We are working hard to transform the North Manchester General Hospital site, delivering your new hospital and healthcare facilities.

Multi-Storey Car Park and Cycle Hub?

The first stage of construction is underway and earthworks are complete.

Piling started as planned in early August, and the piling rigs are on site, marking the first key step in construction of the building foundations.

No alt text provided for this image
No alt text provided for this image

North View inpatient mental health unit

Demolition work has concluded, and the site has been handed over to Greater Manchester Mental Health NHS Foundation Trust (GMMH) for the construction of North View.

Below are start and finish photographs showing the work completed on site.

No alt text provided for this image

Start of demolition & asbestos removal work:

No alt text provided for this image

Completion:

Fifteen buildings underwent asbestos surveys and removals where needed, and then sequenced demolition work took place. Materials were kept on site for re-use in the foundations and earthworks for North View (stockpile shown above).

Materials were salvaged for reclamation to minimise impact on landfill.

No alt text provided for this image

Start of demolition & asbestos removal works: Boiler house dismantling underway.

No alt text provided for this image

Completion:

For more information about the redevelopment of North Manchester General Hospital, please visit: https://mft.nhs.uk/transforming-the-future-at-north-manchester-general-hospital/

Jenny Brown

Director of Ops at North Manchester General Hospital. Trustee SicKids Registered Charity

2 年

Mixed emotions for many of us seeing old buildings come down … but the future is bright for our patients, families and staff in North Manchester and that’s what matters most ??

Billy Murray MCIOB

Director at Murraywood Construction Ltd

2 年

Murraywood Construction are pleased to announce their new contract award for the new North Manchester General Hospital Multi-Storey Car Park project. On this project we have been appointed to complete the foundations, drainage, and ducting. We will also be installing the ground floor slab as part of the internal car park preparations, and then completing the slab installations.

Hassan J.

IT Support, Build and Deployment Engineer (SCCM & InTune)

2 年

Personally I would have kept Limbert House.. Kept it for sentimental values, like a history of how it was then and how it going to luck

要查看或添加评论,请登录

Manchester University NHS Foundation Trust的更多文章

社区洞察

其他会员也浏览了