Part 5 of 8 – Legitimate claims Vs Cheating

Part 5 of 8 – Legitimate claims Vs Cheating

“Claims” is taboo word in client’s parlance!

One must appreciate that, raising Claims is NOT an act of cheating! Many believe that the contractor is there to rake up some or other condition; interpret some clause of contract; twist the situation; all to raise financial claims. In many contracts this makes client / consultants paranoid, which results in humongous documentation in order to set records & to create a defense mechanism to ward off any such possibility of claims.

We all must understand that there can be legitimate claims in any contract, arising out of many situations. There could be dozens of reasons, in every contract, leading to additional cost claims. Is it wrong for one to request for cost compensation against such reasons?

One such example can be of claims related to time overrun. Many contracts face time overrun, leading to extended period of contract, thereby forcing the contractor to stay put for a longer period, during which the contractor is bound to incur costs towards fixed overheads, cost of idle machinery & other resources. If the time overrun is caused by certain action or inaction by the client, is it not legitimate for contractor to claim for such costs? It’s very rare that the client wholeheartedly accepts delays caused by reasons attributable to them & generously agrees for additional cost claim. There have been incidents wherein the client agrees to delays caused & accepts responsibility for delays however does not agree to cost claim; in some cases, even if agrees for claims, sets it off against the penalties & liquidated damages under some or other reasons.

Many contracts carry a condition which says, the client may approve extension of time of the project however refuse to compensate associated costs. I wonder why! While the extension of time caused by reasons attributable to client, is agreeable to client, then associated costs become a legitimate claim. One must appreciate it.

No contractor enters into an agreement with a predetermined intent to raise claims. No contractor intends to always read between the lines or twist the conditions to raise claims. It’s just that certain obvious situations & justified reasons lead to a claim. Even in case of claims, every contractor has willingness to settle it thru discussions for a fair & reasonable settlement. No contractor wishes to adopt legal means to settle disputes / claims. On the contrary, I have come across a few clients representing the Govt departments, agree to the legitimacy of claims however refuse to admit it officially fearing them to be questioned by Govt Auditors, hence advise contractor to take it to Dispute resolution or Arbitration process, thereby the person in question is relieved of burden & owning responsibility of agreeing to claims. Its quite strange & painful, but true.

You may ask any contractor small or big, about their take on getting retention money released from any client, whether its private entity or Government agency. It’s the toughest task for any contractor. Its usually money forgone. Only if you are lucky, just simply lucky, you may expect the retention money to land in your hand within a reasonable time. In most cases, we follow up, write, attend meetings, discuss with no results in sight. If at all you don’t get tired of follow up, you may expect part of retention money after deductions against “many reasons”, after couple of years post its due release date. Even then contractor feel themselves lucky in such cases!

Reluctance to make a decision & reluctance to own the decision, often lead to many claims lead to a dispute, ultimately to be referred to dispute resolution, wherein under the law of Arbitration, we all end up in National waste of time, money, efforts & involvement of many other entities to resolve dispute, which is completely avoidable.

Be fair! Claims is NOT cheating.


Girish Kapoor

Elan|| Adani realty || Shapoorji Pallonji || Shimizu || Shapoorji pallonji

3 年

Very well written Sir. In Projects where contractors are raising their concern within contracted conditions are "enemies for work" as to clients representatives. Delay in Decisions leads to contractual obligations, all required here is cognitive conversation. ??

Abhinav Parmar MRICS

Project Controls | Cost Management

3 年

++

回复

要查看或添加评论,请登录

Shailendra Ajri的更多文章

  • Part 8 of 8 – Is there a remedy? Are we willing to adopt?

    Part 8 of 8 – Is there a remedy? Are we willing to adopt?

    Part 8 of 8 – Is there a remedy? Are we willing to adopt? The world can be a happy place, if we Trust each other;…

  • Part 7 of 8 – All is well! Really?

    Part 7 of 8 – All is well! Really?

    Part 7 of 8 – All is well! Really? One may wonder, if the contracting business is really as bad as understood from…

    2 条评论
  • Part 6 of 8 – Can contractor defend aggressively? At what cost?

    Part 6 of 8 – Can contractor defend aggressively? At what cost?

    Part 6 of 8 – Can contractor defend aggressively? At what cost? It must now be obvious that the contractor undergoes…

    1 条评论
  • Part 4 of 8 – The onus of performance

    Part 4 of 8 – The onus of performance

    Part 4 of 8 – The onus of performance Almost all contract agreement demand “Performance Guarantee” to be submitted by…

    3 条评论
  • Part 3 of 8 - Contract agreement - Bias, Fear or Arrogance?

    Part 3 of 8 - Contract agreement - Bias, Fear or Arrogance?

    Part 3 of 8 – The Contract Agreement – Bias, Fear Or Arrogance? Some 15-16 years back, we were executing a project in…

    4 条评论
  • Part 2 of 8 - The Trust factor

    Part 2 of 8 - The Trust factor

    Part 2 of 8 - The Trust factor The fundamental of any association is “Trust in each other”. The basic criteria, even to…

    4 条评论
  • The Mindset

    The Mindset

    Part 1 of 8 - The Mindset A Contractor / Contracting agency, simply put, is an agency “hired” or “contracted” to…

    28 条评论

社区洞察

其他会员也浏览了