Percentage of completion method- What It Means
Paramita Bhattacharya
Providing Project Accounting ? Monthly Bookkeeping ? Certified Payroll ? Work In Progress Schedule For Trade Contractors Who Need Surety Bonding And CPA Reviewed Financials
Percentage of completion is a?method of accounting?for long-term projects in which revenue and expenses are recognized based on the percentage of work they have completed during the period. Under percentage of completion, a contractor recognizes project income and expenses as the project progresses, usually on a monthly basis.
In contrast with percentage of completion, the?completed contract method?is used to recognize project revenue and costs only when the contract is complete. The completed contract method is usually used in the residential sector and on small projects of short duration.
To calculate the percentage of completion for a project, there are three indicators contractors can use. The most common is costs incurred to date, but they can also use units completed or labor hours. We’ll go into more detail about this calculation later.
Once the contractor has determined the percentage of completion for a project, the percent is multiplied by the total expected revenue. The answer is the amount of income that can be recognized on the project to date. This income is recognized on the?income statement?through the?work in progress?report.
The cost-to-cost formula: How to calculate percentage of completion
The most common way to determine a project’s percentage of completion is by comparing estimated and actual project costs, known as the “cost-to-cost” method:??
Percent complete = Total costs to date ÷ total estimated costs
The total percentage of costs that have been incurred is the percentage of completion for the project. This percentage is multiplied by the total contract amount to determine the revenue to recognize during the period.?
Revenue recognized = Percent complete x contract amount
Instead of costs, percentage of completion can also be calculated using units or labor hours, depending on the nature of the business. The important thing to remember is that?contractors must be consistent in how they calculate the percent complete.
The?work in progress report?provides a summary of the information used in the percentage of completion calculation. It includes total revised contract amount, total costs to date, percent complete based on cost, amount billed to date, and the difference between the amount billed and the percent of revenue that can be recognized.
Percentage of completion example
For example, a project that has estimated costs of $100,000 has incurred $50,000 in costs so far. Dividing the costs ($50,000) into total estimated costs ($100,000), you find that the project is 50% complete.?
Percent complete:?$50,000 ÷ $100,000 = 0.5 (50%)
This means the contractor can recognize half of the total revenue for the project. If the contract is for $120,000, the contractor would record revenue of $60,000 for the period, which would be reflected in their income statement.
领英推荐
Revenue recognized:?$120,000 x 50% = $60,000
Risks with the percentage of completion method
The percentage of completion method is an internal accounting process that can differ from the reality on the jobsite. This can present challenges when the revenue and expenses recognized are different from the actual amounts billed or spent on the project. This can create cash flow problems for the contractor if they aren’t careful.?
Overbilling & underbilling
When the amount billed to date is more than the revenue that is recognized by the percentage of completion method, that’s called?overbilling. If a company consistently overbills, they will have trouble covering remaining costs as the project continues.?
Underbilling?is the opposite scenario, when the amount billed to date is less than the recognized revenue.?
These differences in the billing amount are recorded as journal entries in the?general ledger. They increase or decrease the amount of revenue recognized on the income statement and create an asset or a liability on the balance sheet.
These adjustments ensure that the income shown on the income statement is reflective of the percentage of completion method.
Change orders
Project expenses never exactly equal the estimated costs. When using the percentage of completion method, it’s important for contractors to revise their estimates anytime changes occur on the job. This ensures the accuracy of their accounting calculations, and helps to avoid cash flow challenges.?
When?change orders?are included and estimates change as the project goes along, calculating the percentage complete can get complicated. Because income recognition is based on a percent of the revised contract for each project, it’s important that contractors enter change orders into the system as soon as they are approved.
Revenue recognition doesn’t equal payment
Most commercial contractors, both general contractors and subcontractors, use the percentage of completion method to report their income. When most of your projects last at least a few months, it’s the most accurate way to recognize revenue.
Of course,?reporting income means nothing if you aren’t collecting payments. Cash can only flow out of your business if it’s also flowing in. Regardless of the accounting method your construction business is using, it’s important to?take steps to secure your payments on every project.
Using percent complete income recognition requires some specific data that can be difficult to gather if you aren’t using construction accounting software. If your company is looking to transition to percentage of completion revenue recognition, consider changing to a software package that supports it.