Modification/Variation Clause in Contracts during COVID-19
Even businesses and organisations that have not been required to close by the Government face unprecedented challenges as a result of the COVID-19 pandemic. The immediate focus for many was to work out how they could continue to operate after the introduction of strict social distancing requirements. Attention is now turning to whether businesses and their suppliers, customers and commercial partners can continue to perform their contractual obligations in spite of the fundamentally different situation in which they find themselves and, if not, what consequences flow from that.
These events shine a spotlight on contractual small print and legal concepts that perhaps provoked little thought in more normal times. They may now be critical to business survival.
Many enquiries from our clients focus on whether COVID-19 is a “force majeure” event and on whether a contract has been “frustrated”.
To understand better let us discuss these two clauses:
Force majeure
Most commercial contracts contain a force majeure clause, often buried amongst the so-called boilerplate provisions. The purpose of such a clause is to protect the parties from a breach of contract claim if they are unable to perform their obligations because of an event that is outside their control.
Contrary to common perception, there is no statutory or common law definition of force majeure or a force majeure. The parties to a contract therefore have the freedom to agree what will amount to a force majeure for the purpose of their contract and what the consequences will be if such an event happens. That means there are no generic answers to questions about how force majeure applies – each party must look at the wording of their own contracts to establish how it works in the relevant circumstances.
When reviewing these provisions there are a number of key questions to consider:
1. Is the COVID-19 pandemic a force majeure event?
The sort of unforeseen disruption to lives and businesses that we are now seeing is exactly what one imagines a force majeure clause is designed to respond to. In many cases the pandemic or the restrictions the Government has now advised to limit its spread will fall into a contractual definition of force majeure. However, both the contractual wording and the impact of the relevant circumstances on the parties, including the effect of the most recent Government policies or directions, will need to be scrutinised carefully to determine whether the clause is engaged.
2. What effect must the force majeure event have to trigger the consequences of the clause?
Many contracts specify the level of disruption that the force majeure event must have on the affected party to trigger the relevant consequences under the contract. Some contracts state that the force majeure event must “prevent” the affected party from performing its duties, others that the event must merely “hinder” performance. In both cases the bar is set high. If the contract requires performance to be prevented, that means performance must be legally or physically impossible. It is not enough to show that performance has been made more difficult or that performance is now economically unviable. If the contract requires performance to be “hindered”, that has been held to mean that performance would put the affected party in such a precarious position that it would endanger the business or prevent them from performing contracts with other parties. Some clauses operate where the relevant event “delays” the performance of a party’s duties. This is a lower bar and provides some flexibility if performance remains possible but not at the time required by the contract.
3. What procedural requirements are imposed by the contract?
Many contracts require the party seeking to rely on the force majeure clause to give prompt notice to the other party of the relevant event and the effects it is going to have on them. It is important to bear this in mind, even if the parties are in discussions to try to agree a way forward without invoking the force majeure clause, because the ability to rely on force majeure can be lost if the procedural requirements in the contract are not followed in good time. The party affected by the relevant event may also be required to take steps to minimise or mitigate the impact of the event on its ability to perform.
4. What is the effect of the force majeure clause?
Typically, a force majeure clause will suspend the performance of the affected party’s obligations while the effect of the force majeure event continues. The aim is that, wherever possible, the contract can be resurrected when the event is over and both parties can then perform their obligations as they originally intended. However, some contracts place a time limit on the suspension and may give the non-affected party (and sometimes also the affected party) the right to source goods or services from elsewhere or to terminate the contract if the affected party remains unable to perform its obligations for a specified period.
A force majeure event is unlikely to make it legally or physically impossible for a party to perform some types of contractual obligations, for example an obligation to make payment or the grant of a licence to access land. Other obligations, such as the provision of goods or services, are more likely to be affected. A party whose performance is not made impossible, such as those whose only obligation under the contract is to make payment, will often not be relieved of the obligation to perform, even if the other party’s obligations are suspended. That can feel unjust. However, a force majeure clause is essentially just a means of allocating risk and in some cases that risk will fall on the party not directly affected by the force majeure event.
5. What about costs already incurred or payments made under the contract?
If the force majeure clause is silent on this question then the starting point under the common law is that “costs fall where they lie”. This means that any payments made under the contract or any costs incurred by either of the parties in performing the contract will not be recoverable. That may lead to a result that strongly favours one party or the other. There are two main avenues for mitigating this risk. The first is to assess whether you have insurance such as business interruption or cancellation cover to reimburse you for any losses. The second is to consider the law of frustration.
Frustration
The doctrine of frustration applies where an event that was not foreseen by the parties, and which does not arise as a result of a breach of contract by either of them, makes performance of the contract impossible. The classic example is a contract for the staging of an event at a specified venue when the venue burns down before the event. Frustrating events could also include a change in the law that makes it unlawful for one of the parties to perform their obligations, or something that makes the whole purpose of the contract obsolete.
As with force majeure, frustration requires more than an event that makes performance more difficult or economically less viable. The frustrating event must have made performance impossible or transformed the obligation to perform into something radically different from what was envisaged by the parties when the contract was formed. The party affected by the frustrating event must also be able to show that it took reasonable steps to mitigate the impact of the event on its performance.
On the face of it, therefore, frustration appears to be similar to force majeure. However, the consequences of a contract being frustrated are significantly different from those of a force majeure event:
- If the contract is “frustrated” then the parties are completely released from their contractual obligations. The contract is not merely suspended (which is the usual position as a result of a force majeure) it effectively comes to an end. The courts will therefore not invoke the principle lightly and parties should carefully consider the implications before claiming that a contract has been frustrated.
- The other significant difference compared to force majeure is that if a contract is frustrated costs do not “fall where they lie”. The position can be varied by the terms of the contract and these remedies are not available for all types of contract, but in general:
- - Sums paid under the contract by one party before the frustrating event can be recovered and if money was due to be paid at the time of the event that sum is no longer due.
- - The parties may be able to recover costs they have incurred in performing their contractual obligations prior to the frustrating event. In those circumstances they may be entitled to retain some or all of any payment they have received from the other party to reflect those costs.
- - Where a party has obtained a valuable benefit from the other party’s actions before the frustrating event, the value of the benefit may be recoverable from the benefitting party.
It is important to note that the applicability and effects of frustration can be displaced by the terms of a force majeure clause or other parts of the contract. A carefully drafted force majeure clause that deals with all necessary points, including how costs and losses will be apportioned between the parties, is likely to displace the application of frustration altogether. However, where there are gaps in a force majeure clause the law of frustration may be applied in addition to the terms of the contract.
Modification/Variation Clause to the rescue
As part of their planning for managing the impact of the COVID-19 crisis all businesses should consider carefully whether they or their counterparties will be able to continue to perform their contractual obligations. If performance may be significantly affected it is crucial to review the terms of your contracts so you understand your rights and obligations and to allow you to scenario-plan accordingly. Particularly with long-standing contracting partners, many businesses are trying to agree a mutually acceptable way forward, including varying contractual obligations and sharing the exposure more fairly.