North Manchester General Hospital redevelopment. Progress update – September 2022
Manchester University NHS Foundation Trust
Together care matters.
We are working hard to transform the North Manchester General Hospital site, delivering your new hospital and healthcare facilities.
Multi-Storey Car Park and Cycle Hub?
The first stage of construction is underway and earthworks are complete.
Piling started as planned in early August, and the piling rigs are on site, marking the first key step in construction of the building foundations.
North View inpatient mental health unit
Demolition work has concluded, and the site has been handed over to Greater Manchester Mental Health NHS Foundation Trust (GMMH) for the construction of North View.
Below are start and finish photographs showing the work completed on site.
Start of demolition & asbestos removal work:
Completion:
Fifteen buildings underwent asbestos surveys and removals where needed, and then sequenced demolition work took place. Materials were kept on site for re-use in the foundations and earthworks for North View (stockpile shown above).
Materials were salvaged for reclamation to minimise impact on landfill.
Start of demolition & asbestos removal works: Boiler house dismantling underway.
Completion:
For more information about the redevelopment of North Manchester General Hospital, please visit: https://mft.nhs.uk/transforming-the-future-at-north-manchester-general-hospital/
Director of Ops at North Manchester General Hospital. Trustee SicKids Registered Charity
2 年Mixed emotions for many of us seeing old buildings come down … but the future is bright for our patients, families and staff in North Manchester and that’s what matters most ??
Director at Murraywood Construction Ltd
2 年Murraywood Construction are pleased to announce their new contract award for the new North Manchester General Hospital Multi-Storey Car Park project. On this project we have been appointed to complete the foundations, drainage, and ducting. We will also be installing the ground floor slab as part of the internal car park preparations, and then completing the slab installations.
IT Support, Build and Deployment Engineer (SCCM & InTune)
2 年Personally I would have kept Limbert House.. Kept it for sentimental values, like a history of how it was then and how it going to luck