Need for Notice - Contractor's right for reimbursement of loss and expense
Rajeshkumar Rajendran LLM LLB BE MRICS MCIArb
A senior leader with an impressive background in Commercial, Contracts, & Claims Management, overseeing multimillion-dollar projects. With two decades of experience, the majority gained in Dubai, Qatar & Saudi Arabia.
In FES Ltd v HFD Construction Group Ltd [2024], the Scottish Court of Session addressed a significant issue regarding whether the notification requirements in clauses 4.20 and 4.21 of the Standard Building Contract with Quantities for use in Scotland (SBC/Q/Scot) (2016 Edition) created a condition precedent for a contractor's right to reimbursement of loss and expense. This judgment provides essential guidance for users of SBCC contracts, emphasizing that adherence to notification clauses is crucial for maintaining entitlement to claims.
Contract Overview
FES Limited and HFD Construction Group Ltd entered into a contract for fit-out works on a Glasgow office building, which was based on the SBC/Q/Scot 2016 contract, amended to include certain bespoke clauses. During the works, FES experienced delays, particularly due to COVID-19, and sought additional time and compensation for loss and expense. The contract’s key clauses in dispute were:
When FES submitted its claim, HFD contested it, arguing FES had failed to meet the notification requirements. The adjudicator sided with HFD, deeming the notice provisions a condition precedent. FES appealed, seeking a declaration that clause 4.21’s notice requirements were not a condition precedent for reimbursement under clause 4.20.1.
Court’s Analysis and Decision
The court undertook a detailed examination of the contract’s language and relevant legal principles, ultimately agreeing with the adjudicator’s initial decision.
Implications and Takeaways
The ruling provides critical clarity on the enforceability of notice requirements under the SBC/Q/Scot standard form, setting out clear implications for contractors and contract administrators:
Key Contractual Provisions and Case Background
The contract in question, based on the SBC/Q/Scot 2016 edition, contained clauses 4.20.1 and 4.21 that govern entitlement to claim losses due to delays, provided specific notice requirements are met. In this case, FES failed to provide the required notice under clause 4.21, and the adjudicator determined that this omission barred FES’s claim for loss and expense. FES sought a declarator in court to confirm that the notice requirement was not a condition precedent to their right to reimbursement. The court ultimately held that compliance with clause 4.21 is indeed a condition precedent, reinforcing the principle that procedural obligations must be strictly observed for claims to be maintained.
领英推荐
Cases
1. Lagan Construction v Scot Roads Partnership and Wood v Capita: Textual Interpretation in Professional Contracts
In Lagan Construction v Scot Roads Partnership and Wood v Capita, the courts emphasized a textual approach to contractual interpretation, especially when the contract is professionally drafted. Wood v Capita established that a contract should be interpreted to ascertain the objective meaning of the words chosen, with a focus on both textual and contextual readings. The court in Lagan Construction extended this approach, applying it to construction contracts by noting that professionally drafted contracts warrant close adherence to the language itself, without significant deviation based on subjective interpretations or external concepts like business common sense unless absolutely necessary.
In FES v HFD, Lord Richardson followed this textualist approach, observing that the contract was drafted with clarity by professionals. He noted that interpreting clause 4.20.1 required adherence to its explicit language, which tied the contractor’s right to reimbursement directly to compliance with clause 4.21. He found that the phrase “subject to… compliance with clause 4.21” left little room for an alternative interpretation and concluded that the language clearly created a condition precedent. This aligns with the rulings in Wood v Capita and Lagan Construction, where the courts prioritized precise contract language over inferred intentions or notions of fairness. This approach limits the impact of arguments around business common sense, which were raised by FES but deemed unnecessary by Lord Richardson given the clear language of the contract.
2. Walter Lilly v Mackay and London Borough of Merton v Stanley Hugh Leach: Notification Clauses as Conditions Precedent
Both Walter Lilly v Mackay and London Borough of Merton v Stanley Hugh Leach involved notification clauses similar to those in FES v HFD, where timely notification was required as a condition for claiming loss and expense. In Walter Lilly, the court accepted the notice requirements as a condition precedent, ruling that compliance was mandatory for entitlement. London Borough of Merton similarly found that notification was essential for invoking certain contractual rights, stressing that failure to provide notice effectively precluded claims for loss and expense.
In FES v HFD, Lord Richardson drew from the logic in these cases, particularly in relation to the language used in clause 4.20.1. He noted that interpreting the clause as FES suggested would involve ignoring or altering critical wording, contrary to the approach in Walter Lilly and London Borough of Merton, where the courts accepted that the inclusion of a notification clause established a condition precedent. By affirming that compliance with clause 4.21 was mandatory, Lord Richardson effectively reinforced the view that notice provisions serve a key function in construction contracts, facilitating clear communication of project delays and allowing both parties to address issues in a timely, manageable way.
Critique of the Decision and Implications
Conclusion
The judgment in FES v HFD affirms that compliance with notice provisions in clauses 4.20 and 4.21 is a strict condition precedent to reimbursement for delay-related expenses. By emphasizing the clarity and simplicity of the contract language, the Court of Session reinforces the importance of strictly adhering to notification procedures in construction contracts. This case serves as a reminder for all SBCC contract users to carefully review and meet all procedural requirements for claiming loss and expense.
The Court of Session’s decision in FES v HFD highlights a commitment to strict textual interpretation of contracts in line with Lagan Construction and Wood v Capita, particularly in the construction context where procedural compliance is crucial. By affirming that the notice requirements in clauses 4.20.1 and 4.21 were conditions precedent, the judgment reinforces a clear, standardized approach to construction contract disputes involving notification. It aligns with the outcomes in Walter Lilly and London Borough of Merton, emphasizing the importance of procedural adherence in claiming losses. While this decision promotes contract certainty, it may also prompt contractors to advocate for more balanced terms that consider unforeseen project complexities and avoid disproportionate penalties for procedural lapses.