MS Dynamics 365 Finance, CRM & Supply Chain Integration Project
Here's a comprehensive breakdown of tasks for an MS Dynamics Finance, CRM, and Supply Chain integration, replacing an old legacy system, incorporating data processing, environment upgrades, and a hybrid PRINCE2-Agile approach. The breakdown follows a Stage Gate approach, ensuring structured governance while allowing Agile flexibility.
Project Scope & Objectives
- Replace legacy system with MS Dynamics 365 Finance, CRM & Supply Chain Management (SCM).
- Migrate and cleanse data from legacy systems.
- Upgrade IT infrastructure for optimal performance.
- Implement DevOps practices across multiple environments.
- Ensure a smooth transition to BAU with training and hypercare.
Project Phases & Stage Gates
1. Project Initiation (Stage Gate 1 - Business Case & Planning)
Key Tasks:
? Define project objectives, scope, and expected outcomes.
? Identify key stakeholders and assign project governance roles.
? Develop Business Case, Project Charter, and Initial Budget.
? Conduct feasibility study & gap analysis.
? Establish high-level project timeline & RAID log (Risks, Assumptions, Issues, Dependencies).
? Define Success Criteria & KPIs.
? Initiate vendor selection process if required.
? Define high-level solution architecture.
?? Deliverables:
- Business Case
- Initial Project Plan
- High-Level Requirements
- Stakeholder Matrix
?? Stage Gate Criteria:
- Business case approval
- Budget and resources secured
- Governance model established
2. Discovery & Requirements Gathering (Stage Gate 2 - Scope & Design Sign-off)
Key Tasks:
? Conduct workshops with key stakeholders & SMEs to capture requirements.
? Document current state (As-Is) and target state (To-Be) processes.
? Define and document business rules, workflows, and integration requirements.
? Identify legacy system dependencies.
? Create data mapping document (Legacy vs. Dynamics 365).
? Determine reporting & analytics needs.
? Define non-functional requirements (performance, security, scalability, compliance).
? Confirm Regulatory & Compliance Requirements (ISO 27001, GDPR, SOX, etc.).
?? Deliverables:
- Requirements Document (BRD, FSD)
- Data Mapping Strategy
- Process Workflow Diagrams
?? Stage Gate Criteria:
- Requirements approved
- Solution architecture validated
3. Solution Design & Architecture (Stage Gate 3 - Detailed Design Approval)
Key Tasks:
? Define technical architecture (Cloud, On-Prem, Hybrid).
? Design data migration strategy (ETL, cleansing, transformation).
? Define integration strategy (APIs, middleware, connectors, Azure Data Factory).
? Create detailed system & database design.
? Define role-based access controls (RBAC).
? Develop a sandbox environment for POCs.
? Review third-party integrations (e.g., Power BI, Power Apps, AI-driven automation).
?? Deliverables:
- Detailed Solution Design Document
- Integration & API Specifications
- Data Migration Plan
?? Stage Gate Criteria:
- Approval of detailed design
- Security & compliance validation
4. Environment Setup & Development (Stage Gate 4 - Build Completion)
Environments Used:
- Dev (Development): Coding, configurations, initial testing.
- Test (System Integration Testing - SIT): Component integration testing.
- UAT (User Acceptance Testing): Business validation.
- Pre-Prod: Final checks before production.
- Production: Live system.
Key Tasks:
? Set up Dev, Test, UAT, Pre-Prod, and Prod environments.
? Configure Dynamics 365 modules (Finance, CRM, SCM).
? Develop custom workflows, reports, dashboards.
? Implement security controls & authentication (Azure AD, MFA).
? Develop custom integrations (ERP, third-party apps, APIs, EDI).
? Perform unit testing & peer code reviews.
? Continuous testing via CI/CD pipeline (Azure DevOps).
?? Deliverables:
- Configured Dynamics 365 modules
- CI/CD pipeline
- Code repository in Git
?? Stage Gate Criteria:
- Development complete
- Passed unit & SIT testing
5. Data Migration & Testing (Stage Gate 5 - UAT Completion)
Key Tasks:
? Extract, Transform, Load (ETL) data migration from legacy systems.
? Data Cleansing & Deduplication (Remove obsolete/inconsistent data).
? Conduct mock migrations & verify data integrity.
? System Integration Testing (SIT).
? Performance, Load, and Security Testing.
? Conduct User Acceptance Testing (UAT) with business users.
? Train users & create user guides.
?? Deliverables:
- Data Migration Report
- UAT Sign-off
?? Stage Gate Criteria:
- Successful UAT completion
- Data integrity validated
6. Deployment & Cutover (Stage Gate 6 - Go-Live Approval)
Key Tasks:
? Prepare cutover strategy & rollback plan.
? Perform final data migration & validation.
? Deploy solution in Production environment.
? Execute final regression tests.
? Coordinate Go-Live activities with business & IT teams.
? Provide hypercare support post-launch.
?? Deliverables:
- Go-Live Checklist
- Final Deployment Plan
?? Stage Gate Criteria:
- Final Go-Live approval
- Rollback & contingency plan in place
7. Post-Go-Live Support & Hypercare (Stage Gate 7 - Transition to BAU)
Key Tasks:
? Monitor system performance & error logs.
? Provide 24/7 hypercare support for first 4-6 weeks.
? Collect & resolve post-Go-Live issues.
? Conduct system optimization & fine-tuning.
? Handover system ownership to BAU team.
? Perform final project closure review & lessons learned.
?? Deliverables:
- Hypercare Report
- BAU Handover Plan
?? Stage Gate Criteria:
- Hypercare completed
- Business-as-usual transition confirmed
Governance, Risk Management & Documentation
Throughout the project, implement continuous governance & risk management:
- RAID Log Management (Update & track Risks, Actions, Issues, Dependencies).
- Change Control Board (CCB) for scope changes.
- Regular Steering Committee Meetings (Monthly/Weekly).
- Sprint Planning & Retrospectives (for Agile execution).
Summary
- PRINCE2 Stage Gates ensure controlled project governance.
- Agile methodology allows iterative development & UAT feedback.
- Multi-environment setup supports staged testing & deployment.
- Comprehensive data migration strategy ensures legacy data integrity.
- Cutover & hypercare minimize business disruption.
This approach ensures a successful MS Dynamics 365 migration with minimal risk while delivering maximum business value.