legislation provides a lot more detail which suggests that it is going to be far more reaching than previously anticipated.
‘Make no mistake, the secondary legislation regarding change control has the potential to seriously disrupt programmes’.
To begin, the Change Control Plan is now one of the named ‘accompanying documents’ which must be submitted with a building control approval application for an HRB, putting much more scrutiny on the change control process during construction before works even start.
The Change Control Plan must detail:
This plan is required before a spade is even put in the ground. Once an approval has then been granted there are two types of changes on an HRB project:
The scope of the changes that the BSR needs to approve is vast with a strong likelihood that most of the changes that arise on an HRB probably being categorised as a ‘major change’. All of the below are scoped as ‘major changes’ within the secondary legislation:
The secondary legislation details that the timescale for approval by the BSR for a ‘major change’ is now 6 weeks which is a reduction on the timescale that was previously suggested in the Building Safety Act, however works cannot start until the until the change has been approved.
The scope of a ‘notifiable change’ is much smaller with all of the below being categorised as requiring notification to the BSR:
领英推荐
The secondary legislation doesn’t stop there either, it goes on to give a prescriptive list of what must be included in each change control submitted to the BSR for approval:
It is worth noting that the BSR can request to see the change control log which must be accurate and complete at anytime on a HRB project.
Make no mistake, the secondary legislation regarding change control has the potential to seriously disrupt programmes.
Having recently completed a HRB project with over 10,000 changes processed on it, there is no way we would have got near the completion date we achieved had we had to go through BSR approval process.
Without careful planning and a robust process, change has the potential to become resource intensive for HRB projects. The actual management of the change process will be more intense, design teams will feel the resource strain having to potentially provide more information than would typically be provided to complete a change on a project. The luxury of completing ‘hand to mouth’ changes will no longer be available.
‘Without careful planning and a robust process, change has the potential to become resource intensive for HRB projects’
Clients, designers, project managers and contractors all need to get to grips with the incoming regulations regarding change control. Clear processes and a management strategy must be put in place on HRB
projects from the early design stages to avoid change becoming a mammoth task on HRB projects and ultimately impacting on costs and programmes.
Get in touch with us here if you need any support or guidance to tackle this latest challenge on the industry’s journey to safer buildings.