Here is how Tega achieved 17% improvement in scraper efficiency and almost 87% reduction in spillage for an iron ore mine in India.

Here is how Tega achieved 17% improvement in scraper efficiency and almost 87% reduction in spillage for an iron ore mine in India.

Here is how Tega achieved 17% scraper efficiency and almost 87% reduction in spillage for an iron ore mine in India.

Plant -?12 MTPA Iron ore mines

Application - Conveyor No. DPC-1 & DC-3 of 1200mm belt width

Conveyor Portfolio - DPC-1 is the receiving conveyor after the primary crusher & DC-3 is the receiving conveyor after the secondary crusher.

Challenge –

Both the conveyors faced severe spillage issues:

·????24 Tons of material was spilling from each conveyor every month.

·????Unscheduled shutdowns with engagement of manpower for cleaning, requirement of technicians for scraper adjustment & need for identification and replacement of the damaged rollers.

Solution –

Tega experts audited conveyor no DPC-1 and recommended use of technically advanced under the belt metallic blade C2 scrapers replacing the lower efficient scraper of another make.

Results –

The following improvements were observed after the installation of C2 scraper:

·?????????Spillage reduced from 24 Tons/month to 3.6 Tons/month.

·?????????The scraper efficiency improved by nearly 17%.

·??????????Spillage cleaning frequency reduced from twice a week to once every 3 weeks.

·??????????Scraper adjustment frequency changed to once every 45 days from once every 15 days.

·?????????The above improvements resulted into substantial annual savings

Features of product –

The advanced technical features of C2 scraper resulted in a superior performance in comparison to the existing scraper. Some of the features are:

·?????????Contact with the belt surface at positive angle in lieu of 90°.

·?????????Overlapped blade modules.

·?????????Unique axial rotation to take care of the unevenness in the belt.

·?????????Unique spring-loaded blade modules for higher contact with the belt.

Reordering of product –

After the performance of C scraper in DPC-1, customer promptly reordered C series scraper for DC-3 conveyor, which faced similar spillage issues. After successful installation of C2 scraper in DC-3 conveyor, customer got similar results and is extremely satisfied.